AT&T ENGINEERING REQUIREMENT CHANGE NOTIFICATION - ATT-TP-76400-111

TO: ALL AT&T ENGINEERING SUPPLIERS Date: 06/04/2014

EFFECTIVE DATE: 5 days from posted date or as per Supplier’s Contract

Submitter’s Name: Don Mitrano

TP: TP76400 Subject: FPS Downspout Action: Add: Modification: Delete:

Section: 8 Section Title: Cable rack, Auxiliary Framing & Lighting Systems

Subsection: 4 Section Title: Cable Distribution Systems

Subsection: 7 Subsection Title: FDF Panel Diversity (OSP)

Prior to Change:

4.7.5

The Fiber Protection System shall be placed horizontally parallel to within 6 inches, relative to the front or rear of the terminating equipment i.e. FDF or Network Element, depending on which side of the bay the fiber terminates. Each bay in the lineup should have a downspout. Each vertical drop from the rigid downspout going to the bay shall be placed within two inches of the top of the bay.

Post Change:

4.7.5

The Fiber Protection System shall be placed horizontally parallel to within 6 inches, relative to the front or rear of the terminating equipment i.e. FDF or Network Element, depending on which side of the bay the fiber terminates. Each bay in the lineup should have a downspout. Each vertical drop from the rigid downspout going to the bay shall be placed within two inches of the top of the bay.

In the event that a downspout is not practical then the use of a horizontal TEE or horizontal trumpet flare may also be used but the use of the downspout as out lined above is always first choice.

Questions relative to this ERCN should be addressed to Serena Kwong at 510-796-1097

Serena Kwong

Associate Network Process and Quality Manager

Access the TP's on the Extranet Site https://ebiznet.sbc.com/sbcnebs

Concurred

Area Mgr Eng Network Quality
Implementation Eng & Common Systems Date: 06-04-14

(Mike Cassidy)

Principal-Network Design Engineer (Subject Matter) Date: 05-28-14

(Don Mitrano)

Release Approved

Associated Network Process & Quality Manager Date: 06-04-14

(Serena Kwong)