Instructions for Updating FAMIS Data
Status of Capital Project changing to RELCON (released for construction)
August 21, 2015
Contents
Self-performed Projects
Purchase Order Projects
Minor Projects
Major Projects – General Contractor (GC)
Major or Minor Projects – Construction Manager (CM) or Internal Construction Manager (ICM)
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018
Self-Performed Projects
Self-performed Projects
- Event - Project Request is issued
- Project AdministratorinEAS Administrative Support
- FAMIS Capital Project data
- General tab
- Status - change to RELCON
- Assigned To - remove entry (leave empty)
- Project Manager – change to KELLYS (or LAWVERAS, VALLANCEJ, etc.)
- Description - add note
- Details tab
- PROJ TYPE - confirm SHOPS
- CONSULTANT - enter consultant name or EAS (if in-house design)
- EST COST – confirm matches total budget on project request and also Total Planned Amount in Budget tab
- PR# - enter project request number
- CONTRACTOR – confirm or enter department (ex: PP-PROJECT SERVICES, PP-LANDSCAPE SERVICES, etc.)
- Schedule tab
- Design line, Actual End – enter date on Project Request
- Budget tab
- Planned Amt column – enter planned amounts by budget code from the Budget Cost Summary attached to the Project request
- Reference:Project Request Process
- Unifier data
- Note: the budget for self-performed projects is not currently maintained in Unifier
- Project Information - change status to RELCON
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018
Purchase Order Projects
Purchase Order Projects
- Event – Requisition is placed for Purchase Order to the Contractor
- Project Administrator in EAS Administrative Support
- FAMIS Capital Project data
- General tab
- Details tab
- Schedule tab
- Send e-mail to Earline Solomon with message: “CP has changed to RELCON; please verify schedule dates”. Copy Leisa Williams-Swedberg.
- Budget tab
- Unifier data
- Enter the Unifier itemized budget using the Budget Distribution tool.
- Project Information– General - Attributes
- See screenshots on next page for data to be updated, verified, or entered if missing:
- Famis Status - change to RELCON
- Current Estimate – change to match total budget in FAMIS
- Select Lead Designer… obtain from FAMIS details tab
- Select Project Rep… obtain from FAMIS details tab
- Select Customer… obtain from FAMIS details tab
- Select Contractor… obtain from Unifier Vendor Information Form
- Select Consultant… obtain from Unifier Vendor Information Form
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018
Minor Projects
Minor Projects
- Event – Contract is signed by the Contractor
- Project Administrator in IPF Contracts
- FAMIS Capital Project data
- General tab
- Details tab
- Schedule tab
- Send e-mail to Earline Solomon with message: “CP has changed to RELCON; please verify schedule dates”. Copy Leisa Williams-Swedberg.
- Budget tab
- Unifier data
- Enter the Unifier itemized budget using the Budget Distribution tool.
- Project Information – General - Attributes
- See screenshots on next page for data to be updated, verified, or entered if missing:
- Famis Status - change to RELCON
- Current Estimate – change to match total budget in FAMIS
- Select Lead Designer… obtain from FAMIS details tab
- Select Project Rep… obtain from FAMIS details tab
- Select Customer… obtain from FAMIS details tab
- Select Contractor… obtain from Unifier Vendor Information Form
- Select Consultant… obtain from Unifier Vendor Information Form
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018
Minor Projects
Major Projects – General Contractor (GC)
- Event – Contract is signed by the Contractor
- Project Administrator in IPF Contracts
- FAMIS Capital Project data
- General tab
- Details tab
- Schedule tab
- Send e-mail to Earline Solomon with message: “CP has changed to RELCON; please verify schedule dates”. Copy Leisa Williams-Swedberg.
- Budget tab
- Unifier data
- Enter the Unifier itemized budget using the Budget Distribution tool.
- Project Information – General - Attributes
- See screenshots on next page for data to be updated, verified, or entered if missing:
- Famis Status - change to RELCON
- Current Estimate – change to match total budget in FAMIS
- Select Lead Designer… obtain from FAMIS details tab
- Select Project Rep… obtain from FAMIS details tab
- Select Customer… obtain from FAMIS details tab
- Select Contractor… obtain from Unifier Vendor Information Form
- Select Consultant… obtain from Unifier Vendor Information Form
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018
Major Projects – Construction Manager (CM and ICM)
Major or Minor Projects – Construction Manager (CM) or Internal Construction Manager (ICM)
- Event–First buy-out change order for a trade package is processed in Unifier
- Project Administrator in IPF Contracts
- FAMIS Capital Project data
- General tab
- Details tab
- Schedule tab
- Send e-mail to Earline Solomon with message: “CP has changed to RELCON; please verify schedule dates”. Copy Leisa Williams-Swedberg.
- Budget tab
- Unifier data
- Enter the Unifier itemized budget using the Budget Distribution tool.
- Project Information – General - Attributes
- See screenshots on next page for data to be updated, verified, or entered if missing:
- Famis Status - change to RELCON
- Current Estimate – change to match total budget in FAMIS
- Select Lead Designer… obtain from FAMIS details tab
- Select Project Rep… obtain from FAMIS details tab
- Select Customer… obtain from FAMIS details tab
- Select Contractor… obtain from Unifier Vendor Information Form
- Select Consultant… obtain from Unifier Vendor Information Form
CAPITAL PROJECT - FAMIS DATA ENTRY FOR STATUS CHANGING TO RELCON.DOCX12/13/2018