SAFETY METHOD STATEMENT
Action /DETAILS
/MS REF No:
Brief description of the work to be undertaken and the location / Carry out planned preventative maintenance Bi-weekly / DSG CAT 13 MAINTENANCESite Address / Client Address / DIXONS STORE STANSTEAD AIRPORT /
DSG Retail Ltd
Maylands Avenue
Hemel Hempstead
HertfordshireHP2 7TG
Tel : 01442 353000
Sequence of work including control
Measures / Before Commencing with any work.
1. Introduce yourself to manager on-site; seek WORK PERMITS from the airport maintenance department / centre management.
2. Establish whereabouts of fire exits, fire extinguishers and fire meeting point.
Evaporator – indoor unit (4 off).
3. Gain access to sales area evaporators utilizing engineers own step ladders.
4. Isolate the power supply.
5. Remove and vacuum off filter media.
6. Clean unit internally using vacuum cleaner and coil cleaner.
7. Clean fascia using rags.
8. Replace filter media.
9. Re-instate power.
10. Record operation / performance using temperature probe.
Controls
11. Check operation of all equipment. Record operation and defects.
Lighting
- Isolate defective circuits.
14. Bag all rubbish.
15. Dispose of correctly. In dedicated waste skip.
Signing off
16. Record any Health and Safety issues, explain fully the contents of reports.
17. Explain operation, defects and outstanding H & S issues to manager.
18. Return all keys.
19. Sign off site and Airport
Identify: Identification & avoidance of hazards. / · Items 3-10 - Falls from heights.
· Item 5-8 - Electric shock.
· Item 5-8, 11-14 - Particulate hazard.
· Item 6 - CoSHH guidelines / assessments.
Control Measures.
Access to place of work. / · 3-9 –Use barriers around work area whilst on sales floor, where human traffic dictates, works will also be carried out before store begins trading.
· 5-7– isolate equipment before carrying out any works.
· 5-7 – Utilise standard PPE – Dust mask, eye protection, gloves.
· 5 – read and understand CoSHH data sheets supplied.
· 5-7, 11-14 – Use PPE supplied.
Lighting. / Only applicable when working inside, when working above suspended ceilings ensure that enough tiles are removed to provide ample light.
Hot works. / None permitted within Airports
Is permit to work required : / No.
Access equipment to be used:
E.g.: Tower scaffolding, combination ladders, steps. / Combi type ladders to access cassette units.Site supervision
Identify person in overall charge / Mr David Prout and Mr Chris Ridler will be responsible for site safety during the contract as outlined in Section 2.0 of our Company Policy Document.Works Supervision
Identify the person directly responsible for works / See works request document.Plant and equipment to be used
List major items of equipment
Identify statutory tests/examinations of equipment
/ NoneAssessments (risk, noise, COSHH)
Identify assessments carried out and control measures to be implemented / See Attached
Co-ordination required between contractors to control risk / Not Applicable
Identify hazardous materials and control measures for COSHH assessments carried out, storage of materials, etc / Separate sheets attached for:-
· Hydro-coil
· Acti-tabs
Safety of third parties
Identify works which may present a risk to third parties and detail control measures / · Works will be undertaken outside of store trading hours.Environmental controls
Identify :Control of harmful emissions, e.g. noise, and dust.
Wind, rain, extremes of temperature.
Procedures for disposal of waste / · Noise – Not applicable
· Dust –Vacuum will be utilised to remove surface dust as first method, wet rags will be used second, if nitrogen used will be outside of trading times.
· Release of Nitrogen.
· Any lamps are to be removed from site and disposed of correctly.
First aid and PPE requirements
Identify any additional first aid or PPE requirements, e.g. resuscitator, eye wash, gloves, respirator, hearing protection. / All PPE is issued and should be worn at all times.· Face mask
· Gloves
· Foot protection
Emergency procedures
Are any additional emergency procedures required, will any existing procedures need changing escape routes, location of extinguishers etc / NoOperatives on Site
/ See works request document.Prepared by: / Date:
Paul Boon
/ 26/10/2004Approved by: / Date:
Paul Boon
/ 26/10/2004DSG MAINTENANCE METHOD STATEMENT AIRPORTS 26.05.04 / Page 2 of 3