2013 - 2014 CONSTRUCTION ENGINEERING SERVICES FOR WISDOT

SOUTHEAST REGION – LOCAL PROGRAM

CONSULTANT PACKAGE SE 60L

Project I.D. #12722-10-70

Highway/Street:Coffee Road

Termini/Location:Calhoun Rd To National Ave

County:Waukesha

Length: 1.32 miles

Project Type:Reconstruction

Urban and/or Rural:Urban & Rural

Traffic Control:Closed to thru traffic

Letting Date:January 14, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $3,000,000 - $3,999,999

Major Items of Work:Roadway items, HMA, Electrical

Complexity Level:High

Restrictions:Holidays, Snakes, Contaminated Soils

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:2-3

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse,Contract Specialist

SE Region Local Program, 2013-14 Packages

CONSULTANT PACKAGE SE 61L

Project I.D. #12722-11-70

Highway/Street:Lincoln Avenue

Termini/Location:Calhoun Rd To CTH O (Moorland Rd)

County:Waukesha

Length: 0.93 miles

Project Type:Reconstruction

Urban and/or Rural:Urban & Rural

Traffic Control:Open to thru traffic

Letting Date:January 14, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $5,000,000 - $7,499,999

Major Items of Work:Roadway items, HMA, Bioswales

Complexity Level:High

Restrictions:Holidays, Contaminated Soils, In-stream Disturbance, Railroad

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:3

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 14 Packages

CONSULTANT PACKAGE SE62L

Project I.D. #12160-10-70

Highway/Street:S 76th Street (CTH U)

Termini/Location:600 Ft N Of W High St-Carter Blvd

County:Milwaukee

Length: 1.975 miles

Project Type:Reconstruction

Urban and/or Rural:Urban

Traffic Control:Open to thru traffic

Letting Date:February 11, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $7,500,000 - $9,999,999

Major Items of Work:Roadway items, Concrete pavement, HMA pavement, Traffic signals, Box culvert extension

Complexity Level:High

Associated Contracts:None

Restrictions:Holidays, Swallows, In-stream Disturbance, Ash Borer

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number:3-4

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 63L

Project I.D. #12370-00-73

Highway/Street:CTH F (Redford Blvd)

Termini/Location:Busse Road To STH 190 (South Ramp)

County:Waukesha

Length: 2.613 miles

Project Type:Recondition

Urban and/or Rural:Urban & Rural

Traffic Control:Open to thru traffic, Staging

Letting Date:February 11, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $3,000,000 - $3,999,999

Major Items of Work:Roadway items, Pavement milling & grinding, Concrete pavement repair, HMA, Traffic signals

Complexity Level:High

Restrictions:Holidays, Contaminated Soils

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:2

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 64L

Project I.D. #12718-00-74

Highway/Street:Summit Avenue

Termini/Location:2nd Street To Thackery Trail

County:Waukesha

Length: 1.08 miles

Project Type:Reconstruction

Urban and/or Rural:Urban

Traffic Control:Some Open to thru traffic, Some Closed to thru traffic, Alternate Route Provided

Letting Date:February 11, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work:Roadway items, HMA, Mill & overlay & reconstruction

Complexity Level:High

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 65L

Project I.D. #12984-39-72

Highway/Street:North 45th Street

Termini/Location:Bridge Over Menomonee Rvr & Approaches

County:Milwaukee

Length: 0.02 miles

Project Type:Bridge Rehab

Urban and/or Rural:Urban

Traffic Control:Closed, Temp Bridge

Letting Date:March 11, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work:Bridge redeck, Approaches

Complexity Level:Medium

Restrictions:Holidays, Railroad coordination, Contaminated soild, Archeolgical monitoring

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 66L

Project I.D. #13849-00-71

Highway/Street:Sheridan Springs Rd

Termini/Location:Bridge Over White River (P-64-0074)

County:Walworth

Length: 0.07 miles

Project Type:Bridge Replacement

Urban and/or Rural:Rural

Traffic Control:Closed to thru traffic

Letting Date:March 11, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:Roadway items, Bridge items, HMA, Slab on prestressed girders

Complexity Level:Medium

Restrictions:Holidays, In-stream disturbance, Wetlands, Swallows

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 67L

Project I.D. #12670-00-71

Highway/Street:Green Tree Road

Termini/Location:River Road To Jean Nicolet Road

County:Milwaukee

Length: 0.64 miles

Project Type:Resurfacing

Urban and/or Rural:Urban & Rural

Traffic Control:Open to thru traffic

Letting Date:April 8, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $100,000 - $249,999

Major Items of Work:Roadway items, ADA ramps

Complexity Level:Low/Medium

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 68L

Project I.D. #12704-00-73

Highway/Street:Ohio Street

Termini/Location:16th St To Washington Ave (STH 20)

County:Racine

Length: 0.38 miles

Project Type:Pavement Replacement

Urban and/or Rural:Urban

Traffic Control:Staging, Road Closed/Detour

Letting Date:April 8, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $1,000,000 - $1,999,999

Major Items of Work:Roadway items, Concrete, Pavement marking, Storm sewer, ADA ramps

Complexity Level:Medium/High

Restrictions:Holidays, Ash borer

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 69L

Project I.D. #12155-03-71

Highway/Street:W. Fond Du Lac Ave (STH 145)

Termini/Location:Intersection With Sherman

County:Milwaukee

Length: 0.10 miles

Project Type:Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to thru traffic

Letting Date:May 13, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $100,000 - $249,999

Major Items of Work:Roadway items, Concrete, Traffic Signals

Complexity Level:Medium

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 70L

Project I.D. #12160-15-70

Highway/Street:S 76th Street

Termini/Location:Intersection With Edgerton & Layton Ave

County:Milwaukee

Length: 0.10 miles

Project Type:Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to thru traffic

Letting Date:May 13, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $500,000 - $749,999

Major Items of Work:Roadway items, Concrete, Traffic Signals

Complexity Level:Medium

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 71L

Project I.D. #12967-16-70

Highway/Street:Pedestrian Countdown Signal Head

Termini/Location:49 Various Intersections

County:Milwaukee

Length: 0.00 miles

Project Type:Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:July 8, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:Countdown pedestrian signal heads

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:None

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 72L

Project I.D. #13853-00-72

Highway/Street:West Lake Drive

Termini/Location:CTH P To Road B

County:Waukesha

Length: 0.966 miles

Project Type:Resurfacing

Urban and/or Rural:Urban & Rural

Traffic Control:Road closed to thru traffic

Letting Date:July 8, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:HMA, Curb & gutter, Pavement marking, Grading, Adjust MH rims

Complexity Level:Low/Medium

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:Yes

Anticipated Number of Support Staff:0-1

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 73L

Project I.D. #12984-08-75

Highway/Street:City Of Milwaukee Various Locations

Termini/Location:10 Local Intersections

County:Milwaukee

Length: 0.00 miles

Project Type:Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:August 12, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $500,000 - $749,999

Major Items of Work:Monotube mast arms, Median nose modifications, Detectable warning fields

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 74L

Project I.D. #12265-17-90

Highway/Street:27th Street

Termini/Location:West Highland Blvd To St Paul Ave

County:Milwaukee

Length: 0.86 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:October 25, 2013

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:Sidewalks, Stamped colored concrete, Crosswalks, Lighting

Complexity Level:Low

Associated Contracts:None

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 75L

Project I.D. #11693-44-70

Highway/Street:Bicycle Lane Installations

Termini/Location:Various Roadways City Of Milwaukee

County:Milwaukee

Length: 20-30 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:January 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:Pavement marking, Signing

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:None

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 76L

Project I.D. #12265-00-93

Highway/Street:Layton Blvd Street Scape

Termini/Location:W Oklahoma Ave To National Ave

County:Milwaukee

Length: 2.35 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:February 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Major Items of Work:Lighting, Colored concrete crosswalks, Decorative trash containers and planters

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 77L

Project I.D. #11693-35-93

Highway/Street:Installation Of Transit Priority

Termini/Location:Express Bus/Trolley Circulator Rtes

County:Milwaukee

Length: 0.00 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:February 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $750,000 - $999,999

Major Items of Work:Detection and Controller Equipment

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 78L

Project I.D. #11693-35-98

Highway/Street:Install Semi-Actuated Operation

Termini/Location:32 Local Intersections Citywide

County:Milwaukee

Length: 0.00 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:March 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $250,000 - $499,999

Project I.D. #21693-35-99

Highway/Street:Install Semi-Actuated Operation

Termini/Location:10 Connecting Highway Intersections

County:Milwaukee

Length: 0.00 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:March 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $100,000 - $249,999

Major Items of Work:Traffic Signal Improvements: Pedestrian pushbuttons, Vehicle detection loops

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:Aggregate sampling and PCCTEC-1

Duties:Construction administration, inspection, materials sampling and testing, and construction surveys.

Check the ‘2013-14’ WisDOT Construction: Statewide Project List’ to see if DBE participation goals

For more information, contact:Sandra Villiesse, Contract Specialist

SE Region, 2013-14 Packages

CONSULTANT PACKAGE SE 79L

Project I.D. #11693-48-91

Highway/Street:Traffic Adaptive Signal System

Termini/Location:22 Signalized Intersections

County:Milwaukee

Length: 0.00 miles

Project Type:LFA - Miscellaneous

Urban and/or Rural:Urban

Traffic Control:Open to Thru Traffic

Letting Date:March 25, 2014

Field Rate Accounting Required:No

Anticipated Construction Cost: $500,000 - $749,999

Major Items of Work:Computer controlled traffic signals

Complexity Level:Low

Restrictions:Holidays

Construction Leader Required:Yes

Construction Support Staff Required:No

Anticipated Number of Support Staff:0

Required Certification:None