Student Name: ANYANZO RONALD IP17KYU/11519/J6 KYAMBOGO UNIVERSITY
Month: MONTH 1
Target / Achievements / Challenges / Lessons LearntWEEK 1
- Reconnaissance survey and site visit.
- Official reporting to the site.
- Transportation of formwork from 1st to 2nd floor.
- Erection of kicker formwork for future columns.
- Casting, vibrating and curing of kickers.
- The site was well surveyed
- I successfully reported to site and began work as suggested.
- Formwork to kicker was well made.
- Kicker well casted and vibrated
- Language barrier which affected my communication with others.
- Use of old nails which affected work speed.
- Lack of temporary facilities like clinic to aid first aid.
- Lack full safety gear like hand gloves.
- Kicker should be erected to ease erection of column.
- Curing facilitates gain of full strength to concrete.
WEEK 2
- Bending and fixing of column reinforcement
- Removal of kicker formwork, erection and plumbing of column formwork.
- Casting of columns
- Curing of reinforced columns
- The reinforcement of column was successfully done.
- The formwork for the column and casting was successfully done including curing.
- Few workers which delayed work
- Delay in payment of workers which made the work stunted at some point
- Short struts for supporting formwork which affected plumbing
- Nails used also kept on bending.
- Formwork should be well supported to aid plumbing
- Workers should be paid in time to facilitate work progress
- Questions should be asked by learners to aid learning
- Curing should be often done
WEEK 3
- Un installation of column formwork
- Erection of canopy formwork for 2nd floor.
- Bending and fixing of reinforcements to 2nd floor canopy
- Laying hollow max span blocks in 2nd floor canopy
- Laying conduits and water pipes
- Removal of formwork was well done
- Reinforcements were well bent and fixed
- Max spans were well laid
- Pipes were also well fixed
- Casting was not successfully done in the same week
- Work was also delayed by late coming of workers
- Injury due to nailing
- Segregation of concrete
Care must be taken while removing formwork by use of protective wear.
Column reinforcement must be measured to cater for kicker reinforcement.
WEEK 4
- Casting of canopy to 2nd floor
- Curing of 2nd floor canopy
- Erection of beam formwork to 3rd floor.
- Bending and fixing of beam formwork
- Canopy was well casted.
- It was well cured using water.
- Beam formwork was well erected.
- Reinforcement was well bent and fixed.
- Presence of reinforcements affected the effectiveness of vibration.
- Props were too short and required enough support.
- Some plans were postponed to the other week due to some delays.
- Long poles should be used to support formwork.
- The Timber pieces (crosses) should be at least one meter long.
- Beam formwork to sides should be well supported with struts.