Objective
Main objective:To study and increase total cutting room efficiency
Sub-objectives:
a)“Time & Motion Study” of different operations in spreading & cutting leading to:
1) Determination of efficiency of the worker:
The purpose is to optimize on manpower utilization. Put the best person to best use and avoid multitude of workforce wherever not required.
2) Identification of bottleneck operations:
Bottlenecks increase the throughput time, which is a significant loss on the critical time. Bottlenecks should be identified and taken care of immediately to save on cost and time.
3) Reduction of idle times whenever possible:
Huge expenditure is incurred on machinery. The interest of that investment should always be kept in mind. As such, machine idle time is a disguised expenditure in form of loss of interest on investment. Continuously running machine is an investment justified.
4) Maximum utilization of automatic spreading & cutting systems: Automation is justified only if it is used to the fullest extent. The intention is to de-skill and increase production, and wherever possible economize on cost. All the three purposes should be achieved; otherwise the advantage of automation may not be one hundred percent.
b) Study of the existing layout with reference to material flow & explore scope of improvement:
Layout affects production flow. It should be conducive to material movement, and at the same time technically correct. Haphazard layout may obstruct movement thus costing on time and fatigue, and in turn resulting in loss of time and energy.
c)To utilize the variable resources manpower efficiently in the cutting section:
It will help in target setting and work monitoring for the activities of cutting room.
Our project, thus attempts to strike at a balance in the production activity- cutting department. And the balance is of the most critical components - Man, Machine and Material…
CUTTING DEPARTMENT
Cutting is the very first process in garment manufacturing. The cutting department receives the fabric from the fabric department after inspection.
Objectives of the department
- Cutting according to the master patterns with 100% accuracy.
- Ensuring 100% quality in cutting.
- 100% issue of all the parts to sewing section.
The cutting floor is a combined unit for spreading, cutting, ticketing and bundling. The work of cutting department starts right from the point of order being received from the buyer by the merchandising department. The CAD department prepares the marker using the patterns prepared by the Sampling Department. It also prepares the CAD-Consumption Worksheet and makes estimation for the consumption of the fabric for that particular order. The results are then communicated to merchandiser.
The cutting department at Arvind mills limited; Vadsar unit is an advanced cutting unit. It uses advanced Gerber technology for spreading and cutting. Manual spreading is also done here. Cutting department also has straight knife and band knife. The model no. of these machines has been mentioned later in this section. Band knife is used to cut small components like moon patch, placket, sleeves etc. The capacity of the cutting department is 13000-16000 pieces per day. The department head is Mr. Mittal.
Hierarchy of the cutting department
MATERIAL FLOW
Total number of lights:41
Total number of ventilators:24
Shift wise manpower of cutting department for Gerber:
Process / 1st Shift / 2nd Shift / 3rd Shift / Total / Excess/shortReq. / Actual / Req. / Actual / Req. / Actual
Spreader / 8 / 7 / 8 / 7 / 8 / 7 / 21 / -3
Gerber / 3 / 3 / 3 / 3 / 3 / 3 / 9 / 0
Ticketing / 3 / 3 / 3 / 3 / 3 / 3 / 9 / 0
Bundling / 5 / 5 / 5 / 5 / 5 / 5 / 15 / 0
Collar lay / 2 / 3 / 2 / 3 / 2 / 3 / 9 / 3
Cuff lay / 2 / 3 / 2 / 3 / 2 / 3 / 9 / 3
Band knife / 2 / 1 / 2 / 1 / 2 / 1 / 3 / -3
Cuff overlock / 3 / 2 / 3 / 3 / 3 / 3 / 8 / -1
Parts mix / 2 / 2 / 2 / 2 / 2 / 2 / 6 / 0
Heat parts mix / 2 / 2 / 2 / 2 / 2 / 2 / 6 / 0
Fusing / 5 / 3 / 5 / 4 / 5 / 4 / 11 / -4
RBK parts mix / 6 / 5 / 6 / 6 / 11 / -1
Manual cut, recut / 5 / 6 / 5 / 6 / 5 / 4 / 16 / 1
Total / 48 / 45 / 48 / 48 / 42 / 40
The cutting department is divided into two parts one for spreading and cutting of solids and other for stripes. For stripes both spreading and cutting is done manually. For solids automatic spreader and CAM do spreading and cutting. The fabric that has to go for washing is spread manually and cut into panels. For stripes 2 contractors have been employed. First with 13 labors and second with 18 labors.
Working procedure
- Issue of fabric
- Easing process.
- Spreading of lay
- Marker laying (in case of manual cutting)
- Cutting of cakes
- Sorting & stickering
- Bundling
- Issue to sewing room
For a particular order the amount of fabric, which is required for the order, is determined by the PPC. In Arvind mills limited no extra fabric is ordered like in other garment industries generally 5-10% extra is ordered. Since the fabrics presently were all from Arvind mills textile unit only so no checking is being done. If fabric is taken from some other unit then 10% random inspection is done .if three roles simultaneously is found to be defective then the whole lot is rejected.
The fabric is kept in shelves according to lot wise, roll wise and a report of the fabric received is generated which contains information like lot number ,style number. The information is kept with the store in charge.
Various Stages in Cutting Room of Arvind:
When a particular order is approved from the buyer planning is made by PPC department to execute the job. PPC sends batch order in knitting room for the fabric according to buyer’s demand. All the information related to fabric like GSM, dia, shade, and quantity etc. is given in “batch order” form.
A batch of knitting room is complete order requirement that consists of everything such as fabric, trims (collar, cuff).
Knitting department completes the order and sends fabric rolls to the stores in cutting room.
Process flow of solids cutting:
Spreading on automatic spreader
CAM cutting
Ticketing
Bundling
Work on Cut parts (optional)
Inspection
Cut parts send to warehouse
The cut parts before inspection are also sent to embroidery, heat transfer printing, fusing and in some cases bottom hem.
Process flow of stripes cutting:
Opening of fabric roll
Cutting of blocks
Making of pattern on block
Cutting
3 straight knifes are used for cutting of laid blocks. Shears are used for cutting of panels. A piece of stripes is on the pattern given for matching by the Sampling department.
Fabric Stores:
Receiving of fabrics:
Fabric comes to stores directly from knitting house. For every particular batch samples comes with audit report from audit department in process house of knits. Audit report contains all information regarding the fabric and trims of that particular batch.
Storing of fabric:
Fabric; is stored according to the buyer’s name. Every buyer is allocated a specific rack in storeroom, so batch for that particular buyer is stored in that rack.
There is no further segregation in the warehouse area.
Issuing of Fabric:
Cut plan department sends the required k&p no.of fabric with other data to the store incharge. Required fabric is then allocated to cutting room from the stores.
Fabric rolls are received in trolley. It is ensured that all fabric rolls are loaded uniformly. One trolley carries a max of 15 rolls.
Easing Of The Fabric (Relaxation)
- After the issue of fabric if fabric is single jersey it is taken for relaxation process.
- Here fabric is simply unrolled by the machine.
- In this section handling of fabric is done manually bare handed.
Marker planning and marker making:
Marker planning is done in other unit. In this unit, just arrangement of marker is done according to the width of the fabric and gsm of the fabric. New marker is then uploaded in the cam machine.
Lay planning:
Lay planning is done in data-entry department according to the marker plan and the order of the customer.
Spreading
The main objective of spreading is to spread the fabric lay accurately as per the length of the maker with minimum waste at end of a lay.
Types of fabric laying:
- Face to face alternative plies: For symmetrical pattern pieces, and fabric which is stable spread face to face, the fabric can be spread along face up and immediately back again face down.
- Face up alternative plies: For asymmetrical as well as symmetrical pattern pieces and fabric which is stable spread all the same way up, the fabric can be spread along and immediately back again.
- Face up all plies in the same direction: For asymmetrical as well as symmetrical pattern pieces and fabric which is stable all the same way up, the spreader spreads in one direction only.
- Face to face all plies in the same direction: For symmetrical pattern pieces, and fabric, which is stable face to face, the spreader spreads in one direction only.
Types of laying methods
Automatic spreading: Automatic spreader is used to lay honeycomb, pique, and single jersey fabrics of both open width and tubular.
- Automatic spreading
2. Manual spreading
Automatic Spreading:
Automatic spreading is done for the solid dyed fabric only. After relaxation of fabric; fabric is kept on the spreading tables. From here they are loaded on automatic spreader.
Features of automatic spreader
MODEL: GERBER spreader SY101
- Preset: it sets no of plies required
- 0 point: sets the position of the machine beyond which it cannot move
- Allows zigzag and face one way laying
- Has a sensor which stops the machine if it runs out of fabric
- Dancing bar: checks the tension of the fabric while being laid
- Distance to be traveled by the spreader i.e. the length of the marker is fed into the spreading machine system.
- Maximum speed of the machine 100mtrs/min
Off stndrd time in % / TOTAL / 7-june / 6-june / 6-june / 4-jun / 4-june / 3-june / 3-june / Date / Gerber off standard time
A / B / A / B / A / B / A / Shift
1 / 1 / 1 / 1 / 1 / 1 / 1 / Gerber no.
0.00% / 0 / Marker not ready / Auto cutter off standard time
6.48% / 560 / 225 / 65 / 30 / Machine break down
0.00% / 0 / Marker width issues
12.04% / 1040 / 45 / 105 / 170 / 90 / No feeding
0.00% / 0 / Power failure
18.52% / 1600 / 225 / 45 / 105 / 65 / 170 / 30 / 90 / Total off time
8640 / 1440 / Total min worked
Manual Spreading:
Manual spreading is done for the yarn died fabric and for the fabric that has to be sent for washing. After the fabric is issued from warehouse, it is first blocked, then two persons lay fabric according to the length of marker.
Generally lay is of length of one full piece of t-shirt. A layer of 65-100 pieces is made according to the cut plan. During spreading all the plies are matched stripe to stripe on both the sides by workers.
A separate room is allotted to stripe spreading, cutting and bundling the fabrics which were yarn dyed.
Bundle checklist & Bundle card generation:
Bundle card is generated after the spreading of the lay is done. Bundle card is specifically the information about that certain bundle viz; k&p no., roll no., pieces in that bundle, size etc. this bundle card is made on the basis of the lay data.
Cutting:
Cutting is done by automatic CAM machine for all the fabrics except yarn dyed fabric. For the yarn dyed fabric manual cutting process is used. In manual cutting machine lay is cut by straight knife fabric.
Trims are cut on the band knife machine in a separate area according to the cut plan. Trims are cut in accordance to the main body material of required piece.
Cutting on Automatic Machine :
- First the lay is transferred from spreading table to cutting area.
- First required cut program is selected form the CAD machine
- Particular parameter is set on Gerber cutting machine according to requirement; it consists of speed of blade, area for movement etc.
- The lay is cut in cakes of required
Numbering & Bundling:
After the layer is cut the cut pieces are sorted out according to the different rolls. The sleeves, back, front, and placket pieces of one roll are kept together and the sticker which was used during the laying of the layers is sticked on the cut pieces accordingly and the pieces are bundled.
A job card is attached to every bundle. This job card contains all the information about the bundle and plays an important role till the packing of the garment is done.
Fusing/Heat seal:
Fusing is done for the placket, cuff, collar of the shirts. Different companies/ brands have different requirement for fusing and heat sealing.
Heat sealed machine
Parameters required for the M&S
Time -8 to 10 seconds
Temperature- 185 0C
Pressure – 6 bar
Parameters required for Reebok international And Reebok Domestic
Time - 8 seconds
Temperature - 180 0C
Pressure - 6 bar
Slit making fusing machine
In slit making fusing machine folders are attached. Canvas and bone both are passed together through the folder.
Bone width = 2.4 cm
Canvas width = 0.8 cm
Ready width of the slit = 1 cm
Machine name
HASHIMA HPM – 600B
Parameters for fusing machine (slit making)
Temperature - 140 0C
Pressure - 2kg/cm2
Maximum pressure that can be used is 5kg/cm2
Pressure gauge starts from
- 1kg/cm2
- 2kg/cm2
- 3kg/cm2
- 4kg/cm2
- 5kg/cm2
Fusing machine for placket , collar etc.
Parameters are
Time - 5 seconds
Temperature - 150 0C
Pressure 5 kg
Cut parts inspection:
After all the parts are introduced in a bundle with the bundle card the bundle is checked randomly. In cut parts inspection pieces are checked for the sizes fabric fault and cutting fault. Nearly 10% of the bundles are checked.
Tally of the bundle with information on the job card regarding k&p no., shade, size and no. of pieces is done. 10% visual audit is done. Check list is made here.
Observations & Suggestions
Fabric inspection department:
Fabric inspection is done for each and every roll from a batch. Inspection is done for the fabric faults and to check the width of each roll of fabric.
- But it was observed that every bundle was not being checked for the width.
- Mostly due to workers being uneducated about faults many times roll with faults are passed over to audit department.
- Sometimes due to lac of knowledge defected fabric is passed and for the same reason less defected fabric is bundled under defected category.
- No humidity and temperature measuring instruments are available.
- GSM of fabric is taken without drying it.
- No instruction is given to rolling operator about the dimension of fabric to be cut for GSM measurement.
- GSM of roll is taken from very localized fabric area.
Suggestion:
- Each and every fabric roll must be checked for width at least two times; at start of roll and at middle of it.
- Correct information regarding roll must be fed in slip.
- It must be tried to check the GSM of each roll of fabric.
- Employee education is very necessary here.
- Samples of defected fabrics or photographs of them should be made available to operator.
- Due to excess humidity and temperature,there is more relaxation allowances for worker which decreases overall on standard time.
- Due to moisture contamination observed GSM of fabric may vary from actual one.
- Due to unspecified dimension of cut part which is utilized for GSM measurement leads to fabric wastage.
Fabric audit department:
In fabric audit department 3-4 rolls are checked for width and gsm of the fabric along with the fabric fault.
- Many time GSM of the fabric changes from roll to roll and also in the same roll.
- Same thing happens with the width of the fabric.
- But as each bundle is not checked these faults pass unnoticed to cutting room
Suggestion:
- Cut part which is choosen for GSM measurement should be taken from different location of fabric roll and avg of different measurement should be marked as GSM of fabric.
- Width of the fabric should be taken from different phases of fabric roll ie 1st check when 15 mts are roll is finish.
2nd measurement should be taken at middle of rolling process and third at last.
Fabric Warehouse:
- There is no check of fabric prior to storage in the warehouse.
- Fabric is not segregated according to width or gsm of fabric.
Relaxation of the fabric:
- No proper relaxation machine.
- Machine that is used does not have proper attachments.
- Fabric handle is done manually. This causes fabric disturbance and relaxed fabric is gets ruffled.
- No accountability in this department.
Suggestion:
- Spiral rollers should be used instead of plain rollers.
- Tray should be used in which fabric is collected and loaded to spreading machine along with the tray.
Spreading:
Automatic Spreading
- Running speed of the machine is higher than required
- Used speed of machine is very low in the range of 7m/min.
- Spreading machine uses more workers than needed.
- Spread of single jersey is very difficult due to above operations.
- Achievable target is not achieved even after excess operators being implied on spreader.
- Optimum lay length is 7-8m but here lay length sometimes is more than 10m.
- Lack of attachments in the spreading machine.
- Change in width and lack of data regarding the variation of roll width there is frequent machine stoppage; and sometimes even two or three plies have to be removed after being laid.
Manual Spreading:
- Excessive manpower allocated in this department.
- Hand shears is used instead of end cutters leading to increase of manpower need.
- In yarn dyed spread length is generally for a single piece of shirt leading in the need of excessive manpower for laying.
Shifting of the lay to cutting table:
- While shifting of lay from spreading table to the cutting table air floatation table is not used properly.
Suggestion:
- Decrease running speed of spreader,to avoid turning of plies upside down.
- Keep length of spread between 7-8 m.this will help in faster and precise lay.
- One operator should always travel along with the machine to fix any blockage in the passage of laying. At the beginning itself.
- Spiral rollers should be used instead of plane surface rollers. To insure even lay .
- Two diiffrent lays of tubular knits can be spread at a time to utilize maximum width laying capacity of spreader.
- Spreading operator have no data about width of roll which causes spreading of rolls with different widths ,this will create loss of fabric as marker is made according to roll of minimum width.
- Replace hand shears with end cutters.this will decrease labour requirement from 4 to 2.and will also increase efficiency of lay.
- Instead of laying for single piece one can make a block for two piece and after laying block can be cut and operated separately.
- Before shifting of lay make sure that air flotation is on and running at highest level.this will decrease tension in lay due to pulling and also distortion in lay.
Problems faced in the cutting department