Learning Curve Solutions

1. Captain Nemo, the owner of the Suboptimum Underwater Boat Company (SUB), is puzzled. He has a contract of 11 boats and has completed 4 of them. He has observed that his production manager, young Mr. Overick, has been reducing the number of people working on the contract. The first boat, for example, required 225 workers, while 45 fewer workers were required for the second boat. Overick has told them that “This is just the beginning!” and that he will complete the last boat in the current contract with only 100 workers. Overick is banking on the learning curve, but has he gone too far?

SOLUTION:

Number of workers required for second boat = 225 – 45 = 180

The learning rate is: b = 180/225 = 0.80 (80% learning curve)

K = 225 (number of workers needed for the first boat)

n = ln(b)/ln(2) = ln(0.80) / ln(2) = -0.223 / 0.693 = -0.322

Y(x) = Kxn

Y(11) = 225(11)-0.322 = 103.95

Unfortunately, young Mr. Overick has overestimated the learning curve… he will NOT be able to produce the 11th boat with only 100 workers.


2. SUB has produced the first unit of a new line of minisubs at a cost of $500,000 - $200,000 for materials and $300,000 for labor. It has agreed to accept a 10% profit, based on cost, and is willing to contract on the basis of a 70% learning curve. What will be the contract price for three minisubs?

SOLUTION:

K = 300,000 (do not include the cost of materials in the learning curve)

n = ln(b)/ln(2) = ln(0.70) / ln(2) = -0.357 / 0.693 = -0.515

The learning curve is: Y(x) = Kxn

Labor cost for second sub: Y(2) = 300,000(2)-0.515 = 209,938

Labor cost for third sub: Y(3) = 300,000(3)-0.515 = 170,374

Total cost for 3 subs:

Sub #1 200,000 + 300,000 = 500,000 (material + labor)

Sub #2 200,000 + 209,938 = 409,938

Sub #3 200,000 + 170,374 = 370,374

------------

1,280,312

With a 10% profit margin: 1,280,312(1.10) = 1,408,343

The contract price for three subs should be $1,408,343.


3. A job applicant is being tested for an assembly line position. Management feels that steady-state times are reached after 1,000 performances. Regular assembly line workers are expected to perform the task within 4 minutes. If the job applicant performed the first test operation in 10 minutes and the second in 9 minutes, should this applicant be hired?

SOLUTION:

Time needed for the first test operation: K = 10

The learning rate is: b = 9/10 = 0.90

n = ln(0.90)/ln(2) = -0.105 / 0.693 = -0.152

The learning curve is: Y(x) = Kxn

Amount of time needed for the 1000th unit: Y(1000) = 10(1000)-0.152 = 3.5

Yes, this applicant should be hired because once she reaches steady-state (after 1000 operations) she will take 3.5 minutes to perform the operation.