Last Updated 6/14/02
CONTRACT SUMMARY
This information will made available to the public on the State Water Resources Control Board’s (SWRCB) Website (see address below).
Use the "tab" and arrow keys to move through the form. If field is not applicable, please put N/A in block.
Date filled out: July10, 2003
A) Contract Information Please use complete phrases/sentences. Fields will expand as necessary as you type.1. Contract Number: 02-108-252-0
2. Project Title: San Francisquito Creek Watershed Analysis and Sediment Reduction Plan
3. Project Purpose – Problem: The creek system supports a wild run of steelhead trout which is federally listed as threatened
in central CA; the creek has been listed as sediment impaired under section 303(d) of the Clean Water Act, requiring
establishment of a TMDL. The sediment listing is driven by implied degradation of habitat for steelhead trout and other
threatened species.
4. Project Goals: To conduct specific analysis of the Creek Watershed that will be used to develop a Sediment Reduction
Plan that prioritizes erosion control and sediment reduction measures to be implemented throughout the watershed.
a. Short-term Goals: Historical & Existing Conditions analysis;exisiting management practices review; sediment analysis.
b. Long-term Goals: Create a Sediment reduction plan with recommendations for improving existing practices,
filling gaps, and prioritize potential high sediment productions sites for erosion control measures.
5. Project Location: San Francisquito Creek Watershed;border line between Santa Clara and San Mateo Counties;
Physical Size of Project: 45 Square miles; 72 miles of creeks. / Counties included in the project: Santa Clara and San Mateo
a. Legislative Districts: (Assembly and Senate)
AssemblyDistrict 21- Simitian ; Senate District 11 - Sher
6. Which SWRCB program is funding this contract? Please put an "X" by the one that applies.
_x__ Prop 13 ___ EPA 319(h) ___ Other
B) Contract Contact: Refers to contract project director.
Name: Cynthia D’Agosta / Job Title: Executive Director
Organization: San Francisquito Creek JPA / Webpage Address: http://www.cityofpaloalto.org/jpa/
Address: 701 Laurel Street, Menlo Park, CA 94025
Phone: 650-330-6765 / Fax number: 650-328-7935
Email:
C. Contract Time Frame:
From: October 1, 2002 / To: July 31, 2004
D) Project Partner Information: Name all agencies/groups involved with project SFCreek JPA, San Mateo County Flood, Santa Clara Valley Water District, Woodside, Portola Valley, Santa Clara County, Palo Alto, East Palo Alto, Menlo Park. And there is a Technical Advisory Committee with representatives from Stanford Univ, the Watershed Council,BASMAA, RWQCB,STOPPP,SCVURPP.
E) Nutrient and Sediment Load Reduction Projection (if applicable): n
UnknownPLEASE PROVIDE A HARD COPY AND AN ELECTRONIC COPY TO YOUR CONTRACT MANAGER AND YOUR PROGRAM ANALYST WITH YOUR QUARTERLY/MONTHLY REPORT. ALL APPLICABLE FIELDS ARE MANDATORY. IF FIELD IS NOT APPLICABLE, PLEASE PUT N/A IN BLOCK. INCOMPLETE FORMS WILL BE RETURNED. THE ELECTRONIC VERSION OF THIS FORM CAN BE FOUND AT: http://www.swrcb.ca.gov/nps/319hproj.html.