TOWNSHIP PROJECT AT SEC-99, VILLAGE-DHANKOT, GURGAON, HARYANA BY M/s SPARK TOWN PLANNERS PVT. LTD.

(A) COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE LETTER NO. DEH/09/SEIAA/866 DATED 14th JULY, 2009.

S. No. / Conditions / Status of Compliance
PART A - SPECIFIC CONDITIONS: Construction Phase:-
I / A first aid room as proposed in the project report will be provided in both during construction and operation of the project. / Agreed.
First Aid facility had been provided at the site for construction as well as the same is being provided for operation phase also.
II / Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the laborers strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. / Agreed.
Adequate drinking water and sanitary facilities had been provided at the project site for construction workers. The open desiccation by the labors was strictly prohibited.
Left over cement and mortar, cement concrete blocks, aggregates, sand and other inorganic material were recycled and refused as granular subcase layer of pavements.
III / All the topsoil excavated during construction activities should be stored for use in horticulture/ landscape development within the project site. / Agreed.
The top soil (if excavated) during construction activities had been used in horticulture/ landscape developments.
IV / Disposal of muck during construction phase should not create any adverse effect on the neighboring communities and be disposed taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. / Agreed.
Muck generated during construction phase has been disposed off taking the necessary precautions for general safety and health aspects of people.
V / Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. / Agreed.
Construction spoils such as bituminous material and other hazardous materials are not allowed to contaminate water courses and the dump sites for such material are being secured so that they do not leach into the ground water. Hazardous waste generated during construction phase, has been disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board.
VI / The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards. / Agreed.
D.G sets used during construction phase runs on low Sulphur diesel type and had been ensured that it conforms to Environment (Protection) Rules prescribed for air and noise emission standards. Results of Environmental monitoring carried out at the site are enclosed as Annexure I.
VII / The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. / Agreed.
D.G sets has been used only for power back-up of lighting purpose. The quantity of diesel required is very low. So, storage of diesel was not required.
VIII / Ambient noise levels should conform to commercial standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be made to reduce ambient air and noise level during construction phase, so as to conform to the stipulated standards. / Agreed.
Baseline ambient air and noise quality plus incremental load due to construction had been closely monitored. Adequate measures had been adopted to reduce incremental load on ambient air quality and noise level which conform to the stipulated standards. Ambient air quality report and noise monitoring report is enclosed as Annexure I.
IX / Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and amended as on 27th August, 2003. / As the project is plotted development. So it is not required.
X / Ready mixed concrete must be used in building construction. / Agreed.
Ready mixed concrete had been used for the construction purpose.
XI / Storm water control and its re-use as per CGWB and BIS standards for various applications. / Agreed.
For storm water control, rain water harvesting pits was proposed to reduce water load. The plan showing rain water harvesting pits is attached as Annexure II and Photographs of the same are attached as Annexure III.
XII / Water demand during construction should be reduced by use of premixed concrete, curing agents and other best practices referred. / Agreed.
The practices like use of premixed concrete, curing agents etc. had been adopted to reduce the water demand during construction phase.
XIII / Permission from Competent Authority for supply of water shall be obtained prior to construction / operation of the project. / Agreed.
Water demand during construction phase had been met by private water taker. Application has been filed to HUDA for water during operation phase. The Approval copy is attached as Annexure IV.
XIV / Roof should meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material to fulfill requirement. / The project is plotted development which provide plot with services like roads, parking facility, greenery, RWH pits, STP etc required for society. Development of houses is not a part of this project. This point is not applicable for this project.
XV / Opaque wall should meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is inspirational for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. / The project is plotted development which provide plot with services like roads, parking facility, greenery, RWH pits, STP etc required for society. Development of houses is not a part of this project. This point is not applicable for this project.
XVI / The approval of the competent authority shall be obtained for structural safety of the building due to earthquake, adequacy of fire fighting equipments, etc. If any forestland is involved in the proposed site, clearance under Forest Conservation Act shall be taken from the competent Authority. / Not Applicable.
XVII / During construction phase the project proponent will use water brought to the site by tankers from safe or if there are existing bore wells, the PP will get the prior approval from CGWA for construction of the use of ground water for residential purpose. / Agreed.
The water required for construction purpose had been provided through private water tankers.
SPECIFIC CONDITIONS : Operation Phase
I / The STP is installed for the treatment of the sewage generated to the prescribed standards including odour and treated effluent will be recycled to achieve zero discharge. STP should be installed at the farthest place in the project area. / STP of adequate capacity is being installed for treatment of sewage generated from the project that will meet the prescribed standards. The entire treated water will be recycled back and utilized for Horticulture, Cooling of D.G sets, flushing etc. leading to zero discharge. Site plan showing STP location is attached as Annexure V.
II / Separation of the gray and black water should be done by the use of dual plumbing line. Treatment of 100 % gray water by decentralized treatment should be done ensuring that the recirculated water should have BOD maximum 10 pm and the recycled water will be used for flushing, gardening and HVAC makeup and DG set cooling. / Agreed.
Separation of gray and black water will be done by the use of dual plumbing line. Treatment of 100 % gray water by decentralized treatment will be done ensuring that the re-circulated water should have BOD maximum upto 10 mg/l and the recycled water is being used for flushing, horticulture. Dual Plumbing Plan is attached as Annexure VI.
III / For disinfections of the treated waste water ultra violet radiation or Ozonization should be used. / Agreed and will be complied with.
IV / The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry/ insert solid waste should be disposed off to be approved sites for land filling after recovering recyclable material. / Agreed.
Solid waste generated will be properly collected & segregated. Wet garbage will be sent for composting and dry/inert solid waste would be disposed off to the approved sites for land filling after recovering recyclable material.
V / Diesel power generating sets proposed as source of backup power for lifts, common area illumination and for domestic use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DG sets should be in the basement as promised by the project proponent and appropriate stack height as per the CPCB norms. The diesel used for DG sets should be of low sulphur contents (Maximum 0.25%). / Agreed.
Enclosed type DG sets will be used in case of power failure. Adequate stack height will be provided as per CPCB norms. In addition this, DG sets run on low sulphur diesel only. Site plan showing location of DG sets is attached as Annexure VII.
VI / Ambient noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the proposed Commercial Complex. / Agreed.
It will be ensured that Ambient noise level does not exceed the prescribed standards both within and at the boundary of the proposed Commercial Complex. Ambient noise monitoring report is enclosed as Annexure I.
VII / The project proponent should maintain at least 15% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species so as to provide protection against particulars and noise. The open spaces inside the plot should be preferably landscaped and covered with vegetation/grass. / Agreed.
The green cover providing is more than 15% which includes grass coverage and tree plantation with local species so as to provide protection against particulates and noise. The Landscape plan is enclosed as Annexure VIII.
VIII / Weep holes in the compound walls shall be provided to ensure natural drainage of rain water in the catchments area during the monsoon period. / Agreed.
Weep holes in the compound wall is being provided to ensure natural drainage of rain water in the catchments area during monsoon period.
IX / Rain water harvesting for roof run-off and surface run-off, as plan submitted should be implemented. Before recharging the surface run-off, pre-treatment must be done to remove suspended matter, oil and grease. The bore well for rain water recharging should be kept at least 5 mts. above the highest ground water table. / Agreed.
Rain Water Harvesting has been implemented. Suspended matter, oil and grease removed by treatment before recharging with surface run-off. The bore well for recharge has been kept at least 5m above the ground water table. The plan showing RWH pits location and photographs is enclosed as Annexure II & III.
X / The ground water level and its quality should be monitored regularly in consultation with Central Ground water Authority. / Agreed.
No testing is required for Ground water.
XI / There should be no traffic congestion near the entry and exit points from the roads adjoining the proposed project site. Parking should be fully internalized and no public space should be utilized. / Agreed.
Parking will be provided within the individual plots. The traffic circulation plan is enclosed as Annexure IX.
XII / A report on the energy conservation measures conforming to energy conservation norms finalize by Bureau of Energy Efficiency should be prepared incorporating details about building materials & technology; R & U factors etc. and submit to the IA Division of Environment, Haryana in three months time. / Agreed.
Report on energy conservation measure conforming to energy conservation norms finalized by BEE has been submitted Earlier.
XIII / Energy conservation measures like installation of CFLs/TFLs for lighting the areas outside the building should be integral part of the project design and should be properly collected and disposed off/sent for recycling as per the prevailing guidelines/rules of the regulatory authority to avoid mercury contamination. Use of solar panels may be done to the extent possible / Agreed.
Energy conservation measures like CFL are being used in service area such as switching stations, guard room whereas LED is being used in street lightening. Used CFL/LED is being properly collected and disposed of/sent for recycling as per the prevailing rules/guidelines of the regulatory authority. Use of solar panels has been done to the extent possible.
XIV / The solid waste generated should be properly collected and segregated as per the requirement of the MSW Rules, 2000. The wet garbage should be sent for composting and dry/inert solid waste should be disposed off to the approved sites for land filling after recovering recyclable material. / The solid waste generated will be collected and segregated as per the requirement of the MSW (Management and Handling) Rules, 2000. Wet garbage is being sent for compositing and dry / inert waste will be disposed off to the Govt. approved sites for land filling after recovering recyclable material.
XV / The provision of solar water heating system shall be as per the norms specified by HAREDA and shall be made operational in each building block. / Agreed.
XVI / The project will be operationalized only after commissioning of the infrastructure for supply of water by HUDA or with permission of the DC.CGWA for using ground water from the tube well/bore well. / The project proponent has applied to HUDA for water during operation phase. The Approval Copy of same is enclosed as Annexure IV.
XVII / In no case expert as provided by the CGWA, the ground water will be exploited and developed. / Agreed.
PART-B GENERAL CONDITIONS
I / The environmental safeguards contained in the EIA/EMP Reports should be implemented in letter and spirit. / Agreed.
The environmental safeguards contained in the EIA/EMP Reports is being implemented in letter and spirit.
II / Six monthly compliance reports should be submitted to the HSPCB and Regional Office. MOEF, GOI, Northern Region, Chandigarh and a copy to the regulatory Authority of Haryana. / Agreed.
6 monthly compliances are being submitted to the regulatory authorities at every June 1st and December 1st according to EIA notification 2006. Compliances had been submitted to Northern Region, Chandigarh and a copy to the SEIAA, Panchkula, and Haryana. Receiving for the last compliance report is enclosed as Annexure X.
III / The project proponent will sent one copy of the EMP report to Additional Director, Regional Office, MOEF, GOI, Sector 31, Chandigarh and to the Chairman, Haryana State pollution Control Board, Panchkula for their reference. / EIA/EMP and other relevant documents have already been submitted to RO of MoEF&CC earlier.
IV / The SEIAA, Haryana reserves the right to add additional safeguards measures subsequently, if found necessary. Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. / Agreed.
V / All other statutory clearances such as the approvals for storage of diesel from chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest conservation Act 1980 and Wildlife (Protection) Act, 1972, PLPA, 1900 etc. shall be obtained as, applicable by Project proponents from the respective authorities prior to construction of the project. / Agreed.
All statutory clearance applicable to and required for this project will be obtained from respective authorities in due course of time.
VI / These stipulations would be enforced among others under the provisions of water (Prevention and Control of Pollution) Act, 1986, the public Liability (Insurance) Act, 1991, Forest Conservation Act, 1980 and EIA notifications, 2006. / Agreed.
Forest land is not involved in the project site. The NOC from Forest department is enclosed as Annexure XI.
VII / The project proponent will not violate any judicial orders/ pronouncements issued by the Hon’ble Supreme Court/ High courts. / Agreed.
We will abide by all judicial orders/ pronouncements issued by the Hon’ble Supreme Court/ High courts.
VIII / The Project proponent will seek permission of Forest department under forest (Conservation) Act 1980 and PL PA 1900 before the start of construction work, in view of the Hon’ble Punjab and Haryana High Court orders 15.5.09, passed in CWP No. 20134 of 2004 and CWP No. 4758 of 2008. / Agreed and will be complied with.

(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF&CC