“Half Yearly Compliance Report Tulip Orange &TulipIvory, Sector 70, Gurgaon, Haryana

for Specific and General Conditions”

Chapter 1

Introduction and Project Description

1.1Introduction

M/s Tulip Infratech Pvt. Ltd. Gurgaon has proposed to develop a Group Housing Project “Tulip” at Sector 70 Gurgaon in the state of Haryana. The Tulip Group is a company which has achieved excellence through its foresightedness and expertise in its field. The focused vision, undivided dedication and constant efforts of the company help it to develop strategies for its ceaseless growth in the sphere of real estate and construction.Maintaining the highest standards of quality has always been the foremost priority at Tulip, enabling it to earn an enviable reputation in a brief period of time. With residential and commercial projects, planned to create a benchmark in the future, Tulip is embarking very fast on the way to success. The existing land use is marked for residential development as per Gurgaon Manesar 2021 Development Plan. Therefore, the existing land use is not expected to get altered due to the residential development.

In the Group Housing project, following facilities will be provided to make it a comfortable and convenient living for its residents:

  • 24 X 7 hrs. Security.
  • Street lights.
  • Parks equipped with swings and slopes with jogging
    & walking tracks.
  • Adequate cross ventilation and ideal natural light in every apartment.
  • Provision for lifts and comfortable staircase.
  • Community center.
  • Shop/commercial area
  • Nursery School
  • Housing provisions for Economically Weaker Section
  • 24 hours water supply for the residential population.

The total plot area of the Group Housing project is 71,656.991 m2 or (17.70 acre) and the total built up area is 1,26,434.71 m2 Thus, the construction of buildings requires Environmental Clearance from State Environment Impact Assessment Authority (SEIAA) under category ‘B2’ of EIA Notification 2006.

1.2Project Description

Salient Features:

The plot area of the project is 71,656.991 m2or (17.70 acre) and total built up area is 1,26,434.71 m2.The group housing project will have Built-up Residential area 123100 m2, built up area commercial 623.30 m2t & built-up area institutional 1676.716 m2. The maximum height of the building will be 45 m for which NOC from airport authority has been obtained.The total fresh water requirement for the proposed project is 445 KLD. The quantity of waste water generated from the project will be about 274 KLD which will be treated in the STP by primary, secondary and tertiary treatment. The capacity of STP will be 350 KLD. The 219 KLD of treated water will be recycled back and utilized for horticulture, cooling of DG; flushing and remaining will be used for the road and car washing and excess water from the project site will be used for maintaining the green belt around the project site.

NO untreated water will be discharged from the project site without prior permission from the Haryana State Pollution control board.Total Solid waste will be 2106 kg/day which will be disposed off as per Solid Waste Management & Handling Rules. Proper care will be taken for the collection, storage and transportation and will be collected on a daily basis and will be transported to the government approved authorized landfill site.The total Cost of the project is Rs. 141 crores.

Parking:

The building will have parking in basements and surface. The total proposed parking for the proposed project is 1440 ECS. Total parking required as per the MoEF is 1226 ECS while total parking required as per the State Bylaws is 1326 against which total of 1440 ECS has been provided for te proposed project. Proper care will be taken for the parking and no public space will be used for the parking during the construction d operation phase of the project.

Water Supply: The water during construction phase will be taken from the private water tankers and during operation phase will be used from the HUDA. No ground water abstraction during construction and operation phase will take place.

Electricity:

The building will avail electricity from Dakshin Haryana BijliVitran Nigam Limited. The power requirement is 4900 KVA.For the backup power supply during power failure total of 625 KVA (500*1+125*1) has been provided. DG Sets will be used only during the power failure DG sets room will be acoustic enclosure type and proper operation and maintenance will be done for the DG sets.

Fire Safety:

All buildings in proposed project will be well equipped with all firefighting equipment. Water hose pipes and Fire extinguishers will be provided. Fire approval received from Commissioner Municipal Council Gurgaon. Fire mock drills will be done during the operation and construction phase of the project. Hose pipe will be properly cleaned so that water can be used during the casualty.

1.3 Present Status

Project site is in constructional phase (Near to completion).

1.4 Purpose of the Report

This six-monthly report is being submitted as per the condition stipulated in the Environmental Clearance letter.

Further, the study will envisage the environmental impacts that have generated in the local environment due to the project.

The environmental assessment is being carried out to verify:

  • That the project does not have any adverse environmental impacts in the project area and its surrounding.
  • Compliance with the conditions stipulated in the Environmental Clearance Letter.
  • That the Project Management is implementing the environmental mitigation measures as suggested in the approved Form-1, Form-1A, Environmental Management Plan (EMP) and building plans.
  • The project proponent is implementing the environmental safeguards in true spirit.
  • Any non-conformity in the project with respect to the environmental implication of the project.

Chapter 2

Compliance of Stipulated Conditions of Environmental Clearance for Buildings in Operational Phase

PART A – SPECIFIC CONDITIONS

  1. Construction Phase

S. No. /

Conditions of Environmental Clearance

/
Status of Compliance
1 / A first aid room as proposed in the project report will be provided both during construction and operation phase of the project. / Agreed. A First aid facility is available at project site for the safety of the workers and is under the custody of the project in-charge at the project site.
2 / Adequate drinking water and sanitary facilities should be provided for construction workers at site. Provision should be made for mobile toilets. Open defecation by the laborers should be strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. / Agreed. Supply of drinking water and provision of sanitary facility has been provided within the project site. Facility of mobile toilets has been provided for the construction workers. Open defecation by the laborers is strictly prohibited.
3 / All the topsoil excavated during construction activities should be stored for use in horticulture/landscape development within the project site / Agreed. The top soil is stored secured near the project site and will be used for landscaping after completion of civil work
4 / Disposal of muck during construction phase should not create any adverse effect on the neighboring communities and be disposed taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority. / Agreed. There is no larger quantity of muck generated during construction activity.
Hazardous waste generated is being disposed as per Hazardous waste management and handling rules 2010.Agreement has been done for the disposal of the hazardous waste. Proper care will be taken for the collection, segregation, storage and transporting.
5 / Construction spoils, including bituminous material and other hazardous materials, must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. / Agreed. Construction spoils, including bituminous material and other hazardous materials is being disposed off in scientific manner. The adverse impact on the water course will be negligible.
6 / The diesel generator sets to be used during construction phase should be of low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standards / Agreed. Low sulphur diesel (LSD) is being used during power failure and it will confirm to Environment (Protection) Rules 1986 prescribed for air and noise emission standards. Proper maintenance will be done during the construction and operation phase of the project. Proper stack height will be provided above the roof top for the proper dispersion of the pollutants
7 / The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosives shall be taken. / Agreed. The diesel required for operating DG sets is being stored secure in such a way that no accidents, spillage and leakage possible. Proper care will be taken for the storage, transport and will be properly monitored.
8 / Ambient noise levels should conform to residential standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase. Adequate measures should be taken to reduce ambient air and noise level during construction phase, so as to conform to the stipulated standards / Agreed. Ambient noise level monitoring was carried out and it was found to be within the prescribed limit of residential standards during day and night. Incremental pollution loads on the ambient air and noise quality is closely monitored during construction phase. Adequate measures have been taken to reduce ambient air and noise level during construction phase.
9 / Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and amended as on 27th August 2003 / Agreed. Fly ash is being used along with Ready Mix Concrete as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and amended as on 27th August 2003.
10 / Ready mix concrete must be used in building construction / Agreed. Ready Mix Concrete is being used for the construction purposes.
11 / Storm water control and its re-use as per CGWB and BIS standards for various applications / Agreed. Storm water is being controlled by laying proper internal drainage network within the project site. Storm water plan is attached here as Annexure-1.
12 / Water demand during construction should be reduced by use of pre-mixed concrete, curing agents and other best practices referred / Agreed. To conserve the water, there is use of pre-mixed concrete, curing agents and other best practices.
13 / Permission from competent authority for supply of water shall be obtained prior to construction/ operation of the project / Agreed. Assurance for Water supply has been obtained from HUDA for the operation phase. Copy of the Permission is attached here with as Annexure-2.
14 / Roof should meet prescribed requirement as per Energy Conservation Building Code by using appropriate thermal insulation materials to fulfill requirement / Agreed. Construction of roof will be built as per Energy Conservation Building Codeby using appropriate thermal insulation materials to fulfill requirement.
15 / Opaque wall should meet prescriptive requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is aspirational for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement / Agreed. Energy efficient building material is being used for all air conditioned.
16 / The approval of the competent authority shall be obtained for structural safety of the building due to earthquake, adequacy of firefightingequipment etc. as per National Building Code including protection measures from lighting etc. If any forest land is involved in the proposed sire, clearance under forest Conservation Act shall be taken from the competent Authority / Agreed. All approvals from the competent authority have been obtained for structural safety of the building due to earthquake, adequacy of firefightingequipment etc.
Forest NOC from Tehsildaris attached here as Annexure-3.Forest receiving from the Deputy Commissioner and Chief conservator of forest is attached here as Annexure-4.
17 / The project proponent will use the water for construction phase through tankers. However, prior permission from CGWA will be taken before using the bore well water for construction purposes. / Agreed. Water for the construction purpose is being taken from the private tanker supplier.
18 / The Project proponent will construct rain water harvesting pit @ one pit per acre for recharging the ground the ground water within the project premises / Agreed. There is provision of construct rain water harvesting pit @ one pit per acre for recharging the ground the ground water within the project premises.
The rain water harvesting plan is attached here as Annexure-1.
19 / The project proponent starts construction only after obtaining the NOC from Airport Authority. / Agreed. Permission from the Airport Authority has been applied.
Copy of the application is attached here with as Annexure-5.
  1. Operation Phase

S. No /

Conditions of Environmental Clearance

/ Status of Compliance
1 / The STP shall be installed for the treatment of the sewage generated to the prescribed standards including odour and treated effluent will be recycled to achieve zero discharge. The STP should be installed at the farthest place in the project area / Agreed. There is a provision of 350 KLD STP for treating entire sewage generated from the building. Total of 219 KLD water will be reused from the project site. Treated water from the STP will be used for the flushing, DG sets cooling, Horticulture, Road and Car washing and rest excess water will be used for maintaining green belt outside the project. No untreated water will be disposed without the prior permission from the Haryana State Pollution control board. STP diagram is attached here as Annexure-8.
2 / Separation of gray and black water should be done by the use of dual plumbing line. Treatment of 100% gray water by decentralized treatment should be done ensuring that the recirculate water should have BOD maximum 10 pm and the recycled water will be used for flushing, gardening and HVAC makeup and DG set cooling. / Agreed. Provision of dual plumbing has been made for separation of grey and black water. Treated waste water will be used for flushing, DG cooling water makeup and landscaping.
Dual plumbing plasn is attached here as Annexure-6.
3 / For disinfections of the treated wastewater ultra-violate radiation or ionization should be used. / Agreed. There is provision of ultra-violate radiation for disinfections of treated waste water
4 / The solid waste generated should be properly collected and segregated. Wet garbage should be composted and dry/inert solid waste should be disposed off to the approved sires for land filling after recovering recyclable material / Agreed. Solid waste is will be disposed through MCG authorized waste collector and disposed in the solid waste management facility at Bandhwari village which is an approved site for solid waste treatment and disposal.
5 / Diesel power generating sets proposed as source of backup power for lifts, common area illumination and for office use should be of enclosed type and conform to rules made under the Environment (Protection) Act, 1986. The location of the DF sets should be in the basement as promised by the project proponent with appropriate stack height i.e. above the roof level as per the CPCB norms. The diesel used for DG sets should be of low sulphur contents (Maximum 0.25%) / Agreed. DG sets will be acoustic enclosed type and will conform to the rules made under EP Act 1986.The stack height will be 6 m above the roof level. Low sulphur Diesel (LSD) with maximum sulphur content is 0.25% will be used for the DG sets during construction and operation phase.
6 / Ambient Noise level should be controlled to ensure that it does not exceed the prescribed standards both within and at the boundary of the proposed Residential complex / Agreed. Ambient noise level at the project site has been monitored and observed that it does not exceed the prescribed standards both within and at the boundary of the project site. The maximum dB (A) at 1 m distance from the DG sets will not exceed 75 dB (A).
7 / The project proponent should maintain at least 20% as green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species so as to provide protection against particulate and noise. The open spaces inside the plot should be preferably landscaped and covered with vegetation/grass. / Agreed. Landscape will be developed after completion of entire civil construction works. There is provision of green belt development in the project area up to 20% of green cover area for tree plantation especially all around the periphery of the project and on the road sides preferably with local species so as to provide protection against particulate and noise.