Contract CO35/14

BALLARAT COURT PENSIONER HOUSING COMPLEX RE-ROOF

Cnr Denmark/Miller Streets, Dannevirke

February 2015

Tenders close with:

The Tenders Secretary

Tararua District Council

26 Gordon St

P O Box 115

Dannevirke

At 4.00pm on Wednesday the 18th of March 2015

Envelopes containing the tenders to be endorsed with:

“Tender for Contract CO35/14 BALLARAT COURT PENSIONER HOUSING COMPLEX RE-ROOF”

Contents

Part 1: Tender Documents

1.  Key Information for Tenderers

2.  Conditions of Tendering

3.  Schedule to Conditions of Tendering

4.  Non-price Attributes

5.  Agreement as to Arbitration

6.  Tender Form

7.  Schedule of Prices

Part 2: Conditions of Contract

1.  General Conditions of Contract

2.  First Schedule: Special Conditions of Contract

3.  Second Schedule: Contract Agreement

4.  Eighth Schedule: Certificate as to Contractor’s Public Liability Insurance

5.  Tenth Schedule: Certificate as to Contractor’s Motor Vehicle Insurance

Part 3: Contract Specifications

1.  Management

2.  Administration

3.  Health And Safety

Part 4: Appendices

1.  Site Map


Part 1: Tender Documents

Section 1: Key Information for Tenderers

Contract CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX RE-ROOF

Tararua District Council has the following goals for procurement:

·  To obtain best value for money in a transparent manner

·  To enable fair competition and encourage competitive and efficient markets

Tararua District Council has chosen in its new procurement strategy to achieve these goals by promoting collaborative working with the contracting industry.

This means that when a ‘best value’ contract relationship exists, and any project or activity can be done as a variation or negotiation to avoid unproductive tender costs, Tararua District Council will in the first instance seek to negotiate a variation.

This means in this instance that under the new Tararua District Council Procurement Strategy there exists provision for extending the scope of this contract.

1.1  Description of Contract and Contract Period

This contract sets out the requirement for the reroofing of Ballarat Court Pensioner Housing Complex in Dannevirke.

The start date for the Contract is after the 23rd of March 2015.

1.2  Principal’s Expectations

The Principal wishes to engage a Contractor who can:

·  Minimise costs achieving best value for money

·  Minimise interruption to residents

1.3  Tender Enquiries

Enquiries during the tender period shall be submitted in writing no later than 3 days preceding the tender closing date to:

Colin Veale

Community Assets and Property Manager

Tararua District Council

26 Gordon Street

P O Box 115

Dannevirke 4942

Ph: 06 374 4080 Fax 06 374 4137

1.4  Tender Evaluation

Tenders will be evaluated using the lowest price conforming method (see NZTA’s Procurement Manual, Appendix C)

Section 2: Conditions of Tendering

Contract CO35/14 BALLARAT COURT PENSIONER HOUSING COMPLEX RE-ROOF

The Conditions of Tendering shall be those included in NZS3910:2013 Conditions of Contract for Building and Civil Engineering – Fixed term, with amendments as shown below.

Replace Clause 104.3 with the following clause:

The Principal will only consider tenders based on the Tender Documents.

Add the following new clause, Clause 104.4:

No unauthorized alteration to the Tender Documents shall be accepted.

Replace Clause 105.2 with the following clause:

Tenders shall be delivered at the place for closing before the closing time. Fax or other electronic means of delivering tenders to the Principal will not be acceptable.

No alternate tenders will be accepted

Section 3: Schedule to Conditions of Tendering

Contract CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX RE-ROOF

The Conditions of Tendering shall be those included in NZS3910:2013 Conditions of Contract for Building and Civil Engineering – Fixed Term with the following Schedule.

102.2

No Tender Documents deposit is required.

105.1

Tenders close at 4.00pm on Wednesday the 18th of March 2015 at:

Tararua District Council

26 Gordon Street

P O Box 115

Dannevirke 4942

Tenders shall be addressed to the Tenders Secretary, and marked on the outside of the envelope:

“Tender for Contract CO35/14 Ballarat Court Pensioner Housing Complex Re-Roof”

The information required includes:

·  A completed and signed tender form

·  A completed and signed schedule of prices

·  Tenderer’s proposal including all information relating to the non-price Attributes outlined in Section 4 of this tender document.

106.3

An agreement as to arbitration is to be completed by the Principal and form part of the contract documents

107

Tender evaluation to be by the lowest price conforming method as described in NZTA Procurement Manual.

·  Tenderer’s Non-Price Attributes (see Section 4)

Ø  Relevant Experience & Track Record

Ø  Nominated Personnel

Ø  Plant & Equipment

Ø  Management Skills

Ø  Methodology

The tenderer’s attributes shall not exceed 5 single sided A4 pages of ordinary type (12 point Times Roman or similar type face)

Section 4: Non-price Attributes

Contract CT CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX RE-ROOF

Further to clause 107 Schedule to Conditions of Tendering, the tenderer shall provide information about the following attributes.

·  Relevant Experience & Track Record

·  Nominated Personnel

·  Plant & Equipment

·  Management Skills

·  Methodology

4.1 Relevant Experience & Track Record

Tenderer’s must provide detailed evidence of their experience to complete Contract Works described in these documents for two separate projects.

4.2 Nominated Personnel

Tenderer’s must nominate and state the key technical skills of the nominated personnel.

4.3 Plant & Equipment

The tenderer must submit details of all plant and equipment items that will be used in the execution of the Contract Works.

4.4 Management Skills

Tenderer’s must describe the management methods and skills they will use to successfully complete the Contract Works. The description must include:

·  Attributes and management skills of all nominated personnel

·  Lines of communication within the contract management team and with the Engineer, delegation of duties and authority

4.5 Methodology

Tenderer’s must describe the methodology they will use to complete the Contract Works on time and to the standard specified in the Contract Documents.

Any tender proposal, when evaluated, which scores less than half the allocated marks for one or more of the attributes listed, will be excluded from any further consideration by the evaluation panel.

Agreement as to Arbitration

This Agreement is made on (insert date):

Between (the Principal): Tararua District Council

And (the Contractor):

The Contractor has submitted a tender for:

Contract CO35/14 BALLARAT COURT PENSIONER HOUSING COMPLEX RE-ROOF

The Principal intends to accept such Tender by the letter of acceptance which accompanies this agreement. Such tender and its acceptance, together with the General Conditions and other documents intended to form part of the contract, will constitute a contract. By clause 106.3 of the Conditions of Tendering, no acceptance of tender is valid unless accompanied with a separate agreement to the effect there set out.

By this present separate agreement, and in consideration of the Contractor’s tender, the Principal certifies that, having read and understood the arbitration agreement contained in Section 13 of the General Conditions, it agrees to be bound by it.

Signed for the Principal by:

In the presence of:

TENDER FOR: Contract CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX RE-ROOF

The Chief Executive

Tararua District Council

P O Box 115

Dannevirke

I/We the undersigned hereby tender the sum of:

(words)

(figures)

(excluding GST) for the above-mentioned works described in the drawings, specifications and Conditions of Contract.

I/We further understand that the Principal is not bound to accept the lowest or any tender.

Name of Company:

Address:

Contact Person:

Signature:

Telephone Number:

Fax Number:

Email Address:

GST Number:

Date:

Contract CO35/14 BALLARAT COURT PENSIONER HOUSING COMPLEX

RE-ROOF

Schedule of Prices

Item / Description / Unit / Quantity / Rate / Amount
Rate x Quantity
1 / Removal of decramastic roofing tiles
2 / Disposal of decramastic roofing tiles/building paper
3 / Supply and install new building paper, approved coloured long run roofing steel, ridging, barge flashings, PVC guttering and downpipes
Total excluding GST:
(This is the Tender Sum)

Notes:

Scheduled rates to include provision for:

Item 1:

·  Record keeping costs

·  Claims costs

·  Insurance costs

·  Labour costs

·  Plant and vehicle costs

·  Waste disposal fees

Part 2: Conditions of Contract

Section One : General Conditions of Contract

The General Conditions of Contract shall be those included in NZS3910:2013 Conditions of Contract for Building and Civil Engineering.

7.1 Indemnity

Add the following sub-clause to 7.1.1

7.1.1 (d) Any loss (including any solicitor/client legal costs) or liability incurred by the principal in respect of any proceeding or action taken against the Principal for failure by the Contractor to comply with the provision of any statute, regulation, bylaw or other requirement of Government, local or other public authorities that may be applicable to the Contract Works.

Section Two: Schedules to the General Conditions of Contract

First Schedule: Special Conditions of Contract (clause numbers refer to General Conditions) of NZS3910:2013

1.2

The Principal is:

Tararua District Council

26 Gordon Street

Dannevirke

1.2 (b)

There are no separable portions in this Contract.

3.1.1

A Contractor’s bond is not required.

3.2.1

A Principal’s bond is not required.

5.4.1

The Contractor shall commence the contract after the 23rd of March 2015.

6.1.2

The Engineer is:

Kathy Dever-Tod

Manager Assets Group

Tararua District Council

26 Gordon Street

P O Box 115

Dannevirke 4942

Phone 06 374 4080

Fax 06 374 4137

6.3

The Engineer’s Representative is:

Colin Veale

Community Assets and Property Manager

Tararua District Council

26 Gordon Street

P O Box 115

Dannevirke 4942

Phone 06 374 4080

Fax 06 374 4137

8.1 and 8.3

The Contractor shall insure as provided in 8.1 and 8.3

8.3.1

Public Liability Insurance shall be effected for an amount not less than $5,000,000.

8.3.2

Motor Vehicle Third Party Liability Insurance shall be effected for an amount not less than $1,000,000.

11.1.1

The period of defects liability shall be zero (0) weeks.

12.1

The claim shall be submitted and paid upon completion of the contract works.

12.3.1

No retentions will be retained for this contract.

12.8.2

Cost fluctuation adjustments shall be paid for works carried out in the second and third years according to the provisions of NZS3910:2013 Appendix A

12.11.1

There is no contingency sum included in this Contract.

15.1.2

For the purpose of service of notices, the postal address of:

(a)  The Principal is P O Box 115

Dannevirke 4942

Fax: 06 374 4137

(b)The Engineer is P O Box 115

Dannevirke 4942

Fax: 06 374 4137

SECOND SCHEDULE

Contract Agreement

Contract for; CT CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX RE-ROOF

THIS AGREEMENT is made on

BETWEEN.

(“the Contractor”)

AND..

(“the Principal”).

IT IS AGREED as follows:

1. THE Contractor shall carry out the obligations imposed on the Contractor by the Contract Documents.

2. THE Principal shall pay the Contractor the sum of $

or such greater or less sum as shall become payable under the Contract Documents together with Goods and Services Tax at the times and in the manner provided in the Contract Documents.

3. EACH party shall carry out and fulfil all other obligations imposed on that party by the Contract Documents.

4. THE Contract Documents are this Contract Agreement and the following which form part of this agreement:

(a) The Conditions of Tendering;

(b) Notices to tenderers (give details with dates);

(c) The Contractor’s tender;

(d) The notification of acceptance of tender;

(e) The General Conditions of Contract, NZS 3910:2013;

(f) The Special Conditions of Contract;

(g) Specifications issued prior to the Date of Acceptance of Tender;

(h) The Schedule of Prices; (Delete if not applicable)

(i) The following additional documents: (Identify any additional documents to be included for example agreed correspondence.)

WITNESS to the signature

of the Contractor:

......

Contractor

WITNESS to the signature

of the Principal:

......

Principal

EIGHTH SCHEDULE

INFORMATION AS TO PUBLIC LIABILITY INSURANCE

To Whom It May Concern:

From:

(Name of insurance company)

(Branch)

(Address)

We confirm having effected public liability insurance for:

(The Contractor)

(The Principal)

In respect of: Contract CT CO35/14 BALLART COURT PENSIONER HOUSING COMPLEX

RE-ROOF

(Project title)

Annual policy / Yes / No
Policy expiry date:
8.3.1 / The limit of indemnity / $ / (Plus GST)
Sub limit insured for vibration, removal or weakening of support / $ / (Plus GST)
Deductible is / (GST inclusive) / $
Deductible for vibration, removal or weakening of support / (GST inclusive) / $
We advise that “additional” terms, copy attached, have been specifically applied to this project / Yes / No
The policy covers liability arising out of:
The ownership / use of construction machinery not required to be registered for road use / Yes / No
The use of hired plant / Yes / No
The ownership / use of watercraft up to 8m / Yes / No
The ownership / use of aircraft / Yes / No
The use of explosives / Yes / No
8.5.3, 8.8.4 / Policy cover terms included are:
(a) Automatic reinstatement / Yes / No
(b) No cancellation for non-payment without prior notification / Yes / No
(c) Severally insured / Yes / No
(d) No settlement delay due to exercise of subrogation / Yes / No

We undertake that this policy will not be cancelled or amended by us without written advice to the insured party which has arranged the insurances.

The insurance issued is subject to the terms and conditions of the policy. We do not warrant that this policy complies with the requirements of NZS 3910:2013.

Insurance Company Stamp Date

(Or name of insurance broking company confirming cover)

SIGNED BY

SIGNATORY TITLE

(Clause numbers refer to NZS 3910:2013 and are for information only)