Philip & Margaret Shaw

Hawthorn Cottage

Barrington Road

e-mail:

FOXTON LEVEL CROSSING

A STRATEGIC VIEW

1. INTRODUCTION.

1.1. Network Rail (NR) has produced a project plan to close and by-

pass the level crossing at Foxton. Foxton Level Crossing Elimination GRIP 2

Report Rev C (the Project) which has been posted on the FoxtonVillage web site,

We have read the Project report.

1.2. The Project takes a restricted view for overcoming the perceived problem at

the level crossing. NR has not sought any local view prior to publishing the

report, but has followed the historical approach to provide a solution.

2. HISTORY.

2.1. A proportion of the land the Project incorporates was purchased by the

Department of Transport in 1935 to provide a by-pass for the level crossing at

the time. The situation then was that Barrington Road, Foxton ran through

the level crossing complex. Thus there was a cross road with Station Road and

the A10 together with the level crossing, a complicated junction. Some time after the purchase of the land in 1935 the present Barrington slip road was built. This was considered a solution. Was this the real reason for purchasing the land? Since then there have been a number of proposals for a by-pass to the level crossing but none has been executed, it is thought due to cost.

2.2. About 8 years ago the A10 was ‘detrunked’ as a major route, reverting from

green to red on OS maps. The A505 and M11 were given the status of the ‘trunk’

route access to Cambridge

2.3. The village of Harston has sought to have a by-pass for some time. About

5 years ago a traffic calming project was carried out on the A10 through Harston.

The cost was reported to be in excess of £1M.

2.4. Over the past 20 years the passenger rail traffic using the Cambridge to

Kings Cross line has increased from 2 slow diesel trains each hour to 6 fast and 2

slow electrified trains each hour as standard and 12 trains each hour at peak

times. In the same period the volume of traffic using the A10 travelling both

north and south has increased exponentially. Also the legal physical size of

lorries has doubled which affects Harston particularly.

2.5. The rise of Cambridge as an advanced technological industrial city over the

past 30 years has developed it as a major centre for employment. Thus all

aspects of life in the area have increased and intensified. Cambridge is also

considered within commuting distance of London. These factors have given the

impetus for the increase in road and rail traffic through the level crossing at

Foxton.

3 PRESENT SITUATION.

3.1.The level crossing is a major obstacle to the flow of road traffic,

particularly at peak times. Peak time amounts to a 6/7hour period each work

day, 2.5/3hours in the morning and 3.5/4hours in the evening. Due to the

number of trains at peak times the crossing is closed to road traffic for extensive

periods resulting in very long tail backs both north and south The consequence

is ever longer daily traffic delays. A circumstance that is really unacceptable

today.

3.2. From the rail crossing north bound traffic then encounters Harston creating

a deluge of vehicles into the traffic calmed village hence even more delay. The

calming includes 3 sets of traffic lights, 2 pedestrian and one road set. The

situation creates potential danger for pedestrians, children going to and from

school, cyclists and drivers. The tail back of traffic can reach 1/2 mile.

3.3. The traffic delays at Foxton give rise to frustration and annoyance that cause

a few drivers to take risks as the barrier closes. NR has installed cameras to help

apprehend culprits. A 50mph speed limit over the crossing is frequently

monitored by the transport police to deter speeding and eliminate a potentially

dangerous situation as the barrier is lowered. There has been successful

prosecution of wrong doers.

3.4. The Project states that safety is of paramount importance and accepts that

the safety regime at the crossing meets all current criteria and that there is a

good record of safety.

4. POLITICS/POLICY

4.1. NR has instituted a policy to close as many rail crossings as possible

throughout the country. Government has given its support and made finance

available. The policy has been born due to a number of tragic accidents at rail

crossings that have been given high profile in the media. This has led to more

reporting by the media of incidents at rail crossings, many on a regional basis.

The high profile accidents have given rise to local action groups and these have

further developed into a national action group intent on closing as many

crossings as possible and thus supporting NR’s policy.

4.2. It is evident from reports in the media that most of the accidents or near

accidents are due to lack of self discipline and/or patience on the part of the

perpetrator. This is a very small minority of the public and therefore should not

be allowed to drive policies that infringe the rights and freedom of the public at

large.

4.3. An advantage to NR is that closing crossings will save money in due course. It

will also simplify management of the rail network. Two very good reasons for the

policy. However the policy must not be permitted to close crossings which by

doing so would infringe the environment, cohesion and freedom of any

particular community.

5. THE PROJECT

5.1. The Project takes into use a piece of land purchased nearly 80 years ago to

create a by-pass to the level crossing. The Project will need to purchase

additional land, well in excess of that now held, for it to be achieved. As written

the Project aims to keep cost to a minimum and has a narrow perspective in an

effort to achieve its aim. What is needed is a full examination of all possibilities

and to look well into the future. So many minor projects are absorbed by a bigger

project in following years when it would have been best to do a quality project

from the start.

5.2. If the project is implemented the living circumstance for some residents

will improve whilst for others it will be considerably worse. The layout of the

alternative road positions to the north of the railway is awful beyond

description. It will mean destroying a well developed copse, now nearly 20 years

growth and a quality village feature, and replacing it with tarmac! Two homes

are particularly badly affected by the Project and the Project should consider

purchasing these properties if the owners so wish.

5.3. Closing the level crossing, repositioning the A10 as projected and building a

steel pedestrian bridge, suitable for the disabled and horses, over the crossing

will physically divide the village in two and create an entirely unacceptable

blotch of tarmac and steel within the village.

5.4. The Project is assessed as costing between £14M & £22M depending on

the decision for a flyover or an underpass. Allowing for the usual under

budgeting a figure of £25M is more likely for the top end cost. This is a

substantial amount of money and it has to be asked whether it could be better

used?

6. THE VILLAGES.

6.1. There are two villages affected by the Project, Foxton and Harston. Harston

has called for a by-pass for some time because the A10 constitutes their High

Street. To appease the village a traffic calming scheme was implemented about 5

years ago at a cost reported to be in excess of £1M. The scheme has slowed traffic

but also made the road more dangerous for two wheeled traffic. The scheme also

causes long tail backs, up to 1/2 mile, to the south particularly at peak times.

6.2. If the Project is implemented the A10 is likely to be used even more heavily

than now due to a major delay factor being removed. Also considerable numbers

of houses are being built at either end of this stretch of A10 further increasing

traffic. In consequence Harston will have to cope with even more traffic thus

reducing the quality of life in the village even further.

6.3. Foxton will become a totally disjointed village. The present rail crossing

divides the village but it is at a single point and is used by pedestrians and all

modes of transport. The Project will introduce an absolute division by closing the

crossing, cause additional effort by having to use a footbridge or lift(some people

fear lifts and wont use them) and create a second infringement by having to

cross the relocated A10

6.4. Surely in an advanced civilized society this is not acceptable change.

Countries such as Holland and Italy produce beautiful solutions to overcome

local difficulties created by the increasing burden of traffic. We should be equal

to this approach.

7. STRATEGY.

7.1. The A10 is the major route from the south and south west, using the

A1/A505, to and from Cambridge. The Melbourne by-pass made the A10 more

viable for the increased size of heavy vehicles. That the A10 was ‘detrunked’ has

had no effect on traffic using the road. In the future with Cambridge continuing

to grow in both industry and population and Royston doing the same the A10

between can only get more and more busy. It is therefore not sensible to just

tinker with modifying the road, it requires strategic vision.

7.2. The rail connection between Cambridge and London will increase in

importance and thus usage. The plan to increase trains to 12 carriages, develop

stations to incorporate the change and the new loop line at Hitchin demonstrates

the rail managements forward thinking on need and safety

7.3. The A10 from the junction with the A505 at Royston north as far as

Shepreth,Frog End, is a clear road and could be made into a dual carriageway.

From Frog End the road deteriorates with numerous junctions a level crossing

and a serious built area, Harston.

7.4. There are two possible alternatives to the Projects’ solution. First, to let the

A10 cross the rail line to the west of the rail crossing and then follow the present

sidings towards Barrington swinging right just before meeting the Barrington

Road. It would then meet up with the present A10 route south of Harston. From

here it could either run into Harston or carry on going up on to the ridge and

passing east of Harston to create a by-pass. Second, the better alternative,

reroute the A10 from just north of Frog End by swinging right to the east of

Foxton and Harston on to the east side of the ridge and rejoining the A10 at

Hauxton near the old chemical works. This is virgin land and could provide for a

dual carriageway from the outset. There is bridge over the railway on the B1368

that would require modification. The new build would be 4.66 miles in length.

7.5. A similar project has been done at Baldock to create a by-pass for the A505,

a distance of 3.8miles at a cost of £43M. The tunnel absorbed 10% of the cost,

this was incorporated to enable the land to be returned to farming.

An even bigger project on the Hoggs Back at Guildford in Surrey has seen

the road put through a tunnel a mile long so that the Hoggs Back could be

reinstated to the environment that it enjoyed some hundreds of years ago. The

Hoggs Back has been a major route for travellers since before the carriage was

invented. These are beautiful solutions to traffic problems, and should be the aim

for planners

7.6. The ground on which the road would be built is chalk. Chalk is easily

excavated, as at Baldock, to make the road almost invisible so not to infringe the

enviroment and reducing noise pollution. The spoil could be disposed of in the

quarry at Barrington where it is needed to landscape the quarry for future

development.

7.7. Under this scenario the level crossing would remain so not to divide Foxton.

It could be modified to make it into a minor road crossing, but still retaining pedestrian gates that lock as the barrier closes, and the barrier made

parallel with the rail track thus removing the restriction at the rear of No 2

Barrington Road. The present A10 having become a minor road it would be for

consideration whether both Foxton and Harston could be further developed.

7.8. The route to the east of Foxton and Harston is 4.66 miles, longer but less

complex than the Baldock by-pass so cost may not be that much different, a

budget of £50M should be near the mark. Using the budget from the Foxton rail

crossing it may require only an additional £30M to provide a scheme that will

resolve all problems and last long into the future.

8. CONCLUSIONS.

8.1. The proposed Project has not taken due note of changes in traffic and living

circumstance over the past 80 years.

8.2. The project would not resolve the real problems created by the present density of road traffic using the A10 between Royston and Cambridge. The density will intensify therefore a more strategic solution is needed than that proposed.

8.3. Building a new dual carriageway road to the east of Foxton and Harston would meet present and anticipated future of the village communities and road users.

8.4. The rail crossing should be modified to become a crossing on a minor road and not closed.

IF YOU AGREE WITH THE ABOVE PLEASE E:MAIL US AND WE SHALL CREATE A DATA BASE OF THOSE SUPPORTING A BROADER APPROACH.

THE RED ARROWS SHOW THE TWO STRATEGIC BYPASS IDEAS.

THE ONE TO THE LEFT KEEPS FOXTON AS AN UNDIVIDED VILLAGE

THE ONE TO THE RIGHT IS THE SUGGESTED BYPASS FOR FOXTON AND HARSTON