Los Angeles Southwest College s6

Construction Controls Group

Los Angeles Southwest College Proposition ‘A/AA’ Bond Fund Projects

Six Pack Meeting Agenda March 1, 2007

9:00 a.m.

1. / Child Development Center / Substantial Completion: 3/30/07
Commissioning: Planned in March 2007
Furniture Installation: Planned in April 2007
User’s Move-in, Prior Summer Session 6/4/07 - 6/10/07
2. / NEQ – Student Quad & Palm Court / Demolition in Progress (Parking Lot #1)
·  Proposed Completion April 20, 2007
Demolition of East & South Site Area of Cox Bldg
·  Proposed Completion Summer of 2007
Amphitheater at East of SS Building
·  Proposed Completion Summer 2007
Palm Court Site Area Improvements
·  Proposed Completion Fall 2007
3. / Cox Building Modernization / Revised Scope with College
CPM obtained new Architect (LHA – Proposal)
4. / New Central Plant / Contract Signed: 12/06/06
Weekly Project Meetings: Thurs. 8:00 am, with Chevron; Schematic Design Drawings & Basis of Design being updated to Design Development documents.
Chevron Coordinating with MACTEC – Geotechnical work to prepare Soils Report after Borings are taken within the next 3 weeks.
5. / Design-Build Update / Status of Projects:
Parking Structure: Plans Re-submit to DSA 03/01/07
M&O Site Grading/Utilities In-Progress; DSA Approval by 3/07/07; Start Bldg Construction March 2007
Athletic Field House & Stadium: In DSA Process
Student Services Activities Center: In DSA
Campus Corner Sign: In DSA Process
6. / Campus-Wide Technology / Target Time Schedule to complete: April 15, 2007;
Bid Phase: In Progress
Board Action: Pending on March 21, 2007
7. / Campus Quad Demolition / Campus Quad: Under construction
8. / Cox West Retaining Wall / College to discuss status of Cox West Wall to determine action plan; structural assessment and plans repair/replacement (as SMP project)
9. / SMP Projects / College to discuss status

Handouts:

1.  Campus Project List and Status

2.  Design-Build Project DSA Submittal Schedule

3.  Campus Projects Project Status & Schedule

4.  Campus Projects Financial Updates

5.  Construction Updates