Midway City Restroom Remodel Project
Men’s Restroom
Women’s Restroom
Scope of Work
Project will consist of the removal of the following items:
Floor and Wall Tile
Toilets
Sinks
Urinal
Old Partitions
Light Fixtures
Sanitary Dispensers
Air Fresheners Dispensers
Paper Towel Dispensers
Toilet Dispensers
Soap Dispensers
Wall Mirrors
The following items will be supplied by Midway City:
Replacement Wall and Floor Tiles
New King Size Toyo Toilets
New Handicapped Accessible Sinks
New Restroom Portions
New Light Fixtures
New Paper Towel and Toilet Tissue Dispensers
Soap Dispensers
Air Freshener Dispensers
Paint for walls and ceiling
Wall Mirrors
The contractor will be responsible for all other items needed to perform the remodel of project:
Adhesives, Mortar, quicksets, plumbing parts, electrical connections. Misc. parts, etc...
Project Description:
The Midway City Community Center Buildings Men’s, Women’s and Handicapped Restrooms will be involved in the remodel process.
- The removal and disposal of old restroom fixtures; (toilets, sinks, portions and light fixtures), from the men’s and women’s restroom.
- The removal and disposal of all existing floor tiles from both the men’s and women’s restroom.
- The Sanitary dispensers (soap, hand towels, toilet paper and air fresheners) will need to be removed from the wall and saved for future use. The City will have its supplier supply us with new dispensers.
- New tile will need to be installed on the floor and walls of both the men’s and women’s restrooms to match the tile that is in the handicapped restroom.
- New restroom partitions will need to be installed in all three restrooms.
- New Restroom fixtures will need to be re-plumbed and installed in both the men’s and women’s restrooms.
- Ceiling Light bar will need to be rehung and wired if needed.
- Install new wall mirror in both bathrooms.
- Upper portion of the wall and ceiling will need to be repainted.
- Trim and finish work supplies will be furnished by the contractor.
- The contractor will be responsible for haul off of all debris and construction waste.
- Blinds are new, they will need to be removed during the renovation and then rehung.