Projects Started, Bid, Completed April 2016

  1. PMS Controls Upgrade Project – 640 K. Metro Controls -Finished. Commissioning Finished. Closeout, Punch list completed. Billing and final payout underway.
  2. Frost: Windows/Blinds – Completed, Billing and Punch list underway State Inspection on April 5 2016
  3. Exterior Lighting - J. Ranke Award $900K –Mostly complete. Poles on order for Frost and
  4. Playground
  5. Frost Playground .Board Approved $91,450 Grant funded Project Equipment Ordered January– Install in April
  6. Alcott Playground getting $20,145 Refurbished Equipment from Frost Started Equipment moved to new location
  7. Herrington Boiler Re commission Complete CSD1 Inspector issuing license. Violations resolved
  8. Alcott Boiler. Re commissioning Complete CSD1 Inspector issuing License Violations resolved
  9. Replacement of Sprinkler Heads Pontiac High School Completed State Inspector -no Violations
  10. Frost Fire Monitoring System Board Approved 12-14-2015 Grant Funded work underway
  11. RFP Architect of Record. Integrated Design Systems. Board Approved , Working Facilities Needs Assessment, Pontiac High School HVAC /Controls , Phase 2 and 3 Design (See Below). Evacuation Plans,
  12. ITA , Kennedy and WHRC- Cardinal sprinkler inspections and repairs in process. ITA state inspector signed off. Kennedy tamper valves installed and connected to system. Fire marshal expected to be out April 2016.
  13. Evacuation Plans for Schools finalized Almost Completed all Schools. IDS design.
  14. Owner Operator bids RFP underway
  15. CM/ Construction Manager Bid and RFP underway
  16. Emergency Response Bid. Co- op County Bid 50 K Estimated
  17. PHS HVAC Bid near completion and should be out soon.
  18. Phase 2 Design to go to board approved. WHRC and Admin Building for control project. Pending Capital Budget amendment number 2 FY 16. $131,075
  19. Frost Parking lot and Side Walk. Bid goes to board April 11 2016. Grant Funded Award Pending 103,380 Nagle Paving.
  20. Ansul System PHS and other buildings underway some delays in parts.
  21. Fire Monitoring PMS , WHRC work Completed waiting on Inspector
  22. Frost Grant funding Security Cameras underway
  23. Food Service Equipment. Going to board April 11 2016. Food Service has excess fund balance must spend down. Phase 2 spending of $595,679.00 All Schools.
  24. Parking lots / Sidewalk, ADA Design and Scope all Schools- Underway Nowark and Fraus. 19,300, Design underway IFB bid to follow. Funds from Sinking fund.
  25. Playground Design all schools Underway. Phase 1 in first year Sinking Fund FY 17.
  26. ITA Move and Design. Board Approved. Summer Move, More information to follow.
  27. HVAC Energy Management Temp connects. Underway all Schools. Metro Controls. $20,000