DRAFT Timelines in respect ofServices under Business Reform Action Plan, 2017
in day(s) if not indicated
Department of Labour:
Sl. No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline4 / Registration under Shops and Establishment Act / 1 / 1
31 / Approval of application for licence and renewal for contractors under Contracts Labour (Regulation and Abolition) Act, 1970 / 90 / 90
36 / Approval of application for registration and renewal of licence under Shops and Establishment Act / 30
41 / Approval of application for registration of Principal Employer’s establishment under Contracts Labour (Regulation and Abolition) Act, 1970 / 90 / 90
46 / Approval of application for registration under Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 / 30
51 / Approval of application for registration of establishment under Inter State Migrant Workmen (RE&CS) Act, 1979 / 90 / 90
130 / Online submission of Inspection Report / 48 hours / 48 hours
Factories:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline3 / Validity of factory licence and subsequent renewals / 10 years / 10 years
6 / Approval of application for registration, grant and renewal of licence under Factories Act / 90 / 90
11 / Approval of application for plan and permission to construct/ extend/or take into use any building as a factory / 90 / 90
16 / Approval of application for registration, grant and renewal of licence under Boilers Act / 30 / 30
21 / Approval of application for boiler manufacturer and renewal under Boilers Act / 21 / 21
25 / Approval of application for boiler erector and renewal of licence under Boilers Act / 21 / 21
124 / Online submission of Inspection Report / 48 hours / 48 hours
Partnership:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline392 / Registration of Partnership Firm / 30
Co-opration:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline397 / Registration of Societies / 30
Law:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline58 / Commercial Disputs
(i) First Hearing / 30
(ii) Filing of Statement of Defence / 20
(iii) Completion of the evidence period / 60
(iv) Filing of testimony by expert / 30
(v) Submission of final judgment / 180
59 / Maximum number of adjournments that can be granted in commercial disputes / 3
60 / Maximum number of adjournments due to unforeseen and exceptional circumstances / 3
Registration and Stamps:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline85 / Document registration and mutation of land / 30
Single Window:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline184 / All approvals to be issued by Single Window Body / 30
185 / Intent letter, granting sanction and disbursal of applicabl incentives under Industrial/ Sectoral Policy / 60
210 / Queries/clarifications related to investor’s application / 7 / 7
Fire:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline252 / NOC Certificate prior to commencement of construction activities / 7
MSPDCL:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline295 / Charged electricity connection up to 150 KVA
(i) where no ‘Right of Way’ is required / 7 / 7
(ii) where ‘Right of Way’ is required / 15 / 15
300 / Certificate of Electrical Installation / 7
PWD:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline297 / Grant of ‘Right of Way’ (RoW) permission / 30
PHED:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline305 / Obtaining of water connection / 7
IDCs:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline218 / Land allotment / 30
222 / Conversion of land/change in land use for outside industrial park / 60
MAHUD:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline102,113 / Online submission of Inspection Report / 48 hours
235 / Grant of construction permits for
(i) all required approvals / 45
(ii) pre-construction / 20
(iii) during construction / 20
(iv) post construction / 20
237(iv) / Issuance of digitally signed approved building plan / 30 / 30
238 / Building permit / 30 / 30
239 / Construction permits / 45 / 45
(i) Building Plan approval / 30 / 30
(ii) Plinth inspection / 7 / 7
(iii) Final completion/occupancy certificate (7 days for inspection + 1 day for issuing the certificate) / 8 / 8
402 / Grant of Trade Licence / 10
411 / Registration for levies imposed by State and Local Bodies (other than subsumed under GST) / 30
Forest:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline107 / Online submission of Inspection Report / 48 hours / 48 hours
242 / NOC for tree felling / 15
246 / Approval of application for Tree Transit Permit / 1
Pollution Control Board:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline166 / Online submission of Inspection Report / 48 hours
259 / Validity for consent to Operate / 5 years / 5 years
260 / Validity for consent to Establish / 5 years / 5 years
262 / Consent to establish under Water (Prevention and Control of Pollution) Act, 1974 / 120 / 120
267 / Consent to establish under Air (Prevention and Control of Pollution) Act, 1981 / 120
272 / Authorisation under Hazardous and Other Waste (Management and Transboundary Movement) Rules, 2016 / 120
277 / Consent to operate under Water (Prevention and Control of Pollution) Act, 1974 / 120 / 120
282 / Consent to operate under Air (Prevention and Control of Pollution) Act, 1981 / 120
Pollution Control Board:
Sl.No / Area / provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline1/166 / Online submission/uploading of Inspection Report / 48 hours
Red category of industries / 30 working days
Orange category of industries / 20 working days
Green category of industries / 10 working days
Non-polluting industries / Not required
Bio-medical Waste receiving, transporting, handling, storing, treatment and generating units / 10 working days
Hazardous Waste handling, generation, collection, storage, packaging, transporting, use, treatment, processing, recycling, recovery, pre-processing, co-processing, utilization, offering for sale, transfer or disposal units / 30 working days
e-waste from manufacture, refurbisher, dismantlers and recyclers / 15 working days
2 / Issue of Consent or Authorisation Certificate / 3 to 4 months / 2 months
4/259 / Validity for consent to Operate / 5 years / 5 years
Red category of industries / 5 years
Orange category of industries / 10 years
Green category of industries / 15 years
Non-polluting industries / Consent not required
3/260 / Validity for consent to Establish / 5 years / 5 years
Red category of industries / 5 years
Orange category of industries / 10 years
Green category of industries / 15 years
Non-polluting industries / Consent not required
5 / Authorisation of Bio-medical Waste receiving, transporting, handling, storing, treatment and generating units / In synchronization with consent certificate / In synchronization with consent certificate
6 / Authorisation of Hazardous Waste handling, generation, collection, storage, packaging, transporting, use, treatment, processing, recycling, recovery, pre-processing, co-processing, utilization, offering for sale, transfer or disposal units / 5 years / 5 years
7 / Authorisation of e-waste from manufacture / 5years / 5 years
Authorisation of e-waste from refurbisher / One time / One time
Authorisation of e-waste from dismantlers or recyclers / 5years / 5 years
262 / Consent to establish under Water (Prevention and Control of Pollution) Act, 1974 / 120 / 120
267 / Consent to establish under Air (Prevention and Control of Pollution) Act, 1981 / 120
272 / Authorisation under Hazardous and Other Waste (Management and Transboundary Movement) Rules, 2016 / 120
277 / Consent to operate under Water (Prevention and Control of Pollution) Act, 1974 / 120 / 120
282 / Consent to operate under Air (Prevention and Control of Pollution) Act, 1981 / 120
Taxation:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline309 / VAT refund payment / 60 / 60
327 (366) / Registration for Professional Tax / 1 / 1
Health Services:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline375 / Retail Drug Licence (Pharmacy) and renewal / 30
379 / Wholesale Drug Licence / 30
383 / Granting and renewal of Drug Manufacturing Licence / 60
Legal Metrology:
Sl.No / Area / If provided by relevant Act / Recommended by BRAP, if any / Proposed Timeline178 / Online submission of Inspection Report / 48 hours / 48 hours
386 / Registration and renewal under Legal Metrology Act, 2009 / 30
---