Suggested solutions to the GCC examination

12 June 2009

Question 1

Question 2

2.3

The underground haulages of a mine and some rooms and passages on surface are equipped with 60-W incandescent globes. One of the energy saving drives of the mine is to replace the incandescent globes with compact fluorescent lights (CFL). The cost to change a globe is R15-00 for either and it includes travelling time from globe to globe.

Data:

Quantity of incandescent lights:1 580

Power output of CFL’s11 W

Power factor of CFL0,503

Price per energy unitR0,45/kWh

Price per apparent power unitR22,50/kVA

Lamp life of a CFL6 000 hours

Lamp life of an incandescent lamp1 000 hours

Price of an incandescentR2,45

Price of a CFLR18-00

2.3.1Calculate the cost in replacing the incandescent globes with the CFL’s. [7]

Suggested solution:

Replacement cost:

1 580 (18+15) = R52 140-00

2.3.2What will the impact be on the total electrical account[1]

Suggested solution:

After 100 hours it starts saving electricity despite the elevated kVA costs

2.3.3Propose some feasible ways to save energy on a mine[3]

Suggested solution:

  • Lag steam lines to prevent unnecessary heat loss
  • Lag fridge lines to prevent energy loss
  • Repair all compressed air leaks
  • Apply power factor correction if p.f is not optimal (± 0,9 or better)
  • Switch off compressor during back shift if compressed air is not required
  • Diversify loads to fill valleys and clip peak consumption periods
  • Negotiate better rate with Eskom.
  • Switch off unnecessary lights and airconditioners when not required.
  • Replace incandescent lamps with CFL’s.
  • Optimise plant equipment – replace oversized motors with correctly sized motors.

[20]

Question 3

A mine intends hoisting people up and down a sinking shaft, using a mobile crane. Draw up Code of Practice or procedure, covering the following points:

  • Scope
  • Appointments
  • Responsibilities
  • Design
  • Safety notices
  • Regulatory inspections
  • PPE
  • Maintenance
  • Operational requirements
  • Communication
  • Emergency procedures[20]

Question 6

6.1A used 3-phase, 8-pole, 50-Hz motor was salvaged and is to be considered for a special duty. The following information was obtained after some extensive tests and measurements:

  • Full load slip3%
  • Rotor resistance0,0011 Ω/phase
  • Standstill reactance0,0052 Ω/phase

Find the ratio of maximum to the full load torque and the speed at which maximum torque occurs [10]

Suggested solution:

p = 4 (8 Poles)

f = 50 Hz

s = 3%

Rrotor = 0,0011 Ω/phase

Xo = 0,0052 Ω/phase

When the slip = 3% with R in the circuit, the torque is at maximum.

6.2A 6 600 V, 3-phase induction motor drawing 200 kW at a 0,8 lagging power factor is coupled in parallel with a 6 600V, 3-phase synchronous motor drawing 250 kVA at 0,9 leading power factor.

Calculate the line current and power factor for the installation.[10]

Suggested solution:

Question 7

7.1

An important induction motor with unique insulation, drives a compressor which is essential to production. The compressor is subjected to varying demands. It is thus important to avoid or minimise damage to the motor which has the following particulars:

  • 4 MW, 6,6 kV, 3-phase, 1 480 r/min with forced ventilation.
  • Squirrel cage, star-connected, both ends of each phase winding accessible
  • Locked rotor stall withstand time = 10 s
  • Starting DOL
  • Normal run-up time = 20 s
  • Outboard white metal pedestal bearings with oil rings.

State all the protective devices you would specify for the motor and its switchgear, briefly describing the purpose and function of the devices. [14]

Suggested solution:

  • Sensitive earth-fault protection – to detect any earth leakage through the windings and trip it out before major damage could be caused by a low impedance earth fault.
  • Overcurrent protection – to trip out the motor in the event of unplanned overcurrent conditions. This facility would have to accommodate the 20 second start-up time. This facility will typically be incorporated in the motor protection relay.
  • Motor protection relay that would include:
  • Stall protection in excess of 10 seconds
  • In liaison with the overcurrent protection facility, allow for start-up time of 20 seconds after which it would trip if the current has not subsided to below 100% of running current
  • 3-start per hour lock-out preventing more that 3 starting attempts in a running hour.
  • Undervoltage detection – to trip out the machine, should a power dip arise.
  • Vibration analyser – detecting any vibration on the motor above predetermined vibration levels. This would also have to be able to distinguish between starting-up vibrations and running vibrations.
  • RTD (heat) sensing on the windings in order to monitor the winding temperatures. When rising above predetermined levels (±95 °C, depending on the type of insulation material used) the motor will trip on over temperature and will have to be interlocked to prevent starting efforts before adequate cooling time of the windings.
  • Filtering systems to keep the air inside the motor as clean and dry as possible, should the air be blown through the motor.

7.2

Describe 3 non-destructive tests on the brake rods and -pins of a man-winder. Briefly describe how these tests are done. [6]

Suggested solution:

Dye-pen testing -

X-ray

Magnetic field profile

Question 1 (November 1996)

You have been appointed as the engineer and tasked to increase the capacity of a Koepe winder by improving the winding cycle time. The following data is available:

Rope diameter / 35 mm
Number of ropes / 3
Mass of the rope / 5,448 kg/m
Breaking strength of each rope / 918 kN
Length of ropes / 700 m
Length of wind / 550 m
Nominal drum diameter / 3 m
Sheave mass [is this for the tail end? Or tower end?] / 6,5 t
Mass of skips and attachments [is there more than 1 skip?] / 12 t
Mass of load[is this the payload?] / 10 t
Mass of balance weight / 17 t
Length of balance weight / 4 m
Mass of tail carriage / 5 t
Moment of inertia of tail carriage sheave wheel / 6500 kg.m2
Frictional resistance of skip / 3 kN
Frictional resistance of balance weight / 2 kN
Coefficient of friction between ropes and the sheaves / 0,18

Calculate:

1.1The maximum possible acceleration when raising a fully loaded skip from the loading box.

1.2The factor of safety of the ropes.

Solution

Firstly, mention was made of a ‘drum’, ‘sheave wheel’and a‘tail carriage sheave wheel’.

Does this mean that it is a ground mounted Koepe winder????

Secondly, mention is made of ‘skips and attachments’.

Assumptions:- This is a tower mounted Koepe winder

The drum mentioned is the Friction Drive

The sheave mentioned is the Tail Sheave

Mass of load is actually the mass of the Payload

(not including rope, conveyance,attactments etc.

How many ropes? 2 head ropes and 1 tail rope, or 3head ropes and 3 tail ropes? For this exercise we assume the latter. Now does this mean we have a sheave per rope or is there one sheave with three groves, again we assume the latter for this calculation.

(Please note that this becomes very stressful, as we have made SIX assumptions so far, and this for the already stress candidate to make, is considered unfair. Further a tensioning carriage at the shaft bottom of the shaft is most unusual for South African conditions.)

1.1The maximum possible acceleration when raising a fully loaded skip from the loading box.

To determine T1 (force in rope on the skip side accelerating upwards)

T1 = Fgravity + Facceleration + Ffriction

Fgravity = Mtotal x g = [Mskip & att+ Mrope + Mpayload + ½(Mtail carriage + Mtail sheave)] x g

= [12 000 + (5,448 x 3 x 700) + 10 000 + ½(5 000 + 6 500)] x 9,81

= 39 190,8 x 9,81

= 384 461,748 N = 384,462 kN

Falinear = M x a = [Mskip & att+ Mrope + Mpayload + ½Mtail carriage]x a

= [12 000 + (5,448 x 3 x 700) + 10 000 + ½ x 5 000] x a

= 35 940,8a N

Farotational =½ Itail sheavex a =0,5 x6 500 x a = 1 444,444a N

R²tail sheave1,5²

Fatotal = Falinear + Farotational = 35 940,8a + 1 444,444a = 37 385,244a N

Ffriction = 3 000 N (given)

T1 = Fgravity + Facceleration + Ffriction

= 384 461,748 N + 37 385,244a N + 3 000 N =387 461,78 + 37 385,244a N

To determine T2 (force in rope on the balance weight side accelerating downwards)

T2 = Fgravity - Facceleration - Ffriction

Fgravity = Mtotal x g = [Mbalence weight + Mrope + ½(Mtail carriage + Mtail sheave)] x g

= [17 000 + (5,448 x 3 x 700) + ½(5 000 + 6 500)] x 9,81

= 34 190,8 x 9,81

= 335 411,748 N = 335,412 kN

Falinear = M x a = [Mbalence weight + Mrope + ½Mtail carriage]x a

= [17 000 + (5,448 x 3 x 700) + ½ x 5 000] x a

= 30 940,8a N

Farotational =½ Itail sheavex a =0,5 x6 500 a = 1 444,444a N

R²tail sheave 1,5²

Fatotal = Falinear + Farotational = 30 940,8a + 1 444,444a = 32 385,244a N

Ffriction = 2 000 N (given)

T2 = Fgravity + Facceleration + Ffriction

= 335 411,748 - 32 385,244a N - 2 000 N = 333411,748 - 32 385,244a N

For the maximum acceleration:

T1= eμθ

T2

387 461,78 + 37 385,244a=e0,18 x π

333411,748 - 32 385,244a

387 461,78 + 37 385,244a=1,7603[333 411,748 - 32 385,244a]

387 461,78 + 37 385,244a=586 904,7 - 57 007,7501a

37 385,244a + 57 007,7501a=586 904,7 - 387 461,78

a= 2,113 m/s²

This is reasonable, and hence we would restrict the acceleration not to exceed

say 1.8 m/sec²to ensure that slip will not occur

1.2The factor of safety of the ropes.

FOS =Ultimate force in rope =3 x 918 .

T1 [387 461,78 + 37 385,244a] x 10-3

=3 x 918 .

[387 461,78 + 37 385,244 x 2,113] x 10-3

= 5,9

This is considered acceptable as it is well over the legal requirements for transporting

people. (Again an assumption. Men or mineral?).

Question 2

2.1Discuss the advantages and disadvantages of earthing the neutral conductor of a three-phase system. (6)

Suggested solution

Advantages:

a)The voltages created in this system are limited to phase voltages (line-to-ground)

b)The system eliminates arcing ground faults since it is solidly earthed.

c)Over-voltages due to lighting are discharged to earth.

d)Earthing provides greater safety for persons and equipment since the earth-fault protection relays operate faster.

e)Protective relays in the system may also be used for earth-fault protection, since any fault-to-earth will cause an unbalance in the system.

Disadvantages:

a)The system experiences higher fault currents than in the insulated neutral system.

b)The earth connection must be made at all points thereby increasing the system capital cost. All points from the substation to the equipment must be earthed.

c) Fast isolation is essential to limit the switching voltages.

2.2Discuss the influence on the electrical distribution network if the neutral is earthed in more than one point. (3)

Solution

In a three-phase system earthed at one point, an earth fault in the system causes a large potential to build-up between the earth point and the fault. The resultant fault current is not ‘immediately’ discharged to earth but has to propagate to the earth point before being isolated by the protection system.

So, earthing at multiple points simply limits the earth fault path to very short distances, between the fault and the nearest earth point. The effect is thus quick isolation of the faulty component as soon as possible.

2.3The underground haulage of a mine and some rooms and passages on surface are equipped with 60 W incandescent globes. One of the energy saving drives of the mine is to replace the incandescent globes with compact fluorescent lights (CFL). The cost to change a globe is R15-00 for either and it includes travelling time from globe to globe.

Data:

Quantity of incandescent lights 1 580

Power output of CFL’s 11 W

Power factor of CFL 0,503

Price per energy unit R 0-45/kWh

Price per apparent power unit R 22-50/kVA

Lamp life of a CFL 6 000 hours

Lamp life incandescent 1 000 hours

Price of an incandescent R 2-45

Price of a CFL R 18-00

2.3.1 Calculate the cost in replacing the incandescent globes with the CFL’s

(7)

2.3.2 What will the impact be on the total electrical account? (1)

2.3.3 Propose some feasible ways to save energy on the mine. (3)

Solution

2.3.1 Calculate the cost in replacing the incandescent globes with the CFL’s

Cost to change globes = R 15-00 x 1 580 = R 23 700-00

Cost to by Fluorescents = R 18-00 x 1 580 = R 28 440-00

Cost in replacing globes = Cost to change globes + Cost to by Fluorescents

=R 23 700-00 + R 28 440-00

= R 52 140-00

2.3.2What will the impact be on the total electrical account?

Incandescent globe usage = 60 W x 1 000 hours = 60 kWh

Cost/kWh per bulb = R 0-45 x 60 kWh = R 27-00

Cost/apparent power unit/bulb = 60 VA x R 22-50/kVA = R 1-35

Total cost/bulb = R 27-00 + R 1-35 = R 28-35 over the life of bulb

The cost of the CFL’s = Cost/kWh = 11 W x 6 000 hours = 66 kWh

Cost/kWh = R 0-45 x 66 kWh = R 29-70 (for one)

Cost/apparent power unit = [11 x 10-3/0,503] x R 22-50 = R 0-492/CPL

Total electrical account for incand. bulbs = 1 580 x R28-35

= R 44 793-00 for 1000 hours

Total electrical account for CFL’s = 1 580 x R 30-19 + cost of replacement

= R 47 700-20 + R 52 140-00

= R 99 840-20 for 6 000 hours

CFL cost per 1 000 hours = [R 47 700-20/6] + R 52 140-00

= R 60 090-03

This means there will be a slight increase in the cost of electricity

(R 60 090-03 – R 44 793-20 = R 15 297-03) the cost includes the initial

replacement cost.

There will be increased savings over the life of the CFL.

2.3.3Propose some feasible ways to save energy on the mine.

Suggested solution:

a)Proper insulation of the pipes on the refrigeration circuit.

b)Detect and repair leaks on compressed air systems.

c)Switch off compressor during back shift if compressed air is not required

d)Introduce solar water heating panels for the hostels and change houses as primary heaters to geysers.

e)Insulate geysers and boilers in change houses and hostels with thermal blankets.

f)Control winding times so that no winding should take place during peak times in terms of the supply authorities.

g)Install a wind turbine on the exhaust side of ventilation fans to generate in-house electricity.

h)Install motion sensors in offices to ensure that lights and air-conditioners remain off when there are no persons in offices.

i)Install variable speed drives for varying pumping loads.

j)Introduce strict water control

k)Ensure that most economical use of ventilation air.

l)Electric drilling machines in stopes.

m)Daylight switching of lighting circuits to switch off unnecessary lights

n)Change management in Process Plant wet circuits i.o.w diversify loads to fill valleys and clip peak consumption periods

o)Apply power factor correction if p.f is not optimal (± 0,9 or better)

p)Replace incandescent lamps with CFL’s.

q)Optimise plant equipment – replace oversized motors with correctly sized motors.

Question 3

A mine intends hoisting people up and down a sinking shaft, using a mobile crane. Draw up a Code of Practice or procedure, covering the following points:

Scope, appointments, responsibilities, design, safety notices, regulatory inspections, personal protective equipment, maintenance, operational requirements, communication, emergency procedures.

(20)

Suggested solution

3.1 Scope

Scope will include the hoisting of people via a mobile crane and pre-sink kibbles in a sinking shaft, as well as the hoisting of material and rock.

Permission must be provided by the Engineer to hoist persons with the mobile crane.

(Should this not become a licensed winder?)

3.2 Appointments

The following appointments will be in place:

  • 3.1 Construction Manager for the overall site
  • Site Manager – Mine Captain per shaft
  • 2.13.3.1/2.13.3.6 Engineer per shaft
  • Mechanical and Electrical Foreman per shaft
  • Trained and assessed competent Artisans – 4 Fitters, 4 Electricians, 2 Boilermakers per site, Electricians and Fitters will be on shift.
  • General Foremen per shaft
  • Shift Foremen – 3 per shaft, 1 per shift
  • Appointed Banksman, 3 off, 1 per shift
  • Appointment of trained and assessed competent mobile crane drivers, 4 per shaft, one per shift, 1 standby.

3.3 Responsibilities

The appointed engineer will be responsible for a Hazard Identification and Risk Assessment, and to oversee that the activities associated with the sinking with a mobile crane is conducted in a manner that poses minimum risk to health and safety.

The Mine Captain, General Foreman and Shift foremen will be responsible for the activities associated with sinking the shaft, i.e. the mining activities.

The appointed artisans will be responsible for inspections (pre-use / operational) and the maintenance of plant and equipment.

The mobile crane will be pre-use inspected by the drivers prior to each shift. The drivers will be responsible for the safe operation of the mobile crane.

The suppliers of the mobile crane will be on site at least once a week to do a complete inspection and service of the crane. The suppliers will supply a crane which will be safe for the specific application.

3.4 Design

The Engineer will also ensure that the crane will work within safe load range, given the position of the crane from the centre of the shaft, and also that the crane rope will be able to handle the least favourable load conditions – the falls of rope can be increased to ensure safe working load, given that the rope is long enough to accommodate the depth of the shaft.

The tripod chain slings of the kibble, the drop nose pins, the kibble palm brackets and the kibbles itself are all to be designed to the requirements of the relevant design standards and law regulations.

The two deck stage compartment must be of diameter great enough to allow access through it of the Jumbo Drill Rig, kibbles, 630 Eimco Loaders and all other relevant equipment and materials.

The crane must have on it installed and fully functional:

  • an over wind device (anti two block device)
  • an under wind device which will indicate to the driver that only 3 turns of rope are left on the drum
  • a camera on the rope drum which will provide the driver with a visual of the condition of the rope on the drum
  • overload device which will prevent the driver from overloading the crane

3.5 Safety Notices

The following notices shall be displayed:

  • Maximum permitted persons per kibble.
  • No unauthorised access to the shaft area
  • List of permitted materials
  • Wearing of PPE
  • Signalling Arrangements

The crane is to be barricaded off to prevent other persons from entering the crane area, and vehicles from colliding with the crane.

3.6 Regulatory Inspections

The Engineer shall inspect at least once a week, not exceeding ten days, the crane and all its safety devices and external parts, and at least once a month, not exceeding 45 days the rope of the crane according to the criteria of the MHSA Regulations Chapter 16.

The crane driver shall inspect prior to each shift the entire crane according to a pre-use checklist. The crane driver shall test during each shift the safety devices of the crane when it is safe to do so.

The appointed artisans will be responsible for inspections (pre-use / operational) of the plant and equipment, including the Mobile Crane, Jumbo Drill Rig, Eimco 630 Loaders, Bank Area, The Sub-bank Area, Two Deck Pre-Sink Stage, 5 Dymot Winches, Kibbles, Tipping Area, Hauling Trucks, Electrical Reticulation System, the Compressed Air System, Water Supply System.

3.7 Personal Protective Equipment

The following personal protective equipment shall apply:

  • Safety Goggles
  • Gloves
  • Full body overalls
  • Ear plugs
  • Hard hats (with chin strap)
  • Safety Shoes / Gumboots
  • Full Body Harnesses

3.8 Maintenance

The appointed artisans will be responsible for inspections (pre-use / operational) and the maintenance of plant and equipment, including the Mobile Crane, Jumbo Drill Rig, Eimco 630 Loaders, Bank Area, The Sub-bank Area, Two Deck Pre-Sink Stage, 5 Dymot Winches, Kibbles, Tipping Area, Hauling Trucks, Electrical Reticulation System, the Compressed Air System, Water Supply System.