MKE EP-401Version 3 enPage 1 (9)

examination procedure
Inspection of Connected Cable / Document
MKE EP-401
Version
3en
Date
2006-03-27
Replaces
2 en

1scope

This examination procedure is applicable to connected cable.

2objective

Through inspection of the installation results verify and record that it fulfils the acceptance criteria in point 4.

3MEthod

The inspection is to be performed as a visual inspection, tests after installation and as a check of wiring and connections. It is documented according to the extent given in the Inspection Plan or in the simplified way, to the extent, which is marked in the comprehensive Inspection Certificate.

4ACCEPTANCE criteria

The equipment shall be installed according to valid documentation and MBE. The result shall fulfil the requirements demanded including additional requirements in the manufacturer’s instructions, if any. The performance shall in all parts be professionally and functionally correct.

Test after installation and connecting is made in order to verify that the cable is not damaged and that it has kept desired characteristics after installation. The result of the tests depends on the type of cable involved. There is however a general requirement that electrical circuit, which are galvanic isolated from one another or to earth, shall have an insulation level on at least 100M.

  • Test of insulation resistance is done according to MKE EP-402
  • Test of transmission characteristics within tele and computer cables is done according to MKE EP-403.
  • Test of attenuation within optical cable is done according to MKE EP-404.
  • Inspection of conformance is done according to MKE EP-405

Deviation in performance, if any, from given documentation or installation instruction is to be treated and approved before inspection.

If nothing else is stated the inspection shall be performed according to point 6 ”checklist ”in its applicable parts.

5documentation

Inspection performed is to be documented according to Inspection Plan or in the summarized Inspection Certificate.

6checklist

Supplier / Suppliers ref
Customer
Installation binder / Room
System, equipment / Others
Element no. / Description / Inspection made date. +sign / Deviation/ note no.
401 / Connected cable
401.100 / Self-inspection, inspection of work performed correctly
401.101 / Installed according to documentation
Without deviation  With deviation 
401.102 / Inspection compared to following installation instructions, which have been used in the work: MBE MI 1xxx, design drawings or other additional instructions e.g. the suppliers’ instruction.
1 ......
2 ......
3......
4 ......
5 ......
401.103 / Markings mounted.
401.104 / No visible damage on material.
401.105 / Contact pressure moulding documented in connection documentation.
401.106 / Terminals and connecting device of right type right placed and right mounted
401.107 / All terminal marking of right type, right marked, on right place and right mounted
401.108 / All cables and cable marking of right type, right marked, on right place and right mounted
401.109 / Cables and conductor insulation not squeeze against sharped edges or metal covering. No visible damage on insulation of cables
401.110 / Protection and screening of grounding correct connected. Groundingof cubicleandcubicles arranged.
Atconnectionagainst painted surface is painttaken awayand connection surfaceaccuratelycleaned.
401.111 / Spare parts is fixedand isolated
401.112 / Enclosuresand cubiclescleanedout- and internally
401.113 / All the terminal tighten and busbar jointing torque tighten.
Torque tool
Typeand number:
401.114 / Wire wrappingof bare conductorwho is rightarranged
Wire wrapping tool:
Type and number:
Element no. / Description / Inspection/made Date+sign / Deviation/ Note no.
401 / Installation inspection of installed cable
401.200 / Installation inspection, inspection made from demanded requirements.
401.201 / The plant installation shall be performed in order to fulfil the equipment’s desired characteristics.
401.202 / Markings
401.203 / Seismic requirements.
401.204 / Electrical safety requirements
Earthings are shown in MKE EP-701 
401.205 / Plant specification requirements.
401.206 / Adjustment to operation and maintenance, and to usefulness.
401.207 / Adjustment to existing installation.
401.208 / Environment requirements, choice of material, choice of methods, protection class
401.209 / Separation requirements jeopardy etc.
401.210 / Test of insulation resistance according to
MKE EP-402.
401.211 / Test of transmission within tele and computer cable performed according to MKE EP-403.
401.212 / Test of attenuation within optical cable performed according to MKE EP-403.
401.213 / Conformance check “green-marking” performed according to MKE EP-405
401.214 / Inspection after final installation, after cable installation and connection cap installation and mechanical safety etc.
401.214 / Inspection terminaland adapter
401.215 / Inspection Wire wrap
401.216 / Inspection Reserv wires
401.217 / Inspection Purity

7comments/guidance to inspection element

The purpose with these comments is to facilitate the Self-Inspection and Installation Inspection. It shortly summarizes MBE 401 and mentions the most common working elements. For detailed information look further in MBE and other referring documents (ELSÄK-FS, TBE) and plant specific design instructions.

7.1Inspection of cord marking

Example:

  • Inspect type of marking, colour and orientation.

7.2Inspection of PE- and PEN- marking

Example:

  • Protective earth conductor (PE) shall be marked green/yellow in all its length
  • PEN-conductor shall be green/yellow and be equipped with an added light blue colour marking in both its ends.

7.3Wire marking

Wires should be marked with numbers in both ends. Type, colour and orientation are inspected.

7.4Wiring

The inspection concerns wire laying in enclosures, cabinets and components.

7.5Inspection of no visible damages

7.6Inspection of the performance of wire-laying

Requirements on wiring according to technical provisions TBE 104 and118 should be fulfilled in applicable parts.

Example:

  • Wires should be laid in canals, conduits or shield coil
  • Wires should be laid within safe distance from warm components. Protection are to be found against squeezing, friction, wearing and tearing off. At conductor wiring through metallic objects, edges should be rounded chamfered or being equipped with an edging.
  • Stress relieving of cables and conductors are to be found for connection to each terminal
  • Cable, who has not been connected from below, should be laid in order to prevent water to regain admittance into the apparatus.

7.7Connections

Inspection considering connections of cable conductors, shields and wires in enclosures and components

7.8Inspection of the cable fitting

Example:

  • Cable fittings shall be correctly tightened.
  • Correct dimension (the cable diameter is not to be adapted with e.g. insulation tape).
  • Cable fittings (plugs for blinds) should be made of nickel-plated brass.

7.9Inspection of protective earthing.

  • Requirements on the performance of protective earthing and connection to protective earthing according to TBE104 and 118 and Installation Instructions are to be fulfilled.
  • Cabinets and enclosures for inspection equipment should have earth connection, which gives a safe and permanent earthing of all metallic parts. Serial grounding is not allowed.
  • Good earth terminal should have been achieved if screws have been used for earthing (only allowed for small units) through paint being removed or that toothed washers or screws been used.
  • If components have been installed in doors, hinges are not approved as earth connection. They have to be connected with a flexible cord.
  • Concentric conductor and drain wire or cords in cable with conductors, wich are of the same colour, If they are used as protective conductors, they are to be fitted with green yellow tube.
  • Current Transformers secondary winding should be connected to earth near the current transformer in such a way that earthing is performed on the side, which is directed towards the bus bar.
  • Voltage Transformers secondary side should be connected to earth near the voltage transformer.

7.10Inspection of screen earthing

Requirements on performed screen earthing and connection to protective earth according to TBE 104 and 118. MBE should be fulfilled in its practical parts.

Example:

  • Joints of shielded cables, e.g. in junction boxes, where shields should be jointed without being connected to earth, an insulated shield bar should be of use. Disturbance conductors should be insulated with yellow tubing in new installations, and existing color at completions. Screened cable should be unsheathed at connection terminal in cupboard and connected with shortest possible screen conductors (<5 cm)
  • The individual screened cable must be peeled at the bottom of the cupboard and individual screen will be taken off first at the connection terminal.

7.11Inspection of screwed terminals

  • Internal wiring are to have maximum two conductors connected to the same screw terminal point and when done, under the following conditions:
  • Single-core and stranded conductors are not to be connected to the same terminal. Exceptions are allowed for multiple conductors with a sleeve pin.
  • If two single-core conductors are connected to the same terminal, the very same are to have the same diameter.
  • If two stranded conductors are connected to the same terminal, the very same are to have a proportion between the conductors diameter that are not bigger than 2:1.
  • Within connection of stranded conductors in connection, where the conductors are not all to well united in the terminal, lugs should be used.
  • Only two cable lugs are allowed to be connected into each terminal A washer should always be used under nut or screw head. Cable clips must be installed in such angle position that mechanical deformation does not occur within tightening. Ring cable clips should always be installed with screw, only clamping under clamps is not allowed
  • Loose strands are not to exist outside the connection. Cable clips are not to be bent/crocked.
  • Termination of copper conductors should be done with contact crimped cable lug (plane washer and dome washer) or with clamping if such are available. Conductors should have such length that a terminal switch can be made. i

7.12Inspection of soldered terminals

Requirements of soldered connections according to TBE 105 should be fulfilled

Example:

  • Soldering is normally not allowed for connections other than electronic equipment.
  • Make sure that soldered seam has not been exposed to bend or tensile stress.
  • Make sure that soldering has only been done for connection intended for soldering.

7.13Inspection of contact pressure moulding

Requirements according to TBE 104 should be fulfilled

Example:

  • Contact crimping is only to be used for stranded conductors.
  • Contact device and conductors should be adjusted to the correct area.
  • No loose strands are to exist outside the contact element.
  • Cracking or other types of visible damages are not allowed.
  • Make sure that prescribed check dimension is held.

7.14Make sure that that extra conductors is fixed and insulated

Requirements on wiring according to TBE 104 should be fulfilled.

Example:

  • Extra cords should be separated from used cords and at their ends be equipped with top sleeves.

7.15Inspection of cleanness

Make sure that the enclosures are cleaned

7.16Inspection of performed connection

Requirements according to Installation Instructions of the object in question are to be fulfilled.

7.17Inspection of connection of hot objects

Example:

  • Cables shall be securely fixed beside the components, so that tension stress in the cable not can load the conductors.
  • Cable, who has not been inserted from below, shall be laid in order to prevent water to regain admittance into the device.
  • Insertions from above are to be avoided.

7.18Inspection of wire wrap.

Wire wrap shall be performaccording toMBE and

Commendationin SS-EN60352.

Example:

  • Inspect the wire lengthis adjusted so that wire not extend round wirepin sharpangle.
  • Inspect the wrapping wireis relocated so that will be tighteninsted being unwind about the willed be set for extension strain
  • Inspect that wrapping is performed so that high conjunction three wire must be loosened about a bond wire will be replaced.
  • Inspectthat fieldwith wrapping wirehas semi-protected.
  • Wire wrapshall arrangedby speciallyeducationpersonnel