1.  status

The 17G2 Riserless Subsea Pumping Systems Group is meeting on a quarterly frequency via telecoms. Earlier meetings dedicated time to solicit membership from individuals with coveted skill sets, obtain alignment of what should be included/excluded in the document, and schematic reviews of known systems that are in service globally. Membership is robust but still lacking in a couple areas necessary to complete deliverables (i.e. expertise to develop and mature the equivalents of Annex B and C for spooled fluid conduit products and their associated deployment configurations).

It was decided that the G2 Document will follow the same format as the main 17G document. As such, draft clauses for Scope, System Requirements, and Functional Requirements are at various stages of development, review, and editing at this time. The G2 Group is sharing work in progress and documentation with the other Baby G teams in an effort to obtain alignment. In addition, some of the work product is relevant to other Baby G’s as there are a couple overlap team initiatives (i.e. fluid conduit subject matter is common with G3 Riserless Light Well Intervention efforts and composite design methodology as it relates to mechanical performance is common with the G1 Non Ferrous Alloys effort).

2.  membership

Tables 1 list the current roster for the API task group:

TABLE 2: API “BaBY 17G2” Task Group Members

API 17G2 – Riserless Subsea Pumping Systems
Name
Mike Hess (Chair) Shell
Alai Alavi Bechtel OG&C
Andy Henderson Oceaneering
Bill Barry Atlantic Wave LLC
Charles Tavner Magma
David Bell Bechtel OG&C
Frans Janssen Shell
Jim McAllister Shell
Joe Savoy Wild Well Control
John Smith Global Coil Tubing
Mark Johnson FTO Services
Martin van Onna Airborne
Mitch Holloway Oceaneering
Neil Crawford Blue Ocean
Phil Walsh Magma
Ramsay Cook Blue Ocean
Ryan Addison Tenaris
Sterling Lewis ExxonMobil
Troy Theal Chevron
William Siersdorfer One Subsea
Bart Steuten Airborne
Mike Swift Hess Corporation
Mirick Cox ExxonMobil
Mitch Dziekonski Titanium Engineers
Brian Skeels FMC Techologies

3.  WORK IN PROGRESS

o  Subteams have volunteered to write the various clauses in the document with the main G2 team providing review and edits.

o  Clause 1 (Scope) first draft is complete and being edited by the main G2 team.

o  Clause 2 (Normative References) is deferred at this time and will be addressed later as the other clauses and annexes mature.

o  Clause 3 (Terms, Definitions, etc.) is being ever greened as the subject matter of riserless subsea pumping systems is developed in the document.

o  Clause 4 (System Requirements) is partially drafted and distributed for review by the main G2 team.

o  Clause 5 (Functional Requirements) is partially drafted and distributed for review by the main G2 team.

o  The next G2 team telecom is scheduled for January 12th 2014.