October 30, 2017

Jim Dandy Investment Company LLC & Four Leaf Investments

1950 Victor Pl #100

Colorado Springs, CO 80915

Bucher Design Studio, INC

300 General Palmer Dr.

Palmer Lake, CO 80133

Dear Applicant and/or Consultant:

Subject: PPR-17-036 Claremont Business Park Lots 24 & 25

The purpose of this letter is to provide you with thereview agency responses to the above named development application that have been receivedto-date by Planning and Community Development.

You are encouraged to directly contactthose agenciesthat did provide review comments if the comments requireadditional action by the applicant/applicant’s representative. You are also encouraged to directly contact those agencies that did not provide review comments if such response is required by state statutes and the El Paso County Land Development Code.

EL PASO COUNTY PLANNING AND COMMUNITY DEVELOPMENT DEPARTMENT

Current Planning-

  1. Address Pikes Peak Regional Building
  2. Address Engineering Division Comments- See redlines for GEC

Engineering Division-

  1. Redline commenbts t the Grading and Erosion Control Plan will be uploaded by the Project Manager
  2. On the SWMP report. Provide a statement that no dedicated asphalt/concrete patch pant is proposed on site. (Per Appendix E SWMP checklist footnote regarding “not applicable” items)

ELPASO COUNTY COMMUNITY SERVICES DEPARTMENT

ENVIRONMENTAL

  1. Environmental Division has no additional comments.

CENTRAL MARKSHEFFEL METRO

  1. No additional comments

Colorado Springs Utilities

Utility Comments (electric, gas)

Cherokee Metro

  1. No additional comments

CIMARRON HILLS FIRE

  1. No additional comments

COLORADO SPRINGS AIRPORT ADVISORY COMMISSION

  1. No additional comments

PIKES PEAK REGIONAL BUILDING

Have items bellowed been worked out with PPRBD?

Regarding a request for approval of a development plan for lots 24 and 25 of Claremont Business Park Fil. No. 2, Enumerations has the following comments:

1. Lot 25 looks to have 2 tenant spaces projected for this building, lot 24 looks to have 3 tenant spaces projected for this building. Meters for each building need to be set for all tenant space at the core & shell phase of the building plans. Please show how many tenants at max each building can hold so the suite numbering can be assigned.

BRENT JOHNSON Enumerations Plans Examiner

(719) 327-2888

CENTRAL CO CONSERVATION DISTRICT

CCCD has no comments at this time

Comments received from any of the above non-responding agencies following the issuance of this letter will be forwarded to the applicant/applicant’srepresentative and will be added to the end of this letter for record keeping purposes.

Due to the number of comments and necessary revisions to the plan(s) an additional detailed review will be necessary. Please address the comments as listed above. A detailed letter needs to accompany the revisions to allow for an expeditious re-review timeframe. The letter shouldinclude each comment listed above and, immediately thereafter, include a response from the applicant addressing the comment.

If any review agency has an issue that needs resolution or requires a revision, you will need to provide the necessary documents, drawings, etc., to the Planning and Community Development Departmentin the form of a resubmittal. The Planning and Community Development Department will then forward the resubmitted items directly to the appropriate review agency. If you have any questions pertaining to specific agency comments please contact the appropriate agency directly.

When all the comments have been addressed and corrections made please submit the required documents as requested on the attached resubmittal matrix.

If you have any questions feel free to contact me at

Best Regards,

Gabe Sevigny

El Paso County Planning and Community Development Department

719-520-7943

File:PPR-17-036

Page 1 of 310/12/2018