Contract N62473-11-D-0041
Proposed Task Order XXXX
Repair Fire Suppression System
Building 625
Project BA12-21M
Work Order 1307756
Marine Corps Logistics Base, Barstow (MCLB Barstow)
June 2013
/ RequestforProposal /Repair Fire Suppression System, Building 625 Work Order Number 1307756
Marine Corps Logistics Base Barstow (MCLB Barstow), Barstow, CA
TABLE OF CONTENTS
PART 1: PROPOSAL FROMS and CONTRACTUAL DOCUMENTS
Part 1 will be distributed by separate cover.
PART 2: GENERAL REQUIREMENTS
01 14 00.05 20 Work Restrictions for Design-Build
01 20 00.05 20 Price and Payment Procedures for Design-Build
01 30 00.05 20 Administrative Requirements for Design-Build
01 31 19.05 20 Post Award Meetings
01 32 17.05 20 Network Analysis Schedules (NAS) for Design-Build
01 33 00.05 20 Construction Submittal Procedures
01 33 10.05 20 Design Submittal Procedures
01 35 13.05 20 Special Project Procedures for Design-Build
01 35 26.05 20 Government Safety Requirements for Design-Build
01 45 00.05 20 Design and Construction Quality Control
01 50 00.05 20 Temporary Facilities and Controls for Design-Build
01 57 19.00 20 Temporary Environmental Controls
01 57 19.01 20 Supplemental Temporary Environmental Controls
01 74 19.05 20 Construction and Demolition Waste Management for Design-Build
01 78 24.00 20 Facility Electronic Operation and Maintenance Support Information
PART 3: STATEMENT OF WORK/PROJECT PROGRAM
(See PART 3 Table of Contents)
PART 4: MINIMUM MATERIALS, ENGINEERING AND CONSTRUCTION REQUIREMENTS
(See Basic MACC)
PART 5: PRESCRIPTIVE TECHNICAL SPECIFICATIONS (Not Used)
PART 6: ATTACHMENTS
.
RFP Table of Contents
Repair Fire Suppression System, Building 625 Work Order Number 1307756
Marine Corps Logistics Base Barstow (MCLB Barstow), Barstow, CA
Contract N62473-11-D-0041
Proposed Task Order XXXX
Repair Fire Suppression System
Building 625
Project BA12-21M
Work Order 1307756
Marine Corps Logistics Base, Barstow (MCLB Barstow)
June 2013
Part 2
General
Requirements
Repair Fire Suppression System, Building 625 Work Order Number 1307756
Marine Corps Logistics Base Barstow (MCLB Barstow), Barstow, CA
SECTION 01 14 00.05 20
WORK RESTRICTIONS FOR DESIGN-BUILD
01/12
PART 1 GENERAL
1.1DEFINITIONS
Not used.
1.2SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 013310.0520 Design Submittal Procedures and Section 013300.0520 Construction Submittal Procedures.
SD-01 Preconstruction Submittals
List of contact personnel; G
Personnel List; G
Vehicle List; G
1.3SPECIAL SCHEDULING REQUIREMENTS
- Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:
- The facilities will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the activity.
- Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of fifteen (15) calendar days prior to the desired date of interruption.
- The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.4CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.4.1.1Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
- NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON). Information on costs and requirements to participate and enroll in NCACS is available at or by calling 18777274342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
- One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
1.4.2Working Hours
Regular working hours shall consist of an 8 1/2 hour period or as approved by the by the Contracting Officer; between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.4.3Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval. Make application fifteen(15) calendar days prior to such work to allow arrangements to be made by the Government, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.4.4Exclusionary Period
No work shall be performed outside the hours of 7 a.m. and 3:30 p.m., without prior written approval of the Contracting Officer. This period has been considered in computing the time allowed for the performance of this contract.
1.4.5Occupied and Existing Building(s)
The Contractor shall be working in a facility with secured access. Contractor shall expect delays in production due to limits in access. Warehouse shall remain in service during construction. Extensive coordination required to avoid disrupting, impeding, or interrupting the progress of government production work.
The Contractor shall be working in existing buildings which are occupied. Do not enter the building(s) without prior approval of the Contracting Officer.
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the facility during the construction period.
Relocate movable furniture (approximately 6 feet away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location(s) upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall at the completion of the work.
The Government will remove (and relocate) other Government property in the areas of the building(s) scheduled to receive work. The contractor shall provide the Contracting Officer notification of any such removal/relocation, fifteen (15) calendar days prior to the requirement.
1.4.6Utility Cutovers and Interruptions
- Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
- Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
- Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and or other systems shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be further limited to two (2) hours with exception of the fire alarm system. This time limit includes time for deactivation and reactivation. The contractor will not be required to provide a “fire watch”.
- Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4.6 1Location of Underground Utilities
Although not anticipated, if required, obtain digging permits prior to start of excavation by contacting the Contracting Officer fifteen (15) calendar days in advance. For excavations within the San Diego metropolitan area, applications for excavation permits shall be sent to NAVFAC SW, Coastal IPT, Utilities Systems Planning Division, Code 630 at 6195567348. Completed applications may be faxed to 6195567339, e-mailed or personally delivered. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
- Notification Prior to Excavation: Notify the Contracting Officer at least fifteen (15) days prior to starting excavation work.
1.5SECURITY REQUIREMENTS
Contract Clause "FAR 52.2042, Security Requirements and Alternate II," "FAC 5252.2369301, Special Working Conditions and Entry to Work Area," and the following apply:
For vaults, mailrooms and avionics spaces.
1.5.1Employment Restrictions for NAVFAC Southwest
Submit for approval, at least fifteen (15) days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
- Name
- Date and place of birth
- Citizenship
- Home address
- Social security number
- Current pass expiration date
- Naturalization or Alien Registration number
- Passport number, place of issue, and expiration date
The request for personnel passes shall be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S. citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated"
Signature/Firm Name
1.5.2.1Extraordinary Security Requirements
The Contract Clause entitled "Identification of Employees" and the following apply:
- Vehicle searches. All construction vehicles will be searched by the sentry.
- Photographs. Photographs are prohibited in and around the building unless a written request containing specific justification and details is approved by the security officer via the Contracting Officer. Four (4) days' advance notice is required. Photographs, when approved, shall be taken in the presence of an activity escort.
- Personnel restrictions. Due to sensitivity of building operations, the following apply:
(1)Restrict personnel to the designated work site.
(2)Contractor's movements within the building will be restricted. Contractor personnel will be escorted to and from designated work areas. Contractor personnel shall not be permitted outside of designated work areas without being escorted by authorized personnel. Submit requests for entry into the building four (4) days in advance with information required by paragraph entitled "Personnel List" for submission to the "Division Project Officer" through the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
RFP PART 2 – SECTION UFGS 01 14 00.05 20 - Page 1
Repair Fire Suppression System, Building 625 Work Order Number 1307756
Marine Corps Logistics Base Barstow (MCLB Barstow), Barstow, CA
SECTION 01 20 00.05 20
PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01/12
PART 1 GENERAL
1.1REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP11101-8/ (2009) Construction Equipment Ownership and Operating Expense Schedule, Vol 1-12
1.2SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 013310.0520 Design Submittal Procedures and Section 013300.0520 Construction Submittal Procedures:
SD-01 Preconstruction Submittals
Earned Value Report; G
1.3EARNED VALUE REPORT
1.3.1Data Required
This contract requires the use of a cost-loaded Network Analysis Schedule (NAS). The information required for the Schedule of Prices will be entered as an integral part of the Network Analysis Schedule. Within fifteen (15) calendar days of notice of award, prepare and deliver to the Contracting Officer an Earned Value Report (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2Schedule Instructions
Payments will not be made until the Earned Value Report from cost-loaded NAS has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM shall include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report shall be fully developed with detailed construction line items as design progresses. The complete design and construction Schedule of Prices or Earned Value Report shall be submitted and accepted prior to starting construction work.
For Fast-Tracked or Critical Path Submittals of construction projects, the Earned Value Report shall include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase. Additionally, the Earned Value Report shall be separated as follows:
- Primary Facility/s Cost Breakdown:
Defined as work on the primary facility/s out to the 1.5 m (five (5) foot) line. Work out to the 1.5 m (five (5) foot) line shall include construction encompassed within a theoretical line 1.5 m (5 foot) from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC equipment, that may extend beyond the 1.5 m (five (5) foot) line.
- Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 1.5 m (five (5) foot) line.
1.4CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.2367000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP111018.
1.5CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1Content of Invoice
Requests for payment will be processed in accordance with the Contract. Clause FAR 52.23227, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The Requests for payment shall include the documents listed below:
- The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Quality Control (QC) Manager as required by the contract.
- The Earned Value Report from the cost-loaded NAS, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use LANTNAVFACENGCOM Form 4-330/110 (New 7/84) on NAVFAC Atlantic contracts when a Monthly Estimate for Voucher is required.
- Updated Project Schedule and reports required by the contract.
- Contractor Safety Self Evaluation Checklist.
- Other supporting documents as requested.
- Updated copy of submittal register.
- Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
- Subcontractor and supplier payment certification.
- Materials on Site.
- Affidavit to accompany invoice (LANTDIV NORVA Form 44235/4 (Rev.5/81)).
- Solid Waste Disposal Report.
1.5.2Submission of Invoices
If NFAS Clause 5252.2329301 is included in the contract, the listed documents shall be provided as attachments in Wide Area Work Flow (WAWF). The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer. All other paper invoices shall be forwarded with specific marking on the envelope. This marking shall be in the front lower left hand corner, in large letters, "INVOICES - ENCLOSED."