SITE MONITORING REPORT

Fees for Monitoring of Mining and Landfill Sites in England

Please find detailed below the report for the site monitoring undertaken on23 February 2012. If you should have any queries or require any photographs taken on site please do not hesitate to contact me.

File Ref: 13 421 18/19 / Visit no: 4 of 4
Monitoring Officer: Shelley Bailey
Tel No: 01245 437577 / Time on site: 14:00 / Time off site:
17:00 (including meeting)
Site Co-ordinator:Shelley Bailey / Tel No: 01245 437577
Site Name: Colchester Quarry (including Stanway Pit and Bellhouse Landfill), Warren Lane, Colchester.
Operator: Tarmac Ltd and Cory Environmental
Site Representative: Mark Murray and Simon Treacy (Tarmac)
Mark Harling (Cory Environmental Resource Management)
Permission no’s:
Bellhouse and Abbotstone
ESS/48/01/COL/R – Bellhouse Farm ROMP for LEX/266/69
ESS/07/01/COL/REV – Amendment to ESS/07/01/COL to provide for amended restoration contours at Bellhouse and Abbotstone, excluding ExWaste site.
ESS/32/09/COL – Construction of waste reception and handling area at Bellhouse - issued 25 August 2009.
ESS/65/98/COL – Cory offices.
ESX/66/92/COL – Cory gatehouse, weighbridge and wheelwash.
ESS/52/94/COL – Cory site accommodation and car park.
ESS/31/11/COL – Environmental flare.
West of Warren Lane (Tarmac)
COL/1644/77 – Asphalt plant
ESS/54/04/Col – Concrete batching plant.
ESS/33/03/COL – Variation, time limit to extend use of Tarmac regional offices until 20 September 2020.
ESS/28/02/COL – Lab, office and storage rooms (adj. asphalt plant).
ExWaste
ESS/41/03/COL – restoration of landfill to amenity afteruse
ESS/2/94/COL – Power generation plant (located NW of Bellhouse)
Stanway Hall Quarry
ESS/06/09/COL – Variation to PP ref ESS/14/06/COL (which varied ESS/49/01/COL, the ROMP for LEX/342/68) conditions 6 and 15 to extend the time period for the submission of a detailed working and restoration scheme at Stanway.
ESS/63/06/COL – MBT and AD plant. Issued 11 May 2009.
ESS/17/05/COL – Relocation of inert recycling facility within Stanway Hall area (cessation 11/01/2015).
ESS/51/04/COL – Variation to PP ref ESS/22/99/COL Condition 1 (time limit) to extend to 11 January 2015 and Condition 15 (HGV movements) to increase to 1600 per month at Stanway (Recycling Facility).
ESS/07/05/COL – Dry Silo Mortar Plant and internal access improvements. Cease September 2020 or at cessation of extraction.
ESS/24/00/COL – Power generation plant at Stanway Pit to utilise gas generated at Bellhouse landfill.
ESS/05/99/COL – Workshop (expires on cessation of mineral extraction).
ESS/21/02/COL - Processing Plant – expires 2020 or on completion of extraction.
Permission Number & Romp Date Due: ESS/48/01/COL/R 09/04/2020
ESS/49/01/COL 09/04/2020
Outstanding Submission of details:
Permission No. / Condition No. / Scope of Condition and Action to be taken
ESS/48/01/COL(R) / 6 / Submission of a working scheme for remaining extraction areas within 6 months of date of permission (by 13 Oct 05).
ESS/48/01/COL/R / 24 / Noise Monitoring.
ESS/07/01/COL/REV / 20 / Details of allowances for settlement to be submitted (Overdue Feb 11).
ESS/07/05/COL / 10 / Dust suppression.
ESS/17/05/COL / 14 / Dust suppression.
ESS/07/01/COL/REV / 9 / Noise monitoring (discrepancies re Sept 11 monitoring to be responded to).
Constraints:
Weather:Dry/ Windy / Rain / Snow
Noise:Acceptable/ Not acceptable N/A
Approach Roads:Dry / Dusty / Wet / Muddy / Flooded
Ground:Dry / Dusty / Wet / Damp / Muddy / Flooded
Access: Obstructed / Not Obstructed / Mud on Road / Ice / Slippery
Wheel Cleaning:Washer / Spinner / Sweeper / none
Hose:In use / Not in Use / N/A
Machinery:Working / Not working
In correct position:Yes / No / N/A
Stockpiles:Height = N/A
Bunds:Profiled / Grassed / Weeds/ NA
Actions from last site visit:
  • Additional silos at the DSM should be removed for compliance with planning permission ref ESS/07/05/COL.
  • Details of the proposed silt lagoon are requested – e.g. how would it be constructed, where on site, how would the existing lagoon be restored, etc.
  • A planning application for the temporary retention of redundant kit should be submitted prior to Christmas 2011 following the Parish liaison meeting on 7th Dec.
  • The current operations of the asphalt plant should be confirmed within the next month.
  • Submissions of details required as above from Tarmac, Cory and Tarmac DSM.
  • Condition 6 of ESS/06/09/COL due before Christmas 2011.
  • Cory to continue to actively pick litter in areas surrounding the site.
  • Cory to submit the requested further detail for condition 20 attached to ref ESS/07/01/COL/REV within 1 month.
  • Cory to clarify on a drawing what the current state of each phase is and provide details of the levels survey once results are in.
  • Tarmac to clarify whether ‘maintenance payment’ required by S106 has been paid.
  • The next liaison meeting scheduled for 7th Dec will be attended by the Environment Agency. All representatives from Tarmac and Cory should make every effort to attend.

Inspection Results Summary:
  • There is a small section of pipeline remaining at the Warren Lane end of the Hart Field and a redundant electricity cable running the entire length of the field. This should have been removed and the land properly restored to agriculture by 31 December 2010 as required by condition 2 of permission ref ESS/09/09/COL. MM informed me this would be done w/c 27/02/12.
  • A new hardsurfaced area was being constructed to the rear of the offices in the Stanway Hall area, to the south of the internal DSM haul route. This appears to extend beyond the application area permitted by ref ESS/07/05/COL. It is understood the intention is to move the silos to this area for compliance with the permission, however this must be within the permitted area.
  • An open-sided container is located on the western edge of the DSM area. This should not be permanently retained.
  • The haul route leading to Stanway Hall was muddy. This should be kept clear to ensure no tracking onto Warren Lane.
  • Condition 6 associated with ESS/48/01/COL(R) has not been submitted. This is overdue. Tarmac stated this will be submitted by end of March 2012.
  • Condition 6 associated with ESS/06/09/COL has been submitted to the MPA.
  • The landfill phases (ESS/07/01/COL/REV) were assessed on site with MH. Cory are still requested to provide this on a drawing to ensure compliance with ESS/07/01/COL/REV and the accompanying S106 phasing drawings. Details of levels survey to be provided once results received.
  • The outstanding S106 ‘maintenance payment’ was paid by Tarmac Feb 2012.
  • A hardstanding area has been constructed near to the current tipping area. There is no planning permission for this and it should be removed.
  • A planning application has not been received for surplus kit. This is required to regulate a breach of planning control.

Compliance with Conditions
Permission No. / Condition No. / Scope of Condition and Action to be taken / Action to be taken by
Operator or MPA/WPA
Officer
ESS/48/01/COL(R) / 6 / Submission of a working scheme for remaining extraction areas within 6 months of date of permission (by 13 Oct 05). / Operator. By end March 2012.
ESS/48/01/COL/R / 24 / Noise Monitoring. / Operator. Overdue and urgent.
ESS/07/01/COL/REV / 20 / Details of allowances for settlement to be submitted (Overdue Feb 11). / Operator.
Overdue and urgent.
ESS/07/05/COL / 10 / Dust suppression. / Operator.
Overdue and urgent.
ESS/17/05/COL / 14 / Dust suppression. / Operator.
Overdue and urgent.
ESS/07/01/COL/REV / 9 / Noise monitoring (discrepancies re Sept 11 monitoring to be responded to). / Operator.
Overdue and urgent.
Actions to be taken before next site visit:
Submissions of details required as above by both companies.
Tarmac
  • Pipeline and cable to be removed from Hart Field and the land restored to agriculture as required by permission ref ESS/09/09/COL by end of w/c27/02/12. Note: Since the visit it was discovered that this requirement was not carried out, however Tarmac have stated that the work has now commenced (on 12/03/12).
  • Tarmac to confirm the extent of the new DSM area for compliance with permission ref ESS/07/05/COL.
  • The open-sided container to the west of DSM area is to be removed.
  • The haul route to Stanway Hall is to be kept clear of mud and debris.
  • ESS/48/01/COL(R) condition 6 is overdue. This is a breach of the planning permission. Details are to be submitted by end of March 2012 (this is a Bellhouse permission so Cory will also have involvement).
  • A planning application is required for the temporary retention of surplus kit. This is overdue.
  • The current operations of the asphalt plant should be confirmed. This is overdue.
  • The Management Plan required by the S106 Agreement attached to permission ref ESS/07/02/COL/REV is overdue as of 18 February 2009 and must be submitted urgently (this is a Bellhouse permission so Cory will have involvement).
My letter of 09 February 2012 is relevant and should be complied with.
Cory
  • Hardstanding area adjacent to current tipping area to be removed.
  • Cory to clarify on a drawing what the current state of each phase is and provide details of the levels survey once results are in.
  • Further details for condition 20 attached to ref ESS/07/01/COL/REV have still not been provided. It was agreed at the meeting on 23rd Feb that these would be submitted asap.
Note:The actions noted in this report are required in order to ensure adequate progress is made and to avoid potential enforcement action against a breach of planning control.