1
MECO Magnet System Safety Review
1005S – 3rd Floor
June 3, 2003
8:30 – 8:40Introduction D. Phillips
8:40 – 9:10MECO Description/Overview M. Hebert
9:10 – 9:40Magnet Systems Introduction B. Smith
9:40 – 9:55Solenoid Protection from Primary BeamK. Brown
9:55 – 10:25Proposed Quench Detection and Protection System Introduction B. Smith
10:25 – 10:35Break
10:35 – 11:30Magnet Structure/Structural Analysis and Cryostats P. Titus
11:30 – 12:00Cryogenic Process and Control Description, Relief Valve Calculations,
and ASME Code ComplianceB. Smith
12:00 – 1:00Lunch
1:00 – 1:30Explosion Risk of Cryogenic Liquids Exposed to Ionizing RadiationW. Meng/B. Smith
1:30 – 1:45Anti-proton Stopping WindowD. Weiss
1:45 – 2:00Magnet PS and Electrical Safety Plan W. Meng
2:00 – 2:15ODH, Maintenance and Confined SpaceD. Phillips
2:15 – 2:30Magnet Installation Plan, Lifting Fixtures, Critical Lifts P. Titus
2:30 – 3:00Comments, Discussion & Summary of Major Action ItemsD. Phillips
9/28/2018
1
MECO Magnet System Safety Review
1005S – 3rd Floor
June 3, 2003
While all committee members are encouraged to attend the entire presentation, below is a table of minimum recommended viewing:
Time / Subject / ALARA / ESRC / ASSRC / CSC / RSC8:30 – 8:40 / Introduction / X / / / / X
8:40 – 9:10 / MECO Description / Overview / X / / / / X
9:10 – 9:40 / Magnet Systems Introduction / X / X / / / X
9:40 – 9:55 / Solenoid Protection from Primary Beam / X /
9:55 – 10:25 / Proposed Quench Detection and Protection System Introduction / X / X
10:25 – 10:35 / Break
10:35 – 11:30 / Magnet Structure / Structural Analysis and Cryostats /
11:30 – 12:00 / Cryogenic Process and Control Description, Relief Valve Calculations, and ASME Code Compliance / X
12:00 – 1:00 / Lunch
1:00 – 1:30 / Explosion Risk of Cryogenic Liquids Exposed to Ionizing Radiation / / / X
1:30 – 1:45 / Anti-proton Stopping Window / X / X
1:45 – 2:00 / Magnet PS and Electrical Safety Plan / /
2:00 – 2:15 / ODH, Maintenance and Confined Space / / X
2:15 – 2:30 / Magnet Installation Plan, Lifting Fixtures, Critical Lifts / X / X
2:30 – 3:00 / Comments, Discussion & Summary of Major Action Items / X / X / X / X / X