NZQA registered unit standard / 28165 version 1
Page 1 of 5
Title / Coordinate an outage in a complex energy and chemical plant
Level / 5 / Credits / 30
Purpose / This unit standard is for experienced people working as supervisors of boiler and energy and chemical process operators or advanced technical personnel.
People credited with this unit standard are able to: contribute to the plan for the outage; coordinate the operational shutdown and plant isolation; coordinate operational components during the execution of the outage plan; coordinate the commissioning and testing of equipment and plant; coordinate the plant handover and start-up; contribute to the outage debriefing; and evaluate own performance in coordinating operational components of the outage plan, in a complex energy and chemical plant.
Classification / Energy and Chemical Plant > Operation of Energy and Chemical Plant
Available grade / Achieved

Explanatory notes

1  Assessment conditions

All assessment must be carried out at an energy or chemical site.

2  Definitions

Complex energy and chemical plant – a plant with a number of integrated pieces of equipment that collectively provide a product or a range of products to internal and/or external customers.

Energy and chemical plant may be in – petrochemical, agri-nutrient, power generation, dairy processing, meat processing, and wood fibre manufacturing, or other plants that operate with a combination of high temperatures, pressures, steam and/or chemicals in gas, liquid or solid form.

Organisational requirements – documented policies and procedures. These may include: equipment manufacturers’ procedures, plant procedures, suppliers’ instructions, site signage, codes of practice, company health and safety plans, on site briefings, and supervisor’s instructions. This includes all regulatory and legislative obligations that apply to the plant.

Outage – the planned shutdown and maintenance or inspection of equipment and plant and the re-establishment of plant operation.

Outage stakeholders – staff in other parts of the plant that are involved or impacted by the outage, and external suppliers, contractors and customers.

Plant – the operational unit, equipment and/or workplace at which the person is working.

3  Legislation relevant to this unit standard includes but is not limited to – Hazardous Substances and New Organisms Act 1996, Health and Safety in Employment Act 1992, Resource Management Act 1991.

Outcomes and evidence requirements

Outcome 1

Contribute to the plan for the outage in a complex energy and chemical plant.

Evidence requirements

1.1  Operational activities intended to be completed in the outage are identified and sufficient detail for the plan is gathered in accordance with organisational requirements.

Range operational activities may include but are not limited to – shutting down equipment, isolations, housekeeping, equipment preparation, hand over, inspections, de-isolation, re-commissioning, testing, starting up.

1.2  Information relating to the planned operational activities is gathered in accordance with organisational requirements.

Range information may include but is not limited to – activity timeframes, personnel requirements, materials, equipment, activity start conditions, other resources.

1.3  Input into the outage plan is provided in accordance with organisational requirements.

1.4  Liaison with outage stakeholders to confirm operational aspects of the outage plan is completed in accordance with organisational requirements.

1.5 Any conflicts arising in operational activities are identified and resolved in consultation with outage stakeholders.

1.6 Liaison with outage stakeholders is carried out to ensure the development of an achievable outage plan.

1.7 Outage plan is communicated to outage stakeholders in accordance with organisational requirements.

Outcome 2

Coordinate the operational shutdown and plant isolation in a complex energy and chemical plant.

Evidence requirements

2.1  Activities in the shutdown plan are monitored and action is taken to maintain the required progress in accordance with organisational requirements.

2.2 Activities in the isolation plan are monitored and action is taken to ensure the safety of personnel and plant in accordance with organisational requirements.

2.3  Checks are completed to confirm equipment and plant are safe to hand over to relevant work groups.

2.4 Equipment and plant handover procedures are completed in accordance with the shutdown plan and organisational requirements.

2.5 Communication and reporting requirements for the shutdown and isolation plans are completed in accordance with organisational requirements.

Outcome 3

Coordinate operational components during the execution of the outage plan in a complex energy and chemical plant.

Evidence requirements

3.1 Safe work management system requirements for the daily work plans are implemented and monitored to ensure a safe work environment.

3.2 Human and physical resources required for daily work plans are reviewed and action is taken to ensure timely progress against the outage plan.

3.3 Progress of operational components of the outage plan is communicated and reported to outage stakeholders in accordance with organisational requirements.

3.4 An overview of the outage progress is maintained through liaison with outage stakeholders and any amendments to the outage plan are communicated to outage stakeholders.

Outcome 4

Coordinate the commissioning and testing of equipment and plant in a complex energy and chemical plant.

Evidence requirements

4.1 Human and physical resource plans for commissioning and testing are reviewed and action is taken to ensure scheduled activities are completed as planned.

4.2 Safe work management system requirements for the scheduled commissioning and testing are implemented and monitored to ensure a safe work environment.

4.3 Progress of commissioning and testing is communicated and reported to outage stakeholders in accordance with organisational requirements.

Outcome 5

Coordinate the plant handover and start-up in a complex energy and chemical plant.

Evidence requirements

5.1 Completion of the outage work plan is confirmed with outage stakeholders.

5.2 Operational acceptance of equipment is completed in accordance with organisational requirements.

5.3 Activities in the plant de-isolation plan are monitored and action is taken to ensure personnel and plant safety.

5.4 Activities in the pre-start and start-up plan are monitored and action is taken to maintain progress in accordance with organisational requirements.

5.5 Progress of the start-up is communicated and reported to outage stakeholders in accordance with organisational requirements.

Outcome 6

Contribute to the outage debriefing in a complex energy and chemical plant.

Evidence requirements

6.1 Operational personnel, resource and timeframe overruns are analysed to determine the root cause.

6.2 Outcomes of the analysis are communicated to outage stakeholders in accordance with organisational requirements.

6.3 Modifications to the methodology, tasks, activities, personnel, resources, timeframes and safe work management system are recommended to improve future outage planning in accordance with organisational requirements.

Outcome 7

Evaluate own performance in coordinating operational components of the outage plan in a complex energy and chemical plant.

Evidence requirements

7.1 Evaluation of own performance incorporates a balance of positive and negative experiences related to coordinating operational components of the outage plan.

7.2 Own actions and decisions are reviewed to determine the cause of positive and negative experiences.

7.3 Recommendations for improvement are developed and recorded in accordance with organisational requirements.

Planned review date / 31 December 2019

Status information and last date for assessment for superseded versions

Process / Version / Date / Last Date for Assessment /
Registration / 1 / 24 October 2014 / N/A
Consent and Moderation Requirements (CMR) reference / 0079

This CMR can be accessed at http://www.nzqa.govt.nz/framework/search/index.do.

Please note

Providers must be granted consent to assess against standards (accredited) by NZQA, before they can report credits from assessment against unit standards or deliver courses of study leading to that assessment.

Industry Training Organisations must be granted consent to assess against standards by NZQA before they can register credits from assessment against unit standards.

Providers and Industry Training Organisations, which have been granted consent and which are assessing against unit standards must engage with the moderation system that applies to those standards.

Requirements for consent to assess and an outline of the moderation system that applies to this standard are outlined in the Consent and Moderation Requirements (CMR). The CMR also includes useful information about special requirements for organisations wishing to develop education and training programmes, such as minimum qualifications for tutors and assessors, and special resource requirements.

Comments on this unit standard

Please contact the Primary Industry Training Organisation if you wish to suggest changes to the content of this unit standard.

Primary Industry Training Organisation
SSB Code 101558 / Ó New Zealand Qualifications Authority 2014