2018 STIP Tentative Schedule

Task / What / Who / When /
1 / Approve assumptions for 2018 Fund Estimate / CTC / May 17, 2017
2 / Go over ITIP needs with Districts / HQ & Districts / June 19-27
3 / Submit Draft 2016 Fund Estimate to CTC / Caltrans HQ Budgets / June 28, 2017
4 / 2018 STIP Development Statewide kickoff meeting (teleconference) / Caltrans HQ & Dist / July 3-10, 2017
5 / 2018 STIP guidelines workshop / CTC / July 17, 2017
6 / Communicate to HQ Programming all changes to cost, schedule, and scope –Mandatory / Caltrans Districts / July 31, 2017
7 / Submit signed PSRs and Fact Sheets for any new ITIP candidates to HQ Programming / Caltrans Districts / July 31, 2017
8 / Prepare Draft ITIP / Caltrans HQ Programming / July/August 2017
9 / Adopt the 2018 Fund Estimate and STIP Guidelines / CTC / August 16, 2017
10 / Draft ITIP to CalSTA for review / CalSTA / September 2017
11 / Notify CTC of state highway needs. / Caltrans HQ Planning / September 15, 2017
12 / Input ITIP data into CTIPS / Caltrans HQ Programming / September-November 2017
13 / Submit draft ITIP to CTC / Caltrans HQ Programming / By October 15, 2017
14 / North ITIP Hearing / CTC / By October 28, 2017
15 / South ITIP Hearing / CTC / By November 4, 2017
16 / Finalize ITIP and complete accompanying narratives, summaries, attachments, PPR’s etc. Publish and reproduce / Caltrans HQ Programming / November 5 – December 15, 2017
17 / Final ITIP Submitted to the CTC. / Caltrans HQ Programming / December 15, 2017
18 / North STIP Hearing / CTC / January 21, 2017
19 / South STIP Hearing / CTC / January 26, 2017
20 / Release CTC Staff Recommendations / CTC Staff / February 19, 2018
21 / Adopt the 2018 STIP / CTC / March 16-17, 2018

Note: Any due dates that fall on a weekend will be due the weekday prior to that date.

New ITEMS