In all instances contractors will be required to complete contractor access forms prior to attendance on site.All forms should be issued to the Property Services Team at least 72 hours in advance of anticipated attendance.

Instructions to Contractors

Contractor Access forms will be issued to the contractor by the nominated Selfridges contact acting as the project manager for the works. This can be any one of the below and will be referred to on this form as the Selfridges contact:

Selfridges Project Manager, Concession Manager, Maintenance Manager or a member of the Property Services Team.

Concession’s contractors can only gain access to the store with the Concession Manager’s prior knowledge, agreement and submission of the completed Access Forms.

All contractors should confirm that arrangements have been made for access with the Selfridges contact 24 hours in advance of attendance.

Contractors are responsible for completing the contractors access form, Selfridges method statement and Selfridges risk assessment. No other form of documentation will be accepted. These should be attached alongwith copies of Employer’s Liability and Public Liability insurance documents and sent by email:

The Selfridges contact should also be copied into the e-mail for information.All correspondence should clearly state the name of the Selfridges contact as above.

It is the Selfridges contact’s responsibility to ensure that the contractor access forms are completed in full and that they are accompanied by all required documents as above. They should also ensure that all levels of authorisation are sign-off prior to commencement of works.

All e-mail requests and queries sent to

are attended to Monday to Friday 08.00 – 16.00. E-mails sent outside of these times will not be processed until the next working day.

Method statements and risk assessments accompanying the contractor access form should be sufficiently detailed to descibe the work being undertaken and include details of any and all implications for engineering services installations and fabric. All method statements and risk assessments should be site specific. No generic documents will be accepted. Failure to complete the forms in full or provide suitable and sufficient method statements and risk assessments may result in access being delayed or denied. Blank templates are available on request.

All permits to work activities for hot works, work at height, sprinkler system drain downs and external works on the Selfridges building have to be requested through the Trafford Centre permits office. They can be contacted by the following methods:

Telephone:0161 749 1705

Email :

Page 2 of 3

N.B. Selfridges operates a formal permit to work system, where hazardous or complex works requiring isolation of building services are identified, this procedure will apply. Refer to the Selfridges’ "Contractors Rule Book" for further information. A current copy can be provided on

request.

Project Information:
Name of your company:
Contact telephone number:
Site supervisor name / Mobile:
Site supervisor name (if applicable) / Mobile:
The nominated site supervisor must be on site at all times during project working hours. For sites that are operating 24hrs a day, please give contact details of all site supervisors.
We are on the approved Selfridges contractors list.
Proposed Date(s) / From: / To:
Times of Entry (each day): / From: / To:
Total amount of days on site:
No entry is permitted until 30 minutes after store closing time. Please refer to forcurrent store opening hours.
Project/ ActivityDetails:
Selfridges contact acting as Project Manager for works:
Concession / brand / area name:
Exact location of all planned works:
Access route to and from area of planned works and access to any other areas of the store required.
*Note your access level given will be based on this information.
Details of all planned works
Description of works:
-
-
Additional permits are required for the below. Please inform your contact prior to works.
Contractor permit requirements:
Lights & Power(with specific times, Contractors must supply their owntask lighting when not working on lighting and electrical systems).
From: To: / Hot Works Permit (Via Trafford Centre Permit office)
Electrical isolation to carry out works / Sprinkler works(Via Trafford Centre Permit office)
Working with HVAC / Plant/Service Riser Access *
Security Guard coverage*Must be booked separately, direct with Selfridges Duty Security Mgr.
Working at Height (Via Trafford Centre Permit office).
* For access to these areas and services, please submit specific request forms (available from your Selfridges contact). Charges may apply.

Page 3 of 3

Deliveries:For delivery information, please see appendix 1.
Names of Employees Working On Site:
Forename / Surname / Forename / Surname
The site supervisor has read and understood the Selfridges ‘Contractors Rule Book’ for H&S compliance.
We understand that all employees must bring Photo ID (passport, National Identity Card, Drivers License or current CSCS card only) with them as proof of identification to get on site.
We understand that all employees must have the contractor arm band clearly on show and be wearing appropriate PPE at all times.

* All three signatures are required only when there are engineering works to take place. For all other works, the Selfridges contact and the Property Services Facility Manager only are required to authorise the form.

* In all cases, the final sign off will be by the Property Services Facility Manager. Failure to complete this process will result in access being denied.

Authorised by Selfridges Project Manager Contact:
Name: / Date: / Signature:
Authorisedby Inviron Engineering Manager:
Name: / Date: / Signature:
Authorised by Selfridges Property Services Facilities Manager:
Name: / Date: / Signature:

By emailing this form to Selfridges by default you have declared that the information supplied is correct and legitimate. Selfridges reserves the right to deny access to the contractor if the above information is not submitted as required.

Appendix 1

CONTRACTOR DELIVERY BOOKING IN PROCESS

  • Contact the booking office:

Telephone 0161 629 1106

Office Hours:0600 to 1200 hours Monday to Friday

0600 to 11.30 hours Saturday

Sunday closed

Out of hours deliveries for contractors should arrive after 2230hours. There is no booking system for unloading.

  • Delivery address:

Selfridges & Co

Service Yard 3

1 The Dome

Trafford Centre

Manchester

M17 8DA

  • The loading bay is open to Contractor Deliveries:

Monday - Sunday between 1400 – 0500 hrs

Sunday – All day (Apart from Peak Trade periods between 2nd week of

November and Christmas Eve when the bay is available between 1100 – 2359

hours).

  • Contractor Parking on Service Yard 3

Contractors may park on Service Yard 3 outside trading hours by all vehicles must be clear by 0600 hrs Monday – Saturday and 0930hours on Sunday’s.

During Trading hours contractors are not permitted to park on the loading bay only allowed to unload their vehicles. Parking can be obtained in the external Trafford Centre car parks.

Contractors Access Form – February 2015