Project: Group Housing Project, “Paras Quartier”, Gwal Pahari Sec-2, Gurgaon (Haryana)

Half-yearly Compliance Report of EC (Ref. No. – SEIAA/HR/2013/480 at dated 12th July, 2013) Conditions

Page 1 of 24


Description / Page No.
Chapter 1 / Compliance of Stipulated Conditions of Environmental Clearance
Part A / Specific Conditions for buildings / 3
I. Construction Phase / 3
II. Operation Phase / 8
Part B / General Conditions / 12
Chapter 2 / Details of Environmental Monitoring
2.0 / Introduction / 14
2.1 / Ambient Air Quality Monitoring / 14
2.1.1 / Ambient Air Quality Monitoring Stations / 14
2.1.2 / Ambient Air Quality Monitoring Methodology / 14
2.1.3 / Ambient Air Quality Monitoring Results / 16
2.1.4 / Discussion on Ambient Air Quality in the Study Area / 17
2.2 / Ambient Noise Monitoring / 17
2.2.1 / Ambient Noise Monitoring Locations / 17
2.2.2 / Methodology of Noise Monitoring / 17
2.2.3 / Ambient Noise Monitoring Results / 18
2.2.4 / Discussion on Ambient Noise Levels in the Study Area / 19
2.3 / Drinkingwater Quality Monitoring / 19
2.3.1 / Drinkingwater Quality Monitoring Locations / 19
2.3.2 / Methodology of Drinkingwater Quality Monitoring / 19
2.3.3 / Drinkingwater Quality Monitoring Results / 21
2.3.4 / Discussion on Drinkingwater Quality in the Study Area / 22
2.4 / Soil Monitoring / 22
2.4.1 / Soil Monitoring Locations / 22
2.4.2 / Methodology of Soil Monitoring / 22
2.4.3 / Soil Monitoring Results / 23
2.4.4 / Discussion on Soil Characteristics in the Study Area / 23
Annexure
1 / Test results of ambient air, noise, water and soil monitoring

CHAPTER-1

Compliance of Stipulated Conditions of Environmental Clearance for Group Housing project “Paras Quartier” atGwal Pahari Sec-2, Gurgaon,Haryana.

PART A – SPECIFIC CONDITIONS

  1. Construction Phase

S. No. /

Conditions of Environmental Clearance

/ Status of Compliance
1). / “Consent For Establishment” shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before start of any construction work at site. / Consent to establishment issue by HSPCB. Obtained.
2) / A First aid room as proposed in the project report shall be provided in both during construction and operational phase of the project. / Adequate First aid room is provided
3) / Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the labors is strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. / Adequate drinking water & sanitary facilities shall be provided for construction workers at the site. The workers shall be from the nearby areas therefore the waste water and solid waste generations would be negligible in quantity. Solid waste generated during the construction phase will be disposed off safely.
4) / All the top soil excavated during construction activities should be stored for use in horticulture/landscape development within the project site. / Top soil shall be stored for use in horticulture/landscape development.
5) / The project proponent should ensure that the building material used in the construction phase should be stored within the project area and disposal of construction waste should not create any adverse effect on the neighboring and should be disposed of after taking necessary precautions for general safety and health aspects of the people, only in the approved sites with the approval of competent authority. / Noted. Shall be complied.
6) / Construction spoils, including bituminous materials and other hazardous materials must not be allowed to contamination watercourses and the dump site for such materials must be secured so that they should not leach into ground water and any hazardous waste generated during construction phase should be disposed off as per applicable rules and norms with necessary approval of Haryana State Pollution Control Board. / Construction spoils are stored in a dedicated area duly bounded to avoid contamination to the environment in proximity. Storage area shall be covered by insulated lining to prevent contamination from hazardous materials like fuel of DG sets. Waste oil of the DG Set shall be disposed of through authorized vendors.
7) / The diesel generator sets to be used during construction phase should be of ultra lowsulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standard. / Silent DG sets are used at the project site during construction stage, with maintained noise and emission within the permissible limits.
8) / The diesel required for operating DG sets shall be stored in underground tanks if required,clearance from Chief Controller of Explosive shall be taken. / The diesel isstored in appropriate place with required permissions.
9) / Ambient noise levels should conform to the residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air and noise level during construction phase, so as to confirm stipulated residential standards. / Ambient air & noise monitoring had been conducted at project site and the results showed that the noise levels were within the prescribed limits. Lab report attached in Annexure-1
10) / Fly ash should be used as building materials in the construction as per the provision of Fly Ash Notification of September 1999 and amendment as on 27th August 2003. / Fly ash will be used in construction activities.
11) / Storm water control and its re-use as per CGWB and BIS standard for various applications should be ensured. / The recharge structures for storm water control as well as rain water harvesting are proposed for recharging of ground water.
12) / Water demand during construction phase should be reduced by uses of pre-mixed concrete, curing agent and other best practices. / Premix concrete and curing agent shall be used to save water.
13) / In view of severe constrains in water supply augmentation in the region and sustainability of water resources, the developers will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water –potable and non potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA/R.O. MoEF, Chandigarh before start of construction. / STP Treated water provided by HUDA will be use for construction purpose. This water is further treated by a Tertiary Treatment Plant
14) / Roof should meet prescribed requirements as per Energy Conservation Building Code by using appropriate thermal insulation material. / Thermal insulation of roofs shall be done.
15) / Opaque wall should meet prescribed requirements as per energy conservation building code which is proposed to be mandatory for all air conditioned spaces while it is desirable for non air conditioned spaces by use of appropriate thermal insulation to fulfill the requirement. / This being air conditioned building thermal insulation planned accordingly.
16) / The approval of competent authority shall be obtained for structural safety of the building due to earthquake, adequacy in firefighting equipment etc as per National Building Code including protection measures for light etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be obtained from competent Authority. / The approval for structural safety has been obtained. Forest NOC has been obtained.
17) / Overexploited Drinking water and impending severe shortage of water supply in the region requires the developers to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponentshall incorporate water efficiency /saving measures as well as water reuse /recycling within 3 months and before start of construction to the SEIAA, Haryana and R.O. MoEF, GOI, Chandigarh. / Dual plumbing will be adopted for conservation of water.
18) / The project proponent shall construct 06 rainwater harvesting pits for recharging the ground water with in project premises. Rain water harvesting pits shall be designed to make provision for silting chamber and removal of floating matter before entering harvesting pit. Maintenance budget and person responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RHW pit. / 06 number of RWH pits will be constructed in due course of time. All necessary measures as per your requirement shall be complied.
19) / The Project Proponent shall provide minimum one hydraulic ladder of sufficientlength for escape of people in case of fire. / Shall be complied.
20) / The project proponent shall submit assurance from the DHBVN for supply of 2990 KVA of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. / The project will operate only after obtaining connection of DHBVN power supply. The project will not be operational solely on generators without any power supply from any external power utility.
21) / Detail calculation of power load and ultimate power load of the project shall be submitted to DHBVN under intimation to SEIAA Haryana before the start ofconstruction. Provisions shall be made for electrical infrastructure in the project area. / Will submit letter to DHBVN for electric load.
22) / The project proponent shall obtain NOC from nearest fire station before the start of construction. / Obtained.
23) / The Project Proponent shall not raise any construction in the natural landdepression / Nallah /water course. The project proponent shall ensure that naturalflow of existing nallah should not be obstructed and shall seek NOC fromIrrigation Department before the start of the construction. / Agreed. Shall be complied during construction.
24) / The Project Proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project as per prescribed by-laws. Levels of the other areas in the Projects shall also be kept suitably so as to avoid flooding. / Agreed. Shall be complied during construction.
25) / Construction shall be carried out so that the density of population does not exceed norms approved by the Director General Town and Country Department Haryana. / All norms as prescribed by DG, TCP in the LOI, License, Zoning Plan and other relevant documents shall be taken into consideration and strictly followed.
26) / The project proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only the treated water should be used for construction. / Same has already been submitted.
27) / The project proponent shall not cut any existing tree in the project area and project landscaping plan should be modified to include those trees in the green area. / Agreed.
28) / The project proponent shall provide helipad facility as required under NBC norms and shall seek permission of helipad from AAI accordingly. / Agreed.
29) / The project proponent shall ensure that ECBC norms for composite climate zone are met. In particular building envelope, HVAC service, water heating, pumping, lighting and electrical infrastructure must meet ECBC norms. / Agreed.
30) / The project proponent shall provide 3 meter high barricade around the project area, dust screen for every floor above the Drinking, proper sprinkling and covering of stored material to restrict dust and air pollution during construction. / Agreed. The necessary measures areundertaken during the construction of this project.
31) / The project proponent shall seek NOC from AAI regarding height clearance before the start of construction. / Obtained.
32) / The project proponent shall provide mobile sulabh toilets instead of soak pitduring construction phase for disposal of sullage. / Agreed. Shall be complied during construction.
33) / The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. / Agreed. A sedimentation basin shall be constructed to trap the pollutants and other wastes.
34) / The project proponent shall provide proper Rasta of proper width and proper strength for each project before the start of construction. / There is a rasta provided of adequate width and strength for this project.
35) / The project proponent shall provide all the safety measures for the workers during construction of high rise building. / Agreed. Shall be complied during construction.
36) / The project proponent shall ensure that the U-value of the glass is less than 3.177 and maximum solar heat gain co-efficient is 0.25 for vertical fenestration. / All norms of ECBC shall be complied.
37) / The project proponent shall provide all the safety measures for the workers during construction of high rise building. / Agreed. Shall be complied during construction.
38) / The project proponent shall seek NOC from Town and Country department regarding height of the building allowed in the skyline of that city. / Obtained.
39) / The project proponent shall ensure that no construction activity is undertaken on surface of revenue rasta passing through the project area. / Agreed.
40) / The project proponent shall indicate the width and length of revenue rasta passing through the project area on sign board and shall display the same at both the ends of revenue rasta stretch, for awareness of public. Sign board also display the message that this is public rasta/road and any citizen can used it. There shall not be any gate with or without guards on revenue rasta.. / Agreed.
41) / The project proponent shall ensure structural integrity of high rise building during any seismic activity. / Agreed. Shall be complied during construction.
42) / The project proponent shall adequately control construction dusts like silica dust, non-silica dust, wood dust. Such dusts shall not spread outside the project premises. The project proponent shall provide respiratory protective equipments to all construction workers. / All necessary measures shall be complied during the construction of this project.
43) / The project proponent shall submit design and capacity of STP proposed for plot no. 5 and shall submit revised water balance diagram before the start of construction. / Already submitted.
44) / The project proponent shall ensure that in case of excessive flow of water in nallah, the structural integrity of buildings along-side the nallah is not breached in any circumstances. / Agreed. Shall be complied during construction.
45) / The project proponent shall ensure that there should not be any water logging on the bed of nallah even in case of excessive rain. / Agreed. Shall be complied during construction.
46) / The project proponent shall ensure that sewerage pipe line should not cross over the nallah and project proponent shall maintain separate STP in the plot area across the nallah. / Agreed. Shall be complied during construction.
47) / The project proponent shall ensure that sewerage line shall be planned by taking into account the natural slope and gravity of original land. / Agreed. Shall be complied during construction.
48) / The project proponent shall ensure that bed of nallah is not encroached in any manner, while constructing the culvert over the nallah / Agreed. Shall be complied during construction.
49) / The project proponent shall ensure that there should not be any encroachment on the private land and project proponent shall get NOC from
revenue department that no part of its construction is over the public land. / Agreed. Shall be complied during construction.
50) / The project proponent shall ensure that the plinth level of the building block to be 1.5 meter above 100 years flood level of . / Agreed. Shall be complied during construction.
51) / The project proponent shall provide pervious surface instead of impervious and hard surface in order to reduce overflow water in nallah. / Agreed. Shall be complied during construction.
52) / The project proponent shall provide one refuse area till 24 meter and one till 39 meter and one after every 15 meter as per National Building Code. / Agreed. Shall be complied during construction.
53) / The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. / Agreed. Shall be complied during construction.
54) / The project proponent shall obtain permission of Mines and Geology Department for excavation of soil before the start of construction. / Obtained.
55) / The project proponent shall submit proper certificate regarding non-applicability of Aravali Notification before the start of construction. / Already submitted.
56) / The project proponent shall make provision for parking in each plot as per its requirement on the basis of Haryana Govt norms after making necessary changes / Agreed. Shall be complied during construction.

II. Operation Phase

S. No. /

Conditions of Environmental Clearance

/ Status of Compliance
a) / “Consent to Operate” shall be obtained from Haryana State Pollution Control Board under Air and Water act and a copy shall be submitted to the SEIAA, Haryana. / CTO shall be applied and obtained before the operation phase.