-1-
NOTICE OF PETITION FOR TEMPORARY URGENCY CHANGE
FOR PERMIT 21185 (APPLICATION 28609) OF
JUNE LAKE PUBLIC UTILITY DISTRICT
COUNTY: MonoSTREAM SYSTEM: Fern Creek
On November 4, 2015,the June Lake Public Utility District (Petitioner) filed a Temporary Urgency Change Petition (TUCP) with the State Water Resources Control Board (State Water Board), Division of Water Rights (Division) requesting renewal of the Order issued on May26,2015 (2015 Order). Thispetition renewal request is identical to the Petitioner’s 2015 Order and the Petitioner’s August 25, 2014 Order (2014 Order). The 2014 Order approved the TUCP filed on filed on May 20, 2014 and authorized a temporary reduction in the minimum bypass flow requirement of Permit 21185 (Application 28609) from 200 gallons per minute (gpm) to 25gpm. The requested renewal period would begin November 28, 2015 and end May26, 2016. The requested change would help the Petitioner meet projected potable water demand for its Down-Canyon Service Area.
Summary of Permit 21185:
Source: / Fern Creek tributary to Reversed Creek thence Rush Creek thence Mono LakePoint of Diversion: / NW¼ of SE¼ of Section 21, T2S, R26E, MDB&M
Season of Diversion: / January 1 to December 31 of each year
Diversion Rate and Annual Amount: / 0.30 cubic foot per second (or 134.6gpm) by direct diversion
150 acre-feet per year
Bypass Flow Requirement: / Existing: 200 gpm
Proposed: 25 gpm
Purpose of Use: / Municipal
Place of Use: / N½ of NW¼ and N½ of NE¼ of Section 21 and
NW¼ of NW¼ of Section 22; all within T2S, R26E, MDB&M
More information regarding this TUCP is available at:
Pursuant to Water Code section 1438, subdivision (a), the State Water Board may issue a temporary change order in advance of public notice.
Pursuant to California Water Code section 1438, subdivision (d), any interested person may file an objection to the temporary change. Objections must be received by the Division by 4:30 p.m. on December13, 2015.
Objections filed with the Division must indicate the manner in which service upon the Petitioner of a duplicate copy of the protest has been made. Correspondence directed to the Petitioner should be addressed to: Wagner & Bonsignore, CCE, c/o Mr. Vince Maples, 2151 River Plaza Drive, Suite 100, Sacramento, CA 95833.
For more information regarding this project, including procedures for filing objections, please contact Steve Marquez at (916) 341-5350 or . Written correspondence or inquiries should be addressed as follows: State Water Resources Control Board, Division of Water Rights, Attn:Steve Marquez, P.O. Box 2000, Sacramento, CA 958122000.
DATE OF NOTICE: November 13, 2015
SMarquez.GHernandez 11/13/2015.
S:\DWR\VOL1\PALDRV\SMARQUEZ\TUCP\June Lake PUD\June Lake PUD Renewals\3. JLPUD A28609 TUCP 2nd Renewal 11-5-15\A28609_notice_11-2015.docx