Market Advanced Readings and Settlements

(MARS) Taskforce

ERCOT MET Center RM 206B

Monday, March 9, 2009

1:00 PM – 4:00 PM

Conference Call Numbers:

Conference Bridge Numbers:

User Dial-In #: 512-225-7280 Password: 0517

Chairperson #: 512-225-7281 Password: 6611

1:00 Antitrust Admonition

·  ERCOT strictly prohibits market participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, subcommittees and working Groups to be reviewed and followed by each market participant attending ERCOT meetings. If you have not received a copy of these Guidelines, please send an email to Sheila Letkeman at to receive a copy.

·  Introductions

·  Approve January 12, 2009 MARS Meeting Notes

1:15 PR80027_ Project Implementation Plan (ERCOT)

1:30 Review of LSE File format document – Key Points and Corrections (ERCOT)

1:45 Areas where additional Taskforce discussion and/or processes may be needed:

What is the frequency of the LSE Interval Data Report from ERCOT to the TDSPs that provides ERROR response codes to files, final decision? -

·  One report is created per day containing files/records processed between midnight and midnight

·  One created each day for each file received from the TDSP (expectation is that files from the TDSPs will contain between 10,000 and 50,000 transactions)

(MARS) Taskforce

Meeting

ERCOT MET Center RM 206B

Monday, March 9, 2009

Areas where additional Taskforce discussion and/or processes may be needed:

o  What extracts and web services will be available to market participants at project go-live?

·  Changes impacting 727?

·  When effective?

·  Others?

§  How will TDSPs respond with 867_02 historical usage on AMS meters?

§  When ERCOT is ready to start receiving 814_20 Load Profile changes for AMS would the TDSP need to provide an 814_20 Load Profile update for the AMS profile on a meter read date?

·  If yes, how will the volume be managed for each TDSP?

§  What about Annual Validation being performed around this time?

·  814_20 Volume

·  Resources needed to manage effort

·  Time needed for issue resolution

·  Value?

§  Any additional questions/issues that need to be discussed?

2:15 January 12, 2009 Action Item:

·  Sub-team developed Retail Market Guide Revision Request (RMGRR) documenting the Interim Settlement Solution for AMS

· 

3:30 Next Step for Taskforce/Action Items

4:00 Adjourn