MOKOPANE INTEGRATION PROJECT: 765Kv TRANSMISSION LINE and SUBSTATION

MOKOPANE INTEGRATION PROJECT: 765Kv TRANSMISSION LINE and SUBSTATION

Eskom Holdings Limited

Mokopane Integration Project

APPENDIX ?

MOKOPANE INTEGRATION PROJECT: 765kV TRANSMISSION LINE AND SUBSTATION

ENVIRONMENTAL IMPACT ASSESSMENT

(12/12/20/1187 and 12/12/20/1140)

COMMENTS AND RESPONSES REPORT

25 August 2008

Appendix ??:1 8 August 2008

Comments & Responses Report Version 2

Eskom Holdings Limited

Mokopane Integration Project

1objectives of the Comments and responses report

The Comments and Responses Report has the following objectives:

  • To provide a formal and integrated record of all the issues raised by Interested and Affected Parties (I&APs) and stakeholders, the responses provided by the EIA Study Team and/or the Project Proponent throughout the EIA process.
  • To provide a mechanism that allows all parties participating in the process (including the environmental authorities) to check whether the issues raised have been considered and where appropriate, adequately addressed by the EIA Study Team.

2how issues have been raised

Issues have been raised and recorded through a variety of mechanisms, these include:

  • Discussions held personally or telephonically.
  • Comments sheets received by fax, e-mail, post or at public and focus group meetings.
  • Via e-mails.
  • I&APs raising issues at public and focus group meetings.

3format of comments and responses document

Numerous issues have been raised, many of these are similar in nature, but may appear to also be contradictory as I&APs do not necessarily agree on matters. To effectively manage the issues raised, the issues have been divided into categories which would best reflect the nature of these issues. There may also be some linkages between the different categories. These are reflected in Table 3.1 below. The responses and or action to be taken have also been provided in the “Response Column”.

Table 3.1: Categories

No. / Category
1. / Agricultural Practices, Transmission Power lines and Compensation
2. / Social and safety issues
3. / Socio-economic development
4. / Nature reserves and Game farms
5. / TraditionalLand: Social and Cultural Practices, Compensation for loss of Homes and Land
6. / Aesthetic values/Visual impacts
7. / Technical and servitude management related to transmission power lines
8. / Strategic Planning Issues – in the study area
9. / Strategic Planning Issues – with regards to Eskom
10. / Environmental issues and Natural Environment
11. / Sense of Place
12. / Alternatives suggested
13. / Maps/other information
14. / Public Participation
15. / General/other issues.

4identification of stakeholders

It has not always been possible to identify the individual stakeholders that raised an issue at the various meetings as they may not have identified themselves clearly, or the issue was distilled out of a conversation involving a number of people. Where this has occurred, the following reference is made e.g. “Stakeholder – Lephalale Public Meeting”. Where possible, an individual’s name has been provided or the organisation with whom he/she is affiliated is listed. Written submissions have been referenced as such and copies are provided in Appendix ?. The attendance registers of the various public meetings are attached as Appendix ?. If however, I&APs feel that an issue has not been accurately captured and/or they wish to have their name attached to an issue, please contact the Public Participation Office.

Appendix ??:1 8 August 2008

Comments & Responses Report Version

Eskom Holdings Limited

Mokopane Integration Project

name / organisation / issues raised / response
1. Agricultural Practices and Transmission Power Lines and Compensation
Mr. J. Motlhagodi (Rustenburg Agricultural Forum, Reply Slip received via Post) / The Farmers and/or Traditional Authorities in the area should be given the opportunity to be responsible for clearing and keeping clean the servitudes in their area/on their farms, and be paid by Eskom to do so instead of bringing in outside companies who do not do the job correctly. / Noted. Comment passed onto Eskom for consideration.
Mr. C. Thompson (Iganu Game Ranch, attended Marken Public Meeting 19/06/2008)
Mr. P. Visser (Mahakala’s Game Ranch, fax received 07/07/2008)
Mr. C. Brown (Mahakala’s Game Ranch, email received 07/07/2008)
Ms. FH van der Heever (landowner, Potgietusrus DLU Focus Group Meeting 06/08/2008)
Mr. G. Van Rooyen (landowner, Potgietusrus DLU Focus Group Meeting 06/08/2008) / The relative impact on small farms in and around this area will be huge. / Comment acknowledged. Impacts on properties as a result of the proposed project will be investigated as part of the Impact Assessment Phase of the study.
What compensation will be available to the affected parties? / The Eskom negotiator explained to the stakeholders that internal and external valuations are done on their farms, so that a total understanding of their farms and businesses can be obtained. Compensation is based on current market-related prices and will be negotiated with each affected landowner.
Mr. G. van Zyl (Agri Lephalale, Lephalale Public Meeting 20/06/2008)
Mr. J. Porini (landowner, Lephalale Focus Group Meeting 04/08/2008) / It would be appreciated that once negotiations begin that the negotiations for settlements/compensation be held with organisations and not the individual farmers. A general asking price should be agreed upon. It is unfair that different prices are paid out for the same style/types of farms, people feel affronted by the different settlements. / The negotiations are based on business principles and are personal transactions based on the unique situation on each affected property. The Eskom negotiator explained to the stakeholders that internal and external valuations are done on their farms, so that a total understanding of their farms and businesses can be obtained.
If a group of landowners would like compensation to be considered based on collective activities that are being undertaken, this could be considered during the negotiation phase.
It is important to note that there is a confidentiality issue in terms of negotiating collectively with affected landowners. Individuals may not wish their private business to be made public. However, the broad principles and criteria of the negotiation process could be discussed with the various representative organisations to ensure a fair and equitable process.
The negotiations should be done with Eskom and the landowner individually and not through any organisations.
2. Social and Safety Issues
Mr. C. Thompson (Iganu Game Ranch, attended Marken Public Meeting 19/06/2008) / Displacement will affect the local villages and population. / Acknowledged. Impacts on local villages and populations will be investigated in the social impact assessment of the Impact Assessment Phase of the study. Programmes to address displacement of populations will be implemented.
Bakone, Batlokwa and Lebelo Traditional Councils (Bakone Traditional Office Meeting 10/06/2008)
Laka Traditional Council (Laka Traditional Authority Office 29/07/2008) / Protection must be provided on the towers so that the children can’t climb on them. In 1980 three children died in Bakenburg after climbing on the tower and touching the cables. / Acknowledged. Eskom will ensure safety is a top priority during the construction and operation of the power line.
All the villages have their cemeteries, grazing land and ploughing fields that must be considered when planning the transmission power line. / Acknowledged. Impacts on local villages, agricultural activities, heritage and cultural sites, etc will be investigated in specialist studies to be undertaken within the Impact Assessment Phase of the study.
The amaKgosi request a donation from Eskom to build better schools. / Noted. This request has been passed onto Eskom for consideration.
Seleka Traditional Council (Seleka Traditional Authority Office 29/07/2008) / What will Eskom do if the clinics or schools are affected by the lines? / Clinics or schools affected by the lines will be relocated as agreed with the affected parties. Relocated parties will not be worse off than they were prior to being affected.
Dikgale, Mashashane and Moletsi Traditional Councils (CapricornDistrictMunicipality Meeting 12/06/2008)
Laka Traditional Council (Laka Traditional Authority Office 29/07/2008)
Shongoane Traditional Council (Shongoane Traditional Authority Office 30/07/2008)
Lekalakala Traditional Council (Lekalakala Traditional Office, 12/06/2008) / The contractors must be introduced to the community. Once they are introduced they will be informed of the rules of the area. On the previous Eskom projects construction contractors damaged offices that the communities gave them to stay in. It is up to the contractors if they want to build camps or they want to rent rooms from the community. / Noted. These issues will be addressed in the Environmental Management Plan (EMP) for the project.
If any fence needs to be cut it must be fixed or gates must be put in. All the gates must be closed all the time. If they leave the gates open cattle will be lost or cattle will destroy farmlands.
Lekalakala Traditional Council (Lekalakala Traditional Office, 12/06/2008)
Laka Traditional Council (Laka Traditional Authority Office 29/07/2008) / If the line passes through this Traditional area in what way is the community going to benefit? The community does not have electricity and would like every household to have electricity. / Query referred to Eskom Distribution.
How is Eskom going to take care of the grazing land and farms during and after construction? / During construction, the construction site will be fenced off and access will be restricted. After construction, the site will be rehabilitated in order to make grazing and agricultural activities feasible, provided these do not interfere with Eskom infrastructure.
Eskom must be responsible for any damages that they have caused during construction and maintenance. / This will form part of the EMP. The EMP will form part of the contract between Eskom and the construction and maintenance contractors. The contractors will be responsible for the rehabilitation of any areas damaged as a result of their activities.
Mapela, Mokopane and Bakenburg Traditional Councils (Langa Traditional Office Meeting 13/06/2008) / A binding contract should be signed between Eskom and the communities before the construction starts. Eskom must do proper investigations once the line has been selected because there are graves that may need to be moved and the proper process must be followed. / Noted.
A Heritage Impact Assessment will be undertaken as part of the EIA process. This study will also consider graves. Information from the local communities on the location of these sites is invaluable as part of this process.
Should Eskom be granted authorisation to construct the line, a walk-through survey of the power line route will be undertaken by a heritage specialist in order to ensure that there is minimum impact on heritage sites (including graves).
3. Socio-economic development
Mr. C. Thompson (Iganu Game Ranch, attended Marken Public Meeting 19/06/2008)
Mr. G. van Zyl (Cambodia Overyssel Gemeenskapgroep, fax received 08/06/2008)
Mr. A. Swart (Marken Public Meeting 19/06/2008)
Mr. C. Mills (Tswana Game Reserve, Lephalale Public Meeting 20/06/2008)
Mr. D. Strydom & Mrs. B. Strydom (Mama Tau, email received 23/06/2008)
Mr. S. van Coller (Lindani Game Lodges, Vaalwater Farmers Hall Focus Group Meeting 05/08/2008) /
  • Construction of such a transmission power line will have devastating effects on the potential for inward tourist cash flow and the ability to maintain the existing fauna.
  • Severe business impacts on the tourism and hunting industries – a loss of jobs and property value will drop.
  • Tourists in this area come from Johannesburg and internationally, the transmission line will ruin the prime and pristine tourism area.
/ Noted. These issues will be investigated as part of the Social Impact Assessment in the Impact Assessment Phase of the study.
Mr. K. Basson & Mrs. E. Basson (Owners De Draai, fax received 08/06/2008)
Mr. A. Walker (Lapalala Wilderness, email received 25/06/2008)
Mr. J. Miller (Waterberg Nature Conservancy, 28/06/2008) /
  • Consideration of what will happen to the value of the land and investments in the Waterberg Biosphere area.
  • The permanent damage of a pristine area for the short-term gain of the limited lifespan of the mines in the area.
/ These issues will be investigated as part of the detailed specialist studies to be undertaken within the Impact Assessment Phase of the study.
This project does not include any mining activities.
Babirwa and Nkidikitlana Traditional Councils (Babirwa Traditional Office Meeting 11/06/208)
Seleka Traditional Council (Seleka Traditional Authority Office 29/07/2008) / How will the community benefit from the transmission power line? The odd job must be done by local people. / Construction and maintenance of a power line are generally highly skilled tasks. However, where unskilled or semi-skilled labour is required, this labour would be sourced from the local communities, where possible during construction.
Mr. C. Thompson (Iganu Game Ranch, attended Marken Public Meeting 19/06/2008and Marken Focus Group Meeting 06/08/2008) / Two transmission power lines running next to each other will severely alter the landscape, and for some of the small farms in the servitude a lot more productive land will be displaced. Many small farms will be totally out of income if two 765kV lines had to run through them. Does Eskom have answers for these farmers on their current loss in income due to the proposal of these lines on their land. / Acknowledged. These issues will be investigated as part of the detailed specialist studies to be undertaken within the Impact Assessment Phase of the study.
Mr. G. van Zyl (Agri Lephalale, Lephalale Public Meeting 20/06/2008)
Mr. R. Louw (Lephalale Public Meeting20/06/2008)
Mr. J. Oosterhoff & Mrs. M. Oosterhoff (Leopard Leap Lodge, Lephalale Public Meeting 20/06/2008)
Mr. A. Myburgh (Tholo Bush Estate, Lephalale Public Meeting 20/06/2008)
Mr. J. Parsons (Shayamanzi Game farm, Lephalale Public Meeting 20/06/2008) / This area is full of various industries, agricultural, wild animals/game reserves, hunting grounds and tourism lodges. An estimated 70% of clientele is international. The transmission power lines in this area could harm this industry. / Noted. These issues will be investigated as part of the Social Impact Assessment in the Impact Assessment Phase of the study.
Mr. A. Myburgh (Tholo Bush Estate, Lephalale Public Meeting 20/06/2008)
Mr. C. du Plessis (TOOG, Lephalale Public Meeting 20/06/2008) / The hunting farms in this area attract a number of tourists as they are exempt farms, the international tourists can come there all year round. Being exempt farms pertains to their permits to trade with game. This is the LimpopoProvince’s highest level of business. / Noted. These issues will be investigated as part of the Social Impact Assessment in the Impact Assessment Phase of the study.
Ms. FH van der Heever (landowner, Potgietusrus DLU Focus Group Meeting 06/08/2008) /
  • Their property was purchased with an existing 400kV line on it, if another line comes onto this property it will affect their eco-tourism business.
  • Where can they get the servitude agreement and conditions for the existing line on their property?
/ This issue will be investigated as part of the Social Impact Assessment.
Mr Bobby Richardson (Lands and Rights, Eskom) gave his details to Ms van der Heever and he will assist her in obtaining the necessary information.
Mr. L. de Beer (Mogalakwena Municipality, Potgietusrus DLU Focus Group Meeting 06/08/2008)
Mr. J. Oosterhoff (Leopard Leap Lodge, Vaalwater Farmers Hall Focus Group Meeting 05/06/2008) / If he was a landowner whose property would be affected by the transmission power line, is it true that he cannot do anything underneath the lines i.e. farm? / Eskom has certain restraints about what activities can occur in the servitude.
Mr. R. Baber (Waterberg Biosphere Reserve, Vaalwater Farmers Hall Focus Group Meeting 05/08/2008) / There is very little data available on the existing environment, eco-tourism and tourism in this area, will there be a thorough socio-economic study on a more detailed level than desktop level. / This will be conducted during the EIA Phase of the process, and the social specialist will contact landowners who have indicated that they would be willing to be interviewed by her.
Mr. K. Erasmus (EBB, Marken Focus Group Meeting 06/08/2008) / The impact of the people should not be considered more than biodiversity. There are many proclaimed conservation areas in the southern portion of the study area, but that does not mean that the northern portion has less ‘conservation’ areas. / Stakeholders are encouraged to provide the Public Participation Office of all details regarding these conservation areas.
Mr. W. Esterhuizen (Marken Safaris, Marken Focus Group Meeting 06/08/2008) / The farms in this area are interdependent on each other, they having gaming/hunting rights on each others property therefore the directly affected farms are not only impacted, the line of site and surrounding farms are all affected. / This will be investigated as part of the Social Impact Assessment.
Mr. A. Myburgh (Tholo Bush Estate, Lephalale Focus Group 04/08/2008)
Mr. G. van Zyl (Agri Lephalale and TOOG, Lephalale Focus Group Meeting 04/08/2008) / This proposed project is affecting his sales of property daily. If there is a preferred option they need to know now so as to make decisions regarding their future planning. / It has been determined that the Northern Route is the least impacted route, but the detailed EIA study will confirm this.
4. Nature Reserves and Game Farms
Mr. C. Thompson (Iganu Game Ranch, attended Marken Public Meeting 19/06/2008) / The Northern Route for the proposed transmission power line, Route 2, passes potentially through Iganu Game Ranch and the surrounding based farms. / Noted. Detailed maps of the study area and the proposed power line corridors will be made available shortly to the public. These will assist in determining the exact properties which may be directly affected by the proposed alternative alignments.
Mr. K. Maude (Swebeswebe Wildlife Estate, reply slip received and phone call taken by Terry Baker, 23/06/2008)
Mr. G. van Zyl (Tambotie Overyssel Gemeenskapgroep, fax received 08/06/2008)
Mr. K. Basson & Mrs. E. Basson (Owners De Draai, fax received 08/06/2008)
Mr. J. Oosterhoff & Mrs. M. Oosterhoff (Leopard Leap Lodge, email received03/06/2008)
Mr. A. Myburgh (Tholo Bush Estate, Lephalale Public Meeting 20/06/2008)
Mr. C. du Plessis (TOOG, Lephalale Public Meeting 20/06/2008)
Mr. A. Walker (Lapalala Wilderness, email received 25/06/2008)
Mr. J. Miller (Waterberg Biosphere Conservancy, telephone conversation 01/07/2008)
Mr. P. Visser (Mahakala’s Game Ranch, fax received 07/07/2008)
Mr. C. Brown (Mahakala’s Game Ranch, email received 07/07/2008) /
  • There are declared nature reserves in this study area, e.g. D’Nyala Nature Reserve.
  • The Waterberg Biosphere runs through the middle section of the study area, and it would be a travesty to put Transmission Power Lines through it as it would impact on the plants, animals and birds.
  • The Waterberg Biosphere is a pristine valley which has been rehabilitated after years of neglect, several millions of Rands in investments; unparalleled water coverage with wildlife and migratory birds and ducks will be negatively impacted if the Power Lines go through this area.
  • The Biosphere is a UN initiative, and is one of few in the world; it is a designated area over a core area which is considered bio-diverse in its natural state. This is a project on a National Level, why does the Government not allow such an option to be possible?
/ Noted. Detailed maps of the study area and the proposed power line corridors will be made available shortly to the public. These will assist in determining the exact properties which may be directly affected by the proposed alternative alignments.