Reporting Formalities Road Map Status

Deliverable / Coordinated
by / Associated / Initial
Deadline / Updated Deadline
The Single Window and data flow definition / MOVE.D1 / SW sub-group / June
2012 / Completed
Business rules – General maritime / EMSA / GM sub-group / June
2012 / Completed
Business rules – Security / EMSA / MARSEC / November
2011 / Completed
Business rules – Waste / EMSA / Waste sub-group / March
2012 / Completed
Business rules – Customs
Proposal for eManifest / MOVE.D/EMSA
MOVE/TAXUD / Customs sub-Group
Joint eMS/ECG / June 2012
December 2013 / June 2013
December 2013
Business rules – Border Control / MOVE.D1/EMSA / Border sub-group / October
2012 / Completed
Business rules – Health / MOVE.D1/EMSA / Health sub-group / October
2012 / Completed
Harmonisation of business rules / MOVE.D1/EMSA / eMS / Oct-Dec.
2012 / June 2013
Mapping the data set / MOVE.D1/EMSA / Data Mapping and Functionalities group / Oct-Dec.
2012 / December 2013
Milestone: Functional Specifications / MOVE.D1 / eMS / December
2012 / December 2013
Technical specifications: phase 2
Deliverable / Coordinated
by / Associated / Initial
Deadline / Updated Deadline
Technical specifications for interface Single window – SSN / SSN group / HLSG / June 2013 / November 2013
Guidelines for the interface between the Shipping industry and the national single window / EMSA/MOVE D1 / eMS / June 2013 / March 2014
Mandatory functionalities of the Single Windows including the data quality / MOVE.D1/EMSA / eMS / September 2013 / March 2014
Static Data information repository[1] / MOVE.D1/EMSA / eMS / September 2013 / After2015
Messaging Reference Guide / EMSA/MOVE D1 / September 2013 / March 2014
The management of the access rights / MOVE.D1/EMSA / eMS / September2013 / May2014
User authentication2 / MOVE.D1/EMSA / eMS / September2013 / May2014
Commissioning tests plan – training environment / MOVE.D1,EMSA, TAXUD, HOME,SANCO / eMS/SSN group / December 2013 / May2014
Milestone: Implementation Guidelines and commissioning tests plan / MOVE.D1/EMSA / eMS / December 2013 / May 2014
Technical implementation: phase 3
Technical implementation – SafeSeaNet related / SSN NCAs for national component / EMSA (for central component) / 2014
Technical implementation –Single Window / MS NSW responsible Authority / 2014
Technical implementation – Single window / National systems interface / MS NSW responsible Authority / Other National authorities. / 2014
Testing phase: phase 4
Commissioning tests at national level / MS responsible Authority / Other national authorities / March 2015
Commissioning tests of the Single Window – SSN interface / EMSA / MS responsible Authority / March 2015
Initial Operational Phase: phase 5
Implementation / EMSA/MOVE D1/MS / eMS / June 2015

1

[1] After results of RVD pilot project ( as agreed at eMS 7)