Risk Assessment Guidance & Template

Instructions for Contract Holders:

The information contained in this document, will help understand and assess the HSE Risk of your contract.

Assess and analyse HSE risks

Categorise each contract as Low HSE Risk, Medium HSE Risk or High HSE Risk corresponding to the highest risk inherent in the contract scope as follows:

1. Identify all Hazards associated with activities in the contract work scope, covering but not limited to the following:

·  Nature of the work - work methods, staffing, materials, equipment, tools to be used and associated hazards e.g. lifting, working at heights, transport, etc;

·  Nature of the product or service i.e. is the contractor required to perform an HSE critical activity (such as the design HSE-critical equipment) as opposed to a hazardous activity (such as working at height);

·  Location of the work - vicinity of shops, schools, hospitals, offices, houses; environmentally sensitive locations (beaches, coral reefs, fishing areas, etc), and associated hazards e.g. H2S, asbestos, chemicals and heat;

·  Local constraints;

·  Number of concurrent operations or contractors on site;

·  Potential consequences – environmental harm, injury, illness, asset damage, impact on local societal sensitivities, reputation with Non-Governmental Organisations (NGO) or Governments, etc.

To minimise the assessment effort and to ensure consistency please refer to the relevant hazards encountered in Appendix A- ‘Hazards and Effects Management Process’ guidelines (HEMP).

2. Assess the HSE risk of each Hazard using Appendix B - ‘Risk Assessment Matrix’ (RAM).

3. Document the HSE risk assessment in the table below.

Contract Risk Assessment: (HEMP study)

Please complete the template to help you perform a contract risk assessment. This exercise is not supposed to be an exhaustive or comprehensive assessment as such effort should be directed towards identifying the higher risk activities and their more

Contract Name / Contract Work Scope / Assessed* Risk
(High / Medium/ Low)
Activity / Hazard / Effect
(If hazard was to be realised / released) / Consequence (Severity rating number ) / Likelihood (Frequency -letter) / Risk *Ranking
(letter & Number)
Driving/ Transport / Driving hours, speed, mobile phone use / Road accidents lead to injuries and fatalities. . Also, will lead to LTI. / Catastrophic / Moderate / C5
Use of hand tools / Wrong materials for the job / Injury to people, Figure Cut. . Also, will lead to LTI. / Catastrophic / Moderate / C5
Material handling, Lifting, loading, unloading / Improper lifting of heavy equipment (heavy lifts) / Damage to asset and injuries to people. . Also, will lead to LTI. / Catastrophic / Unlikely / D5
Working at heights / Slips/ trips/ falls / Falling from heights leads to injuries and fatalities. Also, will lead to LTI. / Catastrophic / Unlikely / D5
Entry into Confined Spaces / Release of H2S / Death to people / Catastrophic / Moderate / C5

N.B. For guidance please refer to Appendix A“Hazard and Effects Management Process (HEMP)” and B “Guidance for Using the RAM”

Appendix ‘A’ Hazards and Effects Management Process (HEMP)

To help guide you, we have listed some activities and hazards that, can be considered when determining the contracts risk. This list should only be used as a guide, as it does not include all hazardous activities.

Activity / Hazard
Driving/ Transport / Dust, road condition, weather, 3rd parties, animals/camels, vehicle maintenance/condition, driver competence & fitness, load restraining, driving permit, driving hours, speed, mobile phone use
Material handling, Lifting, loading, unloading / Manual handling, spills, fall of load, crane/ forklift failure, sling failure, air winch failure
Use of hand tools / Home made, wrong for the job, wrong size or type
Storage of tools / Tool racks, stoppers, conditions, securing mechanisms
Use of machines & Equipment / Unsecured objects, earthing, un-authorized personnel, moving/ rotating parts, noise, vibration, hot surface (high operating temperature), slippery surface/ trips, compressed air failure, hydraulic power failure
Waste / Domestic, medical, batteries, drilling, exhaust fumes
Electrical work / Equipment failure, lockout failure, overloading circuit/ cables, incorrect voltage/ frequency, high voltage.
Working at heights / Slips/ trips/ falls, falling objects, condition of ladders, condition and presence of railings, loose gratings
Pressure testing / Release of pressure, release of test fluid, not following manufacturer guidelines, excessive pressure, stored energy, material failure, connection failure, calibration failure
Welding, cutting, grinding / No gas flash back arrester, gas leaks, unsecured cylinders, welding or cutting near flammable fluids, fumes, open flame, arcing, UV light, heat stress, electrical failure
Painting / Exposure to paint, painting at height
Confined spaces / Lack of Air, H2S
Dealing with chemicals / Crude oil & diesel, paints & coatings, oils & greases, solvents, acids, mud chemicals, completion chemicals, cement, cement chemicals, shock cards, storage, shading
Cooking / Sharp objects, manual handling, steam, smoke, boiling water, boiling oil, hot surface, slippery surface/ trips, chemicals, electrical appliances, food contamination, water contamination, flies/ insects, rodents
Accommodation/
desert environment / Fire, smoking, slippery surface, tripping, electrical appliances, flies/insects, spiders, rodents, snakes, scorpions, heat, cold, winds, dust
Gases at surface / Hydrogen sulphide, hydrocarbons
Explosives / Storage (Security, non–segregation of explosives, premature detonation) and transportation (compatibility, shock/stress loading, non–segregation of explosives, premature detonation), gun loading & laying down (e.g. trapped pressure), gun misfire.
Radioactive sources / Radioactive sources, storage and transportation
Well intervention
(in addition to above activities) / Hydrocarbons at surface, high pressure, hydrogen sulphide, ionising radiation, naturally occurring radioactive materials, ignition sources, tubular, drill pipe and BHA handling, elevated objects, working out of direct sight (e.g. in the cellar)
Entry into Confined Spaces / Lack of air, H2S
Moving Equipment under Power Lines / Incorrect voltage /frequency, sparking/ earthing
Etc. / Etc.
“” / “”
“” / “”

Appendix ‘B’ Guidance for Use of the RAM

The starting point for a RAM assessment is an understanding of the Hazard in its context (activity, location etc.), or an understanding of the particular incident being considered.

HSE Risk Assessment Matrix

An assessment consists of the following steps.

Step 1 Identify potential consequences

Identify the consequences that could develop from a release of the Hazard under the prevailing conditions. Ask the question: ‘What could happen if the controls don’t work or they fail?’

For example, the operation of a pump in crude oil service involves the potential for a release of crude oil in the event of a pump seal failure. Some of the consequences that could result are:

a) Leak of crude oil into the drain system and then into the sea.

b) Ignition of the crude oil resulting in a small fire around the pump.

c) Inadequate fire fighting and escalation of the fire to the point where other process equipment fails and a major fire and explosion occurs.

Step 2 Estimate the Severity of each potential Consequence

For each of the identified consequences assess the Severity (0 - 5) in the four Consequence categories - people, assets, environment and reputation (PAER).

In the crude oil pump example above, for the consequence in which crude oil leaks from the pump seal and flows through the drain system into the sea, there could be impacts in 3 Consequence categories - asset, environment and reputation.

Step 3 Estimate the Likelihood

For each of the potential consequences make an estimate of the Likelihood of the Consequence in terms of the Likelihood levels A to E. The Likelihood level should be judged from past experience, by asking the question: ‘How often in the past has a hazard release resulted in a Consequence similar to the one that we are considering?’ The approach is one of applying history to predict the future.

The estimate of Likelihood should be based on the Likelihood of the particular Consequence under consideration, not on the Likelihood of the Hazard being realised or incident occurring. In the example above an estimate should be made of the likelihood of the crude oil pump seal leak resulting in oil into the sea, not the likelihood that the pump seal will leak.

Step 4 Estimate the risk rating

For each potential Consequence determine the risk rating for each of the applicable PAER categories in terms of the product of the Consequence Severity and the Likelihood. The risk ratings (up to 4 for each potential Consequence) can be plotted on the matrix to provide a visual representation of the risk profile of the hazard release scenario under consideration.

contract risk assessment form

The Contract risk assessment should categorise each contract as Low, Medium or High HSE Risk corresponding to the highest risk inherent in the contract scope. This process should be executed by the by the Contract Holder with contributions from the HSE Advisor, SCM/C&P, and the Contract User/Company Site Representative based on any Risk Assessment previously done.

Date: / 13TH Feb, 2010 / Project / Place: / KMW-WF & NM-G (NIMR)
Contract No: / C311033 / Contract Holder: / OSE/2N
Contract / Activity:
Contract Mode / 1 / 2 / 3
Risk Category: / Low / Medium / High
Evaluation Team: / HSSE: / scm: / Contract User:
RAM: / severity: / Likelihood: / target:

1.0  Comment

Contract Scope:
The scope of this Contract includes, Engineering, Construction, procurement and comissioning activities. Design for facalilities is based on High Risk Sour (6000 ppm). This project is planned to be awraded by Sep, 2010 and onstream planned date is June, 2013.
On plot scope includes (at NRPS):
·  Installation of a new Tank
·  Installation of new Booster Pumps
·  Installation of new Emulsion Pumps
·  Installation of new water treatment equipments (CPI & DGF).
·  Installation of Contraol Room & Power requirements
Off Plot Scope:
·  Installation of a high pressure piplines (PE lined) from NRPS to Karim West field.
·  Installation of 21 MSV’s in Nimr G fiedl
·  Installation of new production pipeline (PE lined) from Nimr G field to NRPS.

2.0  Risk identification and Assessment

3.0  Hazard

/

4.0  Risk

/

5.0  Consequence

/

6.0  TARGET

/

7.0  RAM

Driving/ Transport / Driving hours, speed, mobile phone use / Road accidents lead to injuries and fatalities. . Also, will lead to LTI. / C5
Use of hand tools / Wrong materials for the job / Injury to people, Figure Cut. . Also, will lead to LTI. / C5
Material handling, Lifting, loading, unloading / Improper lifting of heavy equipment (heavy lifts) / Damage to asset and injuries to people. . Also, will lead to LTI. / D5
Working at heights / Slips/ trips/ falls / Falling from heights leads to injuries and fatalities. Also, will lead to LTI. / D5
Entry into Confined Spaces / Release of H2S / Death to people / C5
Signatures
HSE Advisor / Contract Holder / SCM/C&P / Contract User