SECTION 10651

OPERABLE PANEL PARTITIONS

This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

PART 1 - GENERAL

1.1RELATED DOCUMENTS

  1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division1 Specification Sections, apply to this Section.

1.2SUMMARY

  1. This Section includes the following:
  2. Manually operated, paired panel partitions.
  3. Related Sections include the following:

1.3DEFINITIONS

  1. NVLAP: National Voluntary Laboratory Accreditation Program.
  2. STC: Sound transmission class.

1.4SYSTEM PERFORMANCE REQUIREMENTS

  1. Acoustical Performance: Provide operable panel partitions tested by a qualified testing agency for the following acoustical properties according to test methods indicated:

If retaining either of two acoustical performance requirement subparagraphs below, indicate ratings in Operable Panel Partition Schedule at end of Part3 or on Drawings.

  1. Sound Transmission Requirements: Operable panel partition assembly tested in a full-scale opening, 14 by 9 feet (4267 by 2743 mm), for laboratory sound transmission loss performance according to ASTME90, determined by ASTME413, and rated for not less than the STC indicated.

1.5SUBMITTALS

  1. Product Data: Material descriptions, construction details, finishes, installation details, and operating instructions for each type of operable panel partition, component, and accessory specified. Include data on acoustical performance, surface-burning characteristics, and durability.

Revise paragraph below to clarify special conditions that deviate from standard installations. Retain optional text if retaining "Delivery, Storage, and Handling" Article.

  1. Shop Drawings: Show location and extent of operable panel partitions. Include plans, elevations, sections, details, attachments to other construction, and accessories. Indicate dimensions; weights; conditions at openings and for storage; and required installation, storage, and operating clearances. Indicate location and installation requirements for hardware and track, and direction of travel. Show blocking to be provided by others. Include the following:
  2. Calculations: Calculate requirements for supporting operable panel partitions and verify capacity of carriers and track components to support loads; indicate deflection limits for partition and adjacent construction.
  3. Setting Drawings: For embedded items and cutouts required in other work, including support beam punching template.
  4. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available for units with factory-applied color finishes.
  5. Include similar Samples of accessories involving color selection.
  6. Product Test Reports: From a qualified testing agency indicating that each operable panel partition complies with requirements, based on comprehensive testing of current products.

1.6QUALITY ASSURANCE

  1. Installer Qualifications: An experienced installer who is certified in writing by the operable panel partition manufacturer as qualified to install the manufacturer's partition systems for work similar in material, design, and extent to that indicated for this Project.

Retain paragraph below if Contractor or manufacturer selects testing agency. Some manufacturers have laboratories accredited by an independent third party, or NVLAP. Revise below to exclude manufacturers' NVLAP-accredited laboratories and to limit testing to only independent testing agencies.

  1. Testing Agency Qualifications: An independent testing laboratory, or an NVLAP-accredited laboratory, with the experience and capability to conduct the testing indicated, as documented according to ASTME548. NVLAP-accredited laboratories must document accreditation, based on a "Certificate of Accreditation" and a "Scope of Accreditation" listing the test methods specified.
  2. Fire-Test-Response Characteristics: Provide operable panel partitions with the following fire-test-response characteristics, as determined by testing identical products per test method indicated below by UL or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify materials with appropriate markings of applicable testing and inspecting agency.
  3. Surface-Burning Characteristics: As follows, per ASTME84:
  4. Flame Spread: 25 or less.
  5. Smoke Developed: 450 or less.

1.7DELIVERY, STORAGE, AND HANDLING

Delete this Article if not critical to suit panel face materials, e.g., for matching pattern or grain.

  1. Protectively package and sequence panels in order for installation. Clearly mark packages and panels with numbering system used on Shop Drawings. Do not use permanent markings on panels.

1.8PROJECT CONDITIONS

  1. Field Measurements: Verify operable panel partition openings and storage arrangements by field measurements before fabrication and indicate measurements on Shop Drawings. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

Delete subparagraph below if not allowed.

  1. Established Dimensions: Where field measurements cannot be made without delaying the Work, establish opening and storage dimensions and proceed with fabricating operable panel partitions without field measurements. Coordinate construction to ensure that actual opening dimensions correspond to established dimensions.

Insert requirements for special warranties here, including applicable standard paragraphs. Not all manufacturers offer warranties. Terms for available warranties vary widely among manufacturers.

PART 2 - PRODUCTS

2.1MANUFACTURERS

Retain this Article if naming either products and manufacturers in Operable Panel Partition Schedule at end of Part3 or if naming manufacturers in this Article. Retain "Products and" in title above if either "Available Products" or "Products" Paragraph is retained below.

  1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

See Editing Instruction No.1 in the Evaluations for cautions about naming products and manufacturers.

  1. Foldoor/Holcomb & Hoke Mfg. Co., Inc.
  2. Hufcor Inc.
  3. Modernfold, Inc.
  4. Panelfold, Inc.

B.Hufcor Model 6903M, STC rating of 49 (basis of design).

2.2MATERIALS

Retain paragraphs below only if materials described are required for assembled products. Correlate content of retained paragraphs with that of Operable Panel Partition Schedule at end of Part3. Consider deleting this Article if products are adequately specified by performance requirements.

  1. Steel Face/Liner Sheets: Tension-leveled steel sheet, not less than 0.0478-inch (1.2-mm (1.5-mm) nominal specified thickness for uncoated steel.

Usually delete all steel thicknesses in paragraph above as tested acoustical performance usually dictates core composition, including steel sheet thickness, if any steel sheet. Retain one value above to suit products selected or to qualify impact resistance of panels.

  1. Gypsum Board: ASTMC36.

Insert requirements in any of three paragraphs below describing fire-retardant-treated, wood-based panel products, if necessary, to suit Project and product and to comply with requirements of authorities having jurisdiction. See Division6 Sections.

  1. Plywood: DOCPS1.
  2. Particleboard: ANSIA208.1.
  3. Medium-Density Fiberboard: ANSIA208.2.

2.3OPERABLE PANEL PARTITIONS

  1. Panel Construction: Provide top reinforcement as required to support panel from suspension components and provide reinforcement for hardware attachment. Fabricate panels with tight hairline joints and concealed fasteners. Fabricate panels so finished in-place partition is rigid; level; plumb; aligned, with tight joints and uniform appearance; and free of bow, warp, twist, deformation, and surface and finish irregularities.

Revise paragraph below if custom-sized panels are required.

  1. Dimensions: Fabricate operable panel partitions, from manufacturer's standard sizes, to form an assembled system of dimensions indicated on Drawings and verified by field measurements.
  2. Operable Panel Partition Characteristics: Comply with requirements indicated in the Operable Panel Partition Schedule at the end of Part3.
  3. Trim: Manufacturer's standard aluminum trim, finished as follows:
  4. Painted, manufacturer's standard neutral color.

Revise below to specify another hardware finish to suit Project.

  1. Hardware: Manufacturer's standard as required to operate operable panel partition and accessories; with decorative, protective finish.

2.4SEALS

  1. General: Provide types of acoustical seals indicated that produce operable panel partitions complying with acoustical performance requirements and the following:
  2. Seals made from materials and profiles that minimize sound leakage.
  3. Seals fitting tight at contact surfaces and sealing continuously between adjacent panels and between operable panel partition perimeter and adjacent surfaces, when operable panel partition is extended, closed, and in place.
  4. Vertical Seals: Deep-nesting, interlocking astragals mounted on each edge of panel, with continuous PVC acoustical seal.

If more than one STC-rated partition is required to suit Project, and, consequently, more than one description of horizontal top and bottom seals is needed, delete both paragraphs below and insert edited text in Operable Panel Partition Schedule at end of Part3.

  1. Horizontal Top Seals: Continuous-contact, extruded-PVC or PVC-faced, mechanical, retractable, constant-force-contact seal exerting uniform constant pressure on track when extended.

Revise paragraph below if continuous-contact seals can meet acoustical performance requirements and suit Project and product. Bottom seals correlate with STC values.

  1. Horizontal Bottom Seals: PVC-faced, mechanical, retractable, constant-force-contact seal exerting uniform constant pressure on floor when extended, ensuring horizontal and vertical sealing and resisting panel movement.
  2. Mechanically Operated: Extension and retraction of bottom seal by operating handle or built-in operating mechanism, with operating range not less than the 2-inch (50-mm) operating clearance between retracted seal and floor finish.

2.5FINISH FACING

  1. General: Provide finish facings that comply with indicated fire-test-response characteristics and that are factory applied to operable panel partitions with appropriate backing, using mildew-resistant nonstaining adhesive as recommended by facing manufacturer's written instructions.

2.6SUSPENSION SYSTEMS

If more than one track is suitable for partition products selected, repeat this Article to suit each product and insert track designations in the Operable Panel Partition Schedule at end of Part3.

Revise paragraph below if track is mounted directly to structural support.

  1. Suspension Tracks: Steel or aluminum with adjustable steel hanger rods for overhead support, designed for type of operation, size, and weight of operable panel partition indicated. Size track to support partition operation and storage without damage to suspension system, operable panel partitions, or adjacent construction. Limit track deflection to no more than 0.10 inch (2.5 mm) between bracket supports. Provide a continuous system of track sections and accessories to accommodate configuration and layout indicated for partition operation and storage.
  2. Panel Guide: Aluminum; finished with factory-applied, decorative, protective finish.

Retain subparagraph above for continuously hinged panels and possibly for paired panels. Retain subparagraph below if required by manufacturer for maximum sound control with some assemblies. Trim also protects overhead surfaces. Indicate trim on Drawings.

  1. Head Closure Trim: As required for acoustical performance; with factory-applied, decorative, protective finish.
  1. Carriers: Trolley system as required for configuration type, size, and weight of partition and for easy operation; with ball-bearing wheels.
  2. Aluminum Finish: Mill finish or manufacturer's standard, factory-applied, decorative finish, unless otherwise indicated.
  3. Steel Finish: Factory-applied, corrosion-resistant, protective coating, unless otherwise indicated.

2.7ACCESSORIES

  1. Storage Pocket Door: Full height at end of partition runs to conceal stacked partition; of same materials, finish, construction, thickness, and acoustical qualities as panels; complete with operating hardware andacoustical seals at soffit, floor, and jambs. Hinges in finish to match other exposed hardware.
  2. Manufacturer's standard method to secure pocket door in closed position.

PART 3 - EXECUTION

3.1EXAMINATION

  1. Examine flooring, structural support, and opening, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of operable panel partitions. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2INSTALLATION

  1. General: Comply with ASTME557, operable panel partition manufacturer's written installation instructions, Drawings, and approved Shop Drawings.
  2. Install operable panel partitions and accessories after other finishing operations, including painting, have been completed.

Retain paragraph below if retaining "Delivery, Storage, and Handling" Article.

  1. Match operable panel partitions for color and pattern by installing panels from marked packages in numbered sequence indicated on Shop Drawings.
  2. Broken, cracked, chipped, deformed, or unmatched panels are not acceptable.

3.3ADJUSTING

  1. Adjust operable panel partitions to operate smoothly, easily, and quietly, free from binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Lubricate hardware and other moving parts..

3.4CLEANING AND PROTECTION

  1. Clean soiled surfaces, fabric facing, metal surfaces, work surfaces, on completing installation of operable panel partitions, to remove dust, loose fibers, fingerprints, adhesives, and other foreign materials according to manufacturer's written instructions.
  2. Provide final protection and maintain conditions, in a manner acceptable to manufacturer and Installer, that ensure operable panel partitions are without damage or deterioration at time of Substantial Completion.
  3. Replace panels that cannot be cleaned and repaired, in a manner approved by Architect, before time of Substantial Completion.

3.5DEMONSTRATION

  1. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain operable panel partitions.
  2. Test and adjust seals, hardware, carriers, tracks and other operable components. Replace damaged or malfunctioning operable components.
  3. Train Owner's maintenance personnel on procedures and schedules for starting and stopping, troubleshooting, servicing, and maintaining equipment and schedules.
  4. Review data in maintenance manuals. Refer to Division1 Section "Contract Closeout."

Delete subparagraph above or below depending on which Section is retained in Division1.

  1. Review data in maintenance manuals. Refer to Division1 Section "Operation and Maintenance Data."

END OF SECTION