Standard Costing and Variance Analysis Problems
Problem 1:
Mix and Yield
Standard (Production: 1 unit) / Actual (Production: 1 unit)SQ (g) / SP ($) / Total / AQ (g) / AP ($) / Total
Material A / 8 / 6 / 48 / 9 / 5 / 45
Material B / 10 / 10 / 100 / 9 / 9 / 81
Material C / 14 / 13 / 182 / 18 / 14 / 252
Total / 32 / $330 / 36 / $378
Required:
- Price Variance
- Mix Variance
- Yield Variance
Problem 2:
Mix and Yield
Standard (Production: 10 units) / Actual (Production: 25 unit)SQ (g) / SP ($) / Total / AQ (g) / AP ($) / Total
Material A / 150 / 10 / 1,500 / 400 / 12 / 4,800
Material B / 120 / 17 / 2,040 / 300 / 15 / 4,500
Material C / 130 / 22 / 2,860 / 300 / 25 / 7,500
Total / 400 / $6,400 / 1000 / $16,800
Required:
- Price Variance
- Mix Variance
- Yield Variance
Problem 3:
Materials Variance Analysis:
The Mabuhay Lawn Furniture Company uses 12meters of aluminum pipe at $0.90 per meter as standard for the production of its Type A lawn chair. During one month's operations, 150,000 meters of the pipe were purchased at $0.82 a meter, and 7,500 chairs were produced using 100,300 meters of pipe. The materials price variance is recognized when materials are purchased.
Required:Materialsprice and quantity variances.
Problem 4:
Materials Variance Analysis:
The standard price for material 4-363 is $4.65 per liter. During December, 3,000 liters were purchased at $4.40 per liter. The quantity of material 4-363issued during the month was 1,997 liters and the quantity allowed for December production was 2,225 liters.Calculatematerialsprice variance, assuming that:
Required:Materialsprice variance, assuming that:
- It is recorded at point of purchase (Materialspurchase price variance).
- It is recorded at point of requisition (Materialsprice usage variance).
Problem 5:
Labor Variance Analysis:
The processing of a product requires a standard of 0.75 direct labor hours per unit for Operation 7-116 at a standard wage rate of $7.35 per hour. The 2,500 units actually required 1,740 direct labor hours at a cost of $7.90 per hour.
Required:Calculate:
- Labor rate variance.
- Labor efficiency variance.
Problem 6:
Factory Overhead Variance Analysis:
Borel Company uses a standard cost system. The factory overhead standard rate per direct labor hour is:
Fixed: / $5,500 / 5,000 hours / = / $1.10Variable: / $8,500 / 5,000 hours / = / $1.70
------
$2.80
For October, actual factory overhead was $13,000 (Fixed = $5,500, Variable = $7,500), actual labor hours worked were 4,500 and the standard hours allowed for the production were 4,800.
Required:
1.)Variable OH Efficiency variance
2.)Fixed OH Efficiency variance
3.)Variable OH Spending Variance
4.)Fixed OH Spending Variance
5.)Idle Capacity Variance
6.)Controllable Variance
7.)Volume Variance
Problem 7:
Variance Analysis:
On June 1, Bogart Company began the manufacture of a newmechanicaldevice known as "Candy." The company installed a standard cost system in accounting formanufacturingcosts. The standard costs for a unit of Candy are:
Materials: 8 lbs. at $1.25 per lb. / $ 10.00Direct labor: 1.5 hours at $5 per hour / $ 7.50
Factory overhead: 80% of direct labor cost / $ 6.00
------
Total / $23.50
======
The following data were obtained from Bogart's record for June:
Actual production of Candy / 6,000 unitsUnits sold of Candy / 3,750
Sales / $75,000
Purchases (50,000 pounds) / 67,500
Materialsprice variance (applicable to June purchase) / $5,000 unfavorable
Materialsusage variance / 2,000 unfavorable
Direct labor rate variance / 800 unfavorable.
Direct labor efficiency variance / 1000 favorable
Factory overhead total variance / 750 unfavorable
Required:
- Standard quantity ofmaterialsallowed (in pounds).
- Actual quantity ofmaterialsused (in pounds).
- Standards hours allowed.
- Actual hours used.
- Actual direct labor rate.
- Actual total factory overhead.
Answers:
Problem 1:Price variance - $0
Mix Variance - $6.75 unfavorable
Yield Variance - $41.25 unfavorable
Problem 2: Price variance - $1,100 unfavorable
Mix Variance - $300 favorable
Yield Variance - $0
Problem 3: MPPV - $12,000 favorable
MUV - $9,270 unfavorable
Problem 4:MPPV - $750 favorable
MPUV - $499.25 favorable
Problem 5:LRV - $957 unfavorable
LEV - $992.25 favorable
Problem 6:Variable OH Efficiency variance - $510 favorable
Fixed OH Efficiency variance - $330 favorable
Variable OH Spending Variance - $150 favorable
Fixed OH Spending Variance - $0
Idle Capacity Variance - $550 unfavorable
Controllable Variance - $660 favorable
Volume Variance - $220 unfavorable
Problem 7: Standard quantity ofmaterialsallowed – 48,000 lbs
Actual quantity ofmaterialsused – 49,600 lbs
Standards hours allowed – 9,000
Actual hours used – 8,800
Actual direct labor rate - $5.0909
Actual total factory overhead - $36,750