Construction Controls Group

Los Angeles Southwest College Proposition ‘A/AA’ Bond Fund Projects

Six Pack Meeting Agenda May 3, 2007

9:00 a.m.

1. / Child Development Center / Substantial Completion: 6/15 to 6/29/07
Commissioning: Planned: June 2007
Furniture Installation: Planned in June 2007
User’s Move-in, July 3 – 8, 2007
2. / NEQ – Student Quad & Palm Court / Parking Lot #1: Beneficial Occupancy 4/20/07
Demolition of East & South Site Area of Cox Bldg
·  Proposed Completion Summer of 2007
Amphitheater at East of SS Building
·  Proposed Completion Summer 2007
Palm Court Site Area Improvements
·  Proposed Completion Fall 2007
3. / Cox Building Modernization / Gkkworks/LHA Architects in design phase
4. / New Central Plant / Existing Contract: Up to Design Development Phase
Weekly Project Meetings: Thurs. 7:30 am, w/ Chevron; Design Development documents in Technical Review;
New CD/Construction Contract: Pending/Need Update
5. / Design-Build Update / Status of Projects:
Parking Structure: DSA Approval Pending 05/16/07
M&O Facility: Construction in progress
Athletic Field House & Stadium: DSA Approval Pending on 5/09/07 to 5/10/07
Student Services Activities Center: In DSA, Package #1 Approved 3/14/07; 2nd/3rd/4th Packages in DSA
Campus Corner Sign: DSA Approval Pending 05/24/07
Campus Security Facility: DSA Approved 02/28/07
6. / Campus-Wide Technology / Target Time Schedule to complete: June 17, 2007 for Phase 1A
2nd Bid Phase: In Progress
Board Action: Phase 1A - May 16, 2007 Board Agenda
7. / Campus Quad Demolition / Campus Quad: Under construction; Existing Gas Line to be replaced with new pipe
8. / Cox West Retaining Wall / Cox West Wall inspected by structural engineer; structural assessment completed; plans for slab repair/replacement pending(as SMP project TBD)
9. / SMP Projects / College to discuss status
10. / Reclaimed Water / Supply pipeline partially installed on Western Ave.

Handouts:

1.  Campus Project List and Status

2.  Design-Build Project DSA Submittal Schedule

3.  Campus Projects Project Status & Schedule

4.  Campus Projects Financial Updates

5.  Construction Updates