EQAG COMMUNICATION SECTION

MONTH & YEAR – June 2006

1. COMMUNICATION AVAILABILITY: -

Communication System Indices / June2006 (%) / June 2005 (%) / Achieved for FY 2006 / Target for the FY 2007
Protection Channels / 99.97 / 99.9
Data channels / 99.98 / 98.0
Voice system / 99.59 / 99.0

The method of calculating the Communication availability index is revised and divided into 3 parts as shown above from the month of October 2005.

Method of calculating Communication availability is changed to individual down time, aggregating the total down time then applying the following formula –

% availability =

Availability Figure / System / Channels affected
Voice System / 99.18 % / Khandi – Thokerwadi PLCC was out for 1 month. Thus the voice (Dialing and express phone) communication between Bhivpuri – Khand – Thokerwadi was disrupted. The P3EO, O3EI, P3EM PCBswere found to be defective. The same were replaced.
2. MAJOR INVESTIGATION & OCCURRENCES: -
Date / Division / Station / OCCURRENCES / INVESTIGATION
22 June 06 / BKC DAS / The BKC DAS failed for 15 stations. The Router port at BPL was found be hanged. The same got resetted of its own at 10. 00 am.
  1. COMMISSIONING / PROJECT ACTIVITIES : -

Date / Division / Description
1. Scada connectivity for Chembur upto Dharavi is connected through CCR network.
04 May 06 / Scada connectivity for Chembur upto Dharavi is connected through CCR network.
2. New Telephone exchanges for the System
04, 05, 06 May 06 / Installation and IP audit for new exchanges at Bhira, Mulshi and Davdi.
10, 11, 12, 13 May 06 / Installation of new exchange at Saki.
17 May 06 / Installation of new exchange at BKC, Mahalaxmi.
3. Fibre Optic connectivity for Ambernath. & Bhivpuri
30 May 06 / Bhivpuri SMS data has been transferred on new Bhivpuri – Khopoli FOX 20 and existing Dharavi – Trombay links.
Party line telephone (hot line) extended from LDD to Bhivpuri on new Bhivpuri – Khopoli FOX 20 links and existing Dharavi – Trombay links.
4. Fibre Optic connectivity for Kalwa
27 - 31 May 06 / The Fiber cable at Tower 77 on Salsette – Kalyan OPGW is rerouted through Kalwa C/R is completed. The 2 nos. FOX 20 equipment has been installed at Kalwa carrier room for establishing new links between Salsette – Kalwa and Kalwa – Kalyan for ABT metering data to Tata LDC and Line protection.
5. Distribution Automation System for Saki, Borivli and Central Mumbai Areas.
May 06 / No further progress.
  1. RETROFITTING JOBS: -

Date / Division / Description
27 May 06 / Kalwa / The FOX 20 panels earlier working between Trombay MW Central Station to LDC has been installed at Kalwa for establishing links between Salsette – Kalwa and Kalwa – Kalyan.
  1. BREAKDOWN MAINTENANCE ACTIVITIES : -

Date / Division / Description
01 June 06 / Versova / The Versova – Malad Fiber Optic link failed. On investigation it was found that the MULDEX PCB had failed. The same was replaced from Kalwa and the link was restored on the same day.
21 June 06 / Khopoli / Khopoli SMS data to LDC not working. The cable between FX U to SIMPACT was found to be broken.
21 June 06 / Ambernath / Ambernath SMS data to LDC not working due to some lightning.
  1. PREVENTIVE MAINTAINANCE ACTIVITIES.

Date / Station / Link / Description
PM completed
PM completed
PM completed
PM completed
PM completed
PM completed
PM completed
PM completed
PM completed
  1. PREVENTIVE MAINTAINANCE ACTIVITIES NOT COMPLETED

MW PM not carried out at Trombay Colony, RCF Chembur and Trombay.
FOP PM to be started.
PLCC PM to be started.
  1. Preventive Maintenance Completion Percentage

Percentage completion of PM for April 2006 – March 2007.
System / April 05-March 06 / Till Last Month / Till end of this month
Fibre Optic / 37.10 % / 0.00 % / 0.00 %
Microwave / 25 % / 80.00 % / 80.00 %
PLCC / 56.25 % / 0.00 % / 0.00 %
Total / 38.30 % / 12.77 % / 12.77 %

9. ADMINISTRATION AND MAN POWER DEVELOPMENT.

Date / Name / Description
NIL

10.COST OF REWORK FOR POOR QUALITY OF RECEIVED MATERIAL / EQUIPMENT.

Modems & adapter received from Secure after repairs were found to be defective & were unusable.