Date filled out: 2-28-05

A) Contract Information Please use complete phrases/sentences. Fields will expand as necessary as you type.
1. Contract Number: 03-231-554-0
2. Project Title: McGrath Lake Watershed/McGrath Drain Project
3. Project Purpose – Problem: In 2002 the McGrath Watershed Action Committee identified a deficiency in the design of the
McGrath Drain/Landfill Drain intersection that causes storm waters (5 year event or greater) to overflow the drain channel bank,
sending storm runoff from the flower fields/Bailard Landfill across the Coultas Ranch, causing sheet erosion, and sending sediment
-laden waters westward into McGrath Lake.
4. Project Goals: Maximize the holding capacity of the drain system (25% increase) through grading/reshaping channel banks;
Reduce sediment/erosion within the drains through construction of a sediment trap and channel bank improvements (bank slope reduction, vegetative cover); Reduce blockage of the outflow culvert (hence overflow/flooding) and maintain current wildlife value of the eucalyptus for nesting/roosting habitat by pruning eucalyptus trees
a. Short-term Goals: N/A
b. Long-term Goals: Reduce sediment contamination of the McGrath Lake and Santa Clara River by reducing the volume of sediment-laden storm runoff arriving from farm fields into McGrath Lake and reducing the concentration of sediment in surface waters flowing to the Santa Clara River.
5. Project Location: (lat/longs, watershed, etc.) Lat. 34.225/Long. -119.229, McGrath Lake Watershed, Landfill/McGrath Drain.
a. Physical Size of Project: (miles, acres, sq. ft., etc.) 5.7 acres. / b. Counties included in the project: Ventura County
c. Legislative Districts: Assembly 35th / Senate 18th
6. Which SWRCB program is funding this contract? Please put an "X" by the one that applies.
X Prop 13 ___ EPA 319(h) ___ Other
B) Contract Contact: Refers to contract project director.
Name: Jason Siegert / Job Title: Source Control Inspector
Organization: Ventura Regional Sanitation District / Webpage Address: www.vrsd.com
Address: 1001 Partridge Drive Suite 150
Ventura, California 93003
Phone: 805 658-4617 / Fax number: 805 658-4631
Email:
C. Contract Time Frame: Refers to the implementation period of the contract.
From: June 30, 2004 / To: March 31,2006
D) Project Partner Information: Name all agencies/groups involved with project. Ventura Regional Sanitation District, SWRCB, Coultas Ranch and LARWQCB.

E) Nutrient and Sediment Load Reduction Projection (if applicable): N/A

PLEASE PROVIDE A HARD COPY AND AN ELECTRONIC COPY TO YOUR CONTRACT MANAGER AND YOUR PROGRAM ANALYST WITH YOUR QUARTERLY/MONTHLY REPORT. ALL APPLICABLE FIELDS ARE MANDATORY. IF FIELD IS NOT APPLICABLE, PLEASE PUT N/A IN BLOCK. INCOMPLETE FORMS WILL BE RETURNED. THE ELECTRONIC VERSION OF THIS FORM CAN BE FOUND AT: http://www.swrcb.ca.gov/nps/formsandsummaries.html