VIDERBHA IRRIGATION DEVELOPMENT CORPORATION, NAGPUR
(Undertaking Govt. of Maharashtra)
Chief Engineer Special Project Water Resources Department Amravati
Akola Irrigation Circle, Akola
Akola Irrigation Division, Akola

Corrigendum No.1

E-Tender Notice No. 01 for 2015-16

Main Portal:

Sub Portal :

The following changes are made in the detailed tender notice published on portals mentioned above.

Tender No.517

Sr.No. / details / Changes now made through corrigendum
1 / 4.7(a) Envelope I (Technical)
ii) scan copy of latest acknowledgment of income Tax return filed by the contractor along with of PAN CARD / Scan copy of latest acknowledgement of income tax return filed by the contractor for the financial year 2013-14 Assessment year 2014-15 along with PAN CARD
2 / Special condition of contract
33.price variation clause 1) Labor component 45%
3) Formula for petrol,oil,and Lubricant componant.
P0 = Average price of HYSD at AKOLA during the quarter preceding the month in which the last date prescribed for receipt of tender,falls
P1 = Average price HYSD at AKOLA during the quarter under consideration
5) formula for steel component / Special condition of contract
33.price variation clause 1) Labor component 26%
3) Formula for petrol,oil,and Lubricant component.
P0 = Average price of HSD at AKOLA during the quarter preceding the month in which the last date prescribed for receipt of tender,falls
P1 = Average price HSD at AKOLA during the quarter under consideration
5) formula for steel component
(So x (SI1 SI0 ) / V5 = So (SI1 - SI0 )
V5 = x T / x T
100 SI0 / SI0
3) So = Basic rate of steel in rupees per metric tonne as considered for working out value of P =34400/ MT / So = Basic rate of steel in rupees per metric tonne as considered for working out value of P =50000/ MT
6)Formula for cement component / 6)Formula for cement component
(Co x ( CI1 CI0 ) / V6 = Co ( CI1 - CI0 )
V6 = x T / x T
100 CI0 / CI0
Co= Basic rate 0f cement in rupees per metric tone as considered for working out value of P=4800/MT
Slo = Average of cement index as per RBI Bulletin during the quarter preceding the month in which the last date prescribed for receipt of tender,falls.
Sl1 = Average cement index as per RBI Bulletin during the quarter under consideration. / Co= Basic rate 0f cement in rupees per metric tonne as considered for working out value of P=6000/MT
Clo = Average of cement index as per RBI Bulletin during the quarter preceding the month in which the last date prescribed for receipt of tender,falls.
Cl1 = Average cement index as per RBI Bulletin during the quarter under consideration.

Executive Engineer

Akola Irrigation Division

Akola