LANE CLOSURE REQUEST

NW 25thSt.,EB and WB between east of SR 826 and NW 89 Ct.

WORK SCOPE

FDOT Project T6127 – NW 25th St from NW 89th Ct to SR 826

(FIN#: 251185-1-52-01, 251185-1-56-01, 405665-1-52-01)

Date / Times: 8/03/12 (Friday)9:00pm–8/06/12 (Monday) 5:30am

Friday thru Sunday– 9:00pm to 7:00am,Sunday thru Monday– 8:00pm to 5:30am

Road: NW 25thSt.eastbound and westbound betweeneast of SR 826 and NW 89 Ct.

Number of Current Thru Lanes EB: 2-3

Number of Thru Lanes to be Closed EB: 1-2

Number of Thru Lanes to be Open EB: 1

Number of Current Thru Lanes WB: 2

Number of Thru Lanes to be Closed WB: 1

Number of Thru Lanes to be Open WB: 1

Turn lanes will be closed @ NW 79, 82, 84 & 87, open onto and off of SR 826

Work Scope: Hydro-Blast Striping Removal, Re-Striping, Traffic Phase 1B MOT Devices & Signage

8-03-12 (Friday night): Hydro-Blast Striping Removal, Re-Striping, Traffic Phase 1B MOT Devices & Signagewest of SR 826 to a location between NW 79thAve. & NW 82nd Ave.

8-04-12 (Saturday night): Hydro-Blast Striping Removal, Re-Striping, Traffic Phase 1B MOT Devices & Signage west of NW 82nd Ave. to a location between NW 84th Ave. & NW 87nd Ave.

8-05-12 (Sunday night): Hydro-Blast Striping Removal, Re-Striping, Traffic Phase 1B MOT Devices & Signage west of NW 84th Ave. to a location between NW 87nd Ave. & NW 89thCt.

Traffic Control Plan: See attached.

Notes: FDOT Standard Index618 will be utilized for necessary lane closures to isolate nightly work zones.

NIGHT 1: 9:00pm to 7:00am (FRIDAY)

9:00 pm: Closing 2 lanes EB and 1 WB of NW 25th Street from East of SR-826 (Palmetto

Expressway) to East of NW 82nd Ave (Set all MOT)

10:00 pm: Begin Hydro-blasting just west of SR-826 and continue west (2Crews): Hydroblast double

yellow, gores, turn arrows, and white skips in preparation for phase 1B.

12:00 am: Striping will start from SR-826 and continue west lagging behind the hydroblasting

(striping operations will have 2 crews)

3:00 am: Done with Hydroblasting.

4:00 am: Complete paint striping for phase 1B configuration.

5:00 am:Complete paint/tape striping for WB lanes transition just east of NW 82nd Ave including

temporary rpm’s.

6:00 am: Pick up MOT / shift traffic to new configuration and open road up at 7:00 am.

NIGHT 2: 9:00pm to 7:00am (SATURDAY)

9:00 pm: Closing 2 lanes EB and 1 WB of NW 25th Street from East of NW 82nd Ave to East of

NW 87th Ave. (Set all MOT)

10:00 pm: Begin Hydro-blasting just East of NW 82nd Ave and continue west (2Crews): Hydroblast

doubleyellow, gores, turn arrows, and white skips in preparation for phase 1B.

12:00 am: Striping will start from east of NW 82nd Ave and continue west lagging behind the

hydroblasting(striping operations will have 2 crews)

3:00 am: Done with Hydroblasting.

4:00 am: Complete paint striping for phase 1B configuration.

5:00 am:Complete paint/tape striping for WB lanes transition just east of NW 87th Ave including

temporary rpm’s.

6:00 am: Pick up MOT / shift traffic to new configuration and open road up at 7:00 am.

NIGHT 3: 8:00pm to 5:30am (SUNDAY)

8:00 pm: Closing 1 lane EB and 1 WB of NW 25th Street from East of NW 87th Ave to NW 89th

Court. (Set all MOT)

9:00 pm: Begin Hydro-blasting just west of NW 87th Ave and continue west to NW 89 Court

(2Crews): Hydroblast double yellow, gores, turn arrows, and white skips in preparation for

phase 1B.

10:00 pm: Striping will start from just east of NW 87th Ave and continue west to NW 89th Court

lagging behind the hydroblasting (striping operations will have 2 crews)

1:00 am: Done with Hydroblasting.

3:00 am: Complete paint striping for phase 1B configuration including temporary rpm’s.

4:00 am: Pick up MOT / shift traffic to new configuration and open road up at 5:30 am.

5:30 am: Open road up at 5:30 am.

/ 8220 State Road 84 – Suite 300, Davie, Florida 33324
Telephone: (954) 423-8766  Fax: (954) 423-2597