STATEMENT OF PROCEDURE
- This procedure is to give guidelines on temporary and portable buildings including trailers which could contain personnel brought onto the plant site.
PROCEDURE
I-D-16.50Page 1 of 2
Revision: 1
- All placement of temporary/portable buildings, including trailers which could contain personnel, must be approved through MOC. A SAP Notification must be written and marked with the task of MOC Required.
- Temporary buildings/trailers cannot be occupied by personnel in the operating areas of the plantor impacted by blast zones.
- All temporary/portable buildings/trailers must be in good condition.
- All steps and stairs leading into the building must be free of hazards. All stairs will meet the requirements of OSHA’s Walking Working Surfaces.
- Housekeeping will be maintained in and around the building at all times. This includes mowing and weed eating around the building.
- The guidelines outlined in the Green Lake Complex SOSO I-D-16.00 Eating and Drinking will be strictly followed.
- Electrical hook up will be made by GreenLake site personnel.
The following items will be addressed for each temporary building brought onto the plant site.
- A list of all flammables and combustibles and inspection must be updated and provided to the Green Lake Complex Safety department on a weekly basis. A copy of the building contents must also be posted outside the building’s main entrance.
- All flammables must be appropriately stored in approved flammable cabinets.
- Combustibles will be kept away from any potential ignition source.
- A key to the building must be left with the Main Guard Gate at all times.
END OF PROCEDURE
SOSOGeneral Procedures
ID1650 Temporary & Portable Buildings
111378 / Approved Locations
Occupied temporary/portable buildings and/or trailers can be set anywhere as is convenient for use as long as it is approved by the appropriate supervisor.
A. True
(B.) False
111379 / Conractor Responsibility
The GreenLake site will determine where the temporary/portable building will be located. The contractor bringing in the temporary/portable building shall:
Check All That Apply:
___ Take care of all needed hookups, such as electrical, plumbing, etc.
_X_ Ensure that it is and remains in good condition
_X_ Maintain proper housekeeping in and around the building
_X_ Provide a key and leave it with the Main gate
111380 / Steps and Platforms
When a temporary building is used, a few blocks and some plywood are sufficient to make some steps and a platform to access the temporary building.
A. True
(B.) False
111381 / Flammable and Combustibles
What must be provided to the Safety Department on a weekly basis?
A. Plumbing problems
(B.) A list of flammables and combustibles and inspection
C. Proposed eating menu and schedule