FORMAT: C - 1
Application for Connection intending inter-connection with Intra-State Transmission System (InSTS)
(To be submitted by the Generating Company)
A / GENERAL1 / Name of the Generating Company
2 / Address of the Generating Company
3 / Details of Power Project
Location of Project (Site, Taluka, District)
No. of Units and Capacity of each Unit
Type of fuel
4 / Details of Contact Person
Name
Designation
Mobile No.
Phone No.
Fax No.
E-Mail ID
5 / Details of Point of Injection
Name of Transmission Licensee with whom system’s connection is required or any existing connection to be modified
Name of EHV Sub-Station or EHV Line to which Project is being inter-connected
Voltage Level of Inter-connection
Inter-connection arrangement
Generation Voltage and Step-up Voltage (kV)
Details of feeder protection on outgoing feeders to be connected to Transmission Licensee system for evacuation of power.
Attach Single Line Diagram of Point of Injection
Attach Copy of Single Line Diagram and layout of power station, switch yard
B / CONSTRUCTION SCHEDULE & COD of units
1 / Unit No. / Unit Size (MW) / Date of Work Commencement / Work Completion Date / Date of Synchronization
(Scheduled) / Scheduled Commercial Operation Date (COD)
C / GENERATOR
1 / Metering system provided on lines indicating ownership and responsibility for joint meter reading, sealing and calibration etc. as per Metering Code
2 / Details of feeder protection on outgoing feeders to be connected to Transmission Licensee system for evacuation of power.
3 / Details of relay schemes provided for Generator Protection, Generator Transformer Protection and Unit Auxiliary Transformer Protection.
4 / Generator Capability Curve and droop characteristic curve at which it shall operate upon
5 / Governor characteristic and confirmation of complying with Grid Code Requirement.
6 / Details of data acquisition and control system for unit being inter-connected.
7 / Start-up power requirement and black-start sequence and process.
D / CERTIFICATION & CONFIRMATION
1 / Copy of Power Purchase Agreement /MOU for power purchase
2 / Consent from the concerned Distribution Licensee for drawal of infirm power
3 / Confirmation to the effect that all conditions outlined in the Connection Agreement, Site Responsibility Schedule shall be complied with by the user applying for new connection or modification of existing connection.
4 / Confirmation to the effect that Standard Planning Data (Generation) in compliance to Grid Code for new connection
5 / Detailed Planning Data (Generation) in compliance to Grid Code for new connection
E / COMPLETION REPORT
1 / Work Completion Report (certified from the Concerned Transmission Licensee) and
2 / The Generating Company shall furnish the Planning and existing data in the prescribed formats as when required.
Note: Filling up of all the columns in the above form are mandatory and for any irrelevant column please specify as “Not Applicable”.
It is hereby certified that the applicant unequivocally confirms to the terms and conditions and has fully understood the guidelines issued by STU for Time Extension of Grid Connectivity on intra-state transmission system. I have verified the above mentioned information & documents attached and are in order.
Authorized Signatory
Name :
Place: Designation :
Date: Seal :
Page 3 of 3