Terminal Evaluation Review form, GEF Independent Evaluation Office, APR 2016
1. Project Data
Summary project dataGEF project ID / 3105
GEF Agency project ID / 3578
GEF Replenishment Phase / GEF-4
Lead GEF Agency (include all for joint projects) / UNDP- Lead Implementing Agency
FAO – Co-lead Implementing Agency (Component 1-3 activities)
Project name / Building Capacity to Eliminate POPs Pesticides Stockpiles
Country/Countries / Vietnam
Region / Asia and the Pacific
Focal area / POPs
Operational Program or Strategic Priorities/Objectives / POPs-3 and POPs-2
Executing agencies involved / Ministry of Natural Resources and Environment
NGOs/CBOs involvement / Local community groups in Thach Luu commune, Thach Ha district, Ha Tinh province - consultations
Private sector involvement / N/A
CEO Endorsement (FSP) /Approval date (MSP) / December 15th, 2008
Effectiveness date / project start / March 2010
Expected date of project completion (at start) / December 2013
Actual date of project completion
/ December 2015Project Financing
At Endorsement (US $M) / At Completion (US $M)
Project Preparation Grant / GEF funding / 0.350 / N/A
Co-financing / 0.075 / N/A
GEF Project Grant / 4.301 / N/A
Co-financing / IA own / 0.210 / N/A
Government / 6.406 / N/A
Other multi- /bi-laterals / N/A
Private sector / N/A
NGOs/CSOs / N/A
Total GEF funding / 4.651 / N/A
Total Co-financing / 6.616 / N/A
Total project funding
(GEF grant(s) + co-financing) / 11.266 / N/A
Terminal evaluation/review information
TE completion date / December 2015
Author of TE / Carlo Lupi and Toan Thang
TER completion date / February 14, 2017
TER prepared by / Punji Leagnavar
TER peer review by (if GEF IEO review) / Molly Watts
2. Summary of Project Ratings
Criteria / Final PIR / IA Terminal Evaluation / IA Evaluation Office Review / GEF IEO ReviewProject Outcomes / S / HS / - / MS
Sustainability of Outcomes / L / - / L
M&E Design / S / - / S
M&E Implementation / S / - / S
Quality of Implementation / HS / - / S
Quality of Execution / HS / - / S
Quality of the Terminal Evaluation Report / --- / - / S
3. Project Objectives
3.1 Global Environmental Objectives of the project:
The broader goal of the project was to “support to sustainable development in Vietnam through the elimination of POPs from the environment” (ProDoc, p.24)
3.2 Development Objectives of the project:
Objective of this project is “to remove capacity barriers to the sustainable elimination of POPs pesticides in Vietnam” (ProDoc, p.24). At project conception it had the following outcomes:
- Outcome 1. Improved capacity facilitates elimination of POPs pesticides stockpiles
- Outcome 2. All known stockpiles are destroyed and impacts on human health relieved
- Outcome 3: Improved chemicals management prevents importation and use of POPs pesticides
3.3 Were there any changes in the Global Environmental Objectives, Development Objectives, or other activities during implementation?
Although there were no changes in the GEOs and DOs, there were changes to Outcome 2. This occurred after the Project Inception meeting, so the project operated under this revised outcome for the entirety of project implementation. The language changed to: (TE, p.35).
Outcome 2: At least 5 sites with a minimum of 1,140 tons of POP pesticides stockpiles and pits are rehabilitated, stocks are destroyed and impacts on human health relieved at these sites within budget limitations
4. GEF IEO assessment of Outcomes and Sustainability
Please refer to the GEF Terminal Evaluation Review Guidelines for detail on the criteria for ratings.
Relevance can receive either a Satisfactory or Unsatisfactory rating. For Effectiveness and Cost efficiency, a six point rating scale is used (Highly Satisfactory to Highly Unsatisfactory), or Unable to Assess. Sustainability ratings are assessed on a four-point scale: Likely=no or negligible risk; Moderately Likely=low risk; Moderately Unlikely=substantial risks; Unlikely=high risk. In assessing a Sustainability rating please note if, and to what degree, sustainability of project outcomes is threatened by financial, sociopolitical, institutional/governance, or environmental factors.
Please justify ratings in the space below each box.
4.1 Relevance
/ Rating: SatisfactoryRelevance to GEF4 Strategic Objectives - the project is highly relevant with reference to the objective of the GEF4 focal area strategy on POPs. It supported several expected GEF-4 impacts, including: (a) GEF-supported countries have strengthened capacity for POPs management and consequently strengthened capacity for the general sound management of chemicals; (b) dangerous obsolete pesticides that pose a threat to human health and to the environment are disposed of in an environmentally sound manner, and; (c) the risk of adverse health effects from POPs is decreased for those local communities living in close proximity to POPs wastes that have been disposed of or contained. The project had several activities related to capacity building/training, direct removal of POPs waste from burial sites, and developing environmental management plans to reduce risk exposure to POPs from the surrounding populations.
Relevance to Vietnam national objectives: The ProDoc notes that “Vietnam has suffered perhaps more than any other country from the effects of POPs. Most of the negative impacts are associated with the war-time use of chemical defoliants” (ProDoc, p.5). Despite the government’s concern over POPs exposure, it lacked the necessary technology, knowledge and financing to begin eliminating POPs waste in a systematic and controlled manner. Thus, the project was an asset for the government and also supported a host of national policies and regulation concerning environmental safety and sustainable development.
Relevance to beneficiaries: There are several locations in Vietnam where dramatic health impacts, including deaths and birth abnormalities have resulted from storage of POPs pesticides. From the health perspective alone, this project was extremely relevant for local beneficiaries and communities living in close proximity to POPs waste and/or contaminated sites. The project helped to create the initial foundations for the country to identify, clean-up, and eliminate these toxins to ultimately improve the health of local populations.
4.2 Effectiveness
/ Rating: Moderately satisfactoryThe TE rated effectiveness as highly satisfactory. This TER disagrees with the rating, and rates effectiveness as moderately satisfactory since the project could not achieve all of its outcomes and lower level outputs. The main outcome, which was the elimination of POPs stockpiles was also only partially achieved, eliminating only 79% of what it originally set out to eliminate. A discussion on each outcome is below.
Outcome 1. Improved capacity facilitates elimination of POPs pesticides stockpiles
The project achieved all of its outcome/output targets and was able to demonstrate that it developed an improved capacity and knowledge that would facilitate the elimination of POPs stockpiles. The results framework had 10 separate outputs that were all achieved and rated in the TE as either satisfactory or highly satisfactory. One of the main achievements under this outcome was that the project developed an extensive data inventory for all of the 1,153 POPs pesticide sites in Vietnam, provided training for government staff on how to continuously update it, and fully integrated it into the Ministry of Natural Resources and Environment operations. Another achievement was creating many governance and institutional interventions, such as: a monitoring plan for the disposal of stockpiles ( Output 1.8), tender documents and budding processes for new companies wanting to open POPs sites (Output 1.10), and training of government staff in enforcement of POP pesticides clean-up (Output 1.6).
Outcome 2. At least 5 sites with a minimum of 1,140 tons of POP pesticides stockpiles and pits are rehabilitated, stocks are destroyed and impacts on human health relieved at these sites within budget limitations
Outcome 2 was the main focus of the project since it resulted in direct environmental impacts/benefits. This outcome can be rated as moderately satisfactory because it was not 100% achieved, but it came close. The project excavated, packaged, transported and destroyed approximately 900 tons of POP pesticide waste (~79% of originally envisaged) across 10 sites in Vietnam (TE, p.35). It also contained POPs pesticides in soil with a surface of approximately 3,480 m2 (TE, p.39).
Outcome 3: Improved chemicals management prevents importation and use of POPs pesticides
Outcome 3 is intended to increase capacity building and awareness in POPs legislation and management; it is considered a key component to ensure project sustainability. This outcome was partially achieved through the delivery of project outputs (the most notable achievement being the adoption of a national chemical safety standard), however the quality of the effectiveness of the outputs is lower than expected. For example, the project was supposed to develop a taskforce between customs agencies in Vietnam, China, Laos and Cambodia on pesticides (output 3.4). The TE noted that this output could not be finalized because the customs agents only agreed to talk about the issue in their annual meeting. Another setback was the project was supposed to evaluate and upgrade 5 storage facilities for confiscated pesticides at border sites. However, the project was only able to evaluate 2 facilities and was not able to upgrade any of them.
4.3 Efficiency
/ Rating: Moderately satisfactoryThis TER rates efficiency as moderately satisfactory. This rating is slightly lower than the TE which rated it as satisfactory. The project was extended by 2 years (at a no-cost extension) due to some factors which could have been prevented. One preventable factor was that at the beginning of the project, only one site in Vietnam was capable and licensed to dispose of POP pesticides (the Holcim Vietnam), which limited the project’s ability to achieve its planned outputs and the overall outcome of POPs elimination. This was a risk that the project could have foreseen, and the results frameworks could have been adjusted according to this factor. Other delays that affected efficiency included internal management problems between the two Implementing Agencies, and coordination issues related to staffing and procurement (discussed in Quality of Project Implementation section). However, despite the minor setbacks, the TE noted that the project operated with “a high cost effectiveness due to the well managed procurement of disposal services” (TE, p.8) which allowed it to complete many of the project activities at cost.
4.4 Sustainability
/ Rating: LikelyThe sustainability of the project is considered to be likely because the project has long term financial support from the government, has built strong capacities for government staff to respond to POPs sites, and has developed a series of policies and regulations that are integrated into national objectives. Below is a discussion of each of the sustainability dimensions:
Financial sustainability: The financial sustainability of the project looks likely because the government has committed to allocating approximately USD 48 million for the disposal of POPs and clean-up of contaminated sites. This new financial commitment is facilitated through the National Target Program. The TE noted that the government, at local and national levels, “has great and urgent expectations on the guidance and outcomes envisaged by the project to implement a plan for the optimal use of the above financial resources” (TE, p.41).
Institutional and governance sustainability: Vietnam has instituted key pieces of legislation that support the enforcement of the POPs activities, such as Decision 1946/QĐ-TTg - National Action Plan on treatment and prevention of POP Pesticides, and the Decision 1206/QĐ-TTg - National Target Program on Overcoming Pollution and Environment Improvement. Both of these policies have a state fund that has been allocated for POP pesticide interventions (TE, p.11). In addition, the project was able to upgrade an existing database on contaminated sites for the Department for Waste Management and Environment Improvement. The database will continue to be used for archiving information on contaminated sites adopting common standards. (TE, p.11) To that extent, it ensures some of the project results.
Socio-political sustainability: The capacity building activities of the project was one of its strengths and the TE notes that the increased awareness and technical capacity will probably help sustain project outcomes. Specifically, local authorities who were trained to be more sensitive to contaminated sites will be more likely to report and enforce rules for newly found sites.
Environmental sustainability: There were no noted risks to environmental sustainability.
5. Processes and factors affecting attainment of project outcomes
5.1 Co-financing. To what extent was the reported co-financing essential to the achievement of GEF objectives? If there was a difference in the level of expected co-financing and actual co-financing, then what were the reasons for it? Did the extent of materialization of co-financing affect project’s outcomes and/or sustainability? If so, in what ways and through what causal linkages?
The project originally planned to mobilize a total of USD 6,540,110 in co-financing. It is difficult to ascertain the final co-financing figures from the project, and the TE does not provide the latest final amount.
5.2 Project extensions and/or delays. If there were delays in project implementation and completion, then what were the reasons for it? Did the delay affect the project’s outcomes and/or sustainability? If so, in what ways and through what causal linkages?
The project was extended from December 2013 to December 2015. The delays were a result of internal administrative problems having to do with finances, co-management of the project and defining roles between FAO and UNDP, and hiring of staff. This did not in the end seem to affect the delivery or achievement of the project outcomes. In 2013, the Mid-Term Review suggested a project extension (at no cost) because some of the project activities needed more time to complete.
5.3 Country ownership. Assess the extent to which country ownership has affected project outcomes and sustainability? Describe the ways in which it affected outcomes and sustainability, highlighting the causal links:
According to the TE, the project had a high level of government ownership (TE, p.40). The Ministry of Natural Resources and Environment demonstrated a big commitment to the objective of the project. That was reflected in the way the project was executed as well as the new policy commitments from the government regarding the continuation of POPs activities in the country. Some of those policy initiatives include the 1946 /QĐ-TTg Plan to treat and prevent environmental pollution caused by pesticides stockpiles all over the nation, the USD 48 million allocation for the disposal of obsolete pesticides, and the regulation on remediation of pesticides to land use.
6. Assessment of project’s Monitoring and Evaluation system
Ratings are assessed on a six point scale: Highly Satisfactory=no shortcomings in this M&E component; Satisfactory=minor shortcomings in this M&E component; Moderately Satisfactory=moderate shortcomings in this M&E component; Moderately Unsatisfactory=significant shortcomings in this M&E component; Unsatisfactory=major shortcomings in this M&E component; Highly Unsatisfactory=there were no project M&E systems.
Please justify ratings in the space below each box.
6.1 M&E Design at entry
/ Rating: SatisfactoryThe TE and this TER rates the Quality of M&E Design as satisfactory. The project documents show that the project had a very robust system of M&E which included a logical hierarchy of outcomes, outputs and activities with supportive targets and baselines. The project justification and intervention techniques were justified in the project approach. As well, the indicators were SMART and the project even listed several impact indicators that it monitored throughout the span of the project, something that not all POPs projects have. Those were: Quantity of POP pesticides destroyed and Number of people previously exposed to POPs. The M&E design included two different results frameworks (one for the UNDP components and one for FAO components) because it wanted to streamline M&E activities for each of the Implementing Agencies.
6.2 M&E Implementation
/ Rating: SatisfactoryThe M&E implementation had many strengths and this TER and TE both rate it as satisfactory. M&E activities were delivered successfully and on time, and there were no indications that there were any serious problems in the project documents.
Of its strengths, the project showed an ability to integrate an adaptive management approach and adapted to an M&E system that was more efficient for project needs and measuring results. For example, the project initially did not have a set target for training activities for staff on the clean-up of contaminated sites, so instead it developed a quality control system based on pre and post assessments of the trainees which illustrated how much they learned. As well, the project team realized that a 2 separate results framework per organization was not efficient, so it consolidated the 2 into one common results framework to solve inconsistences related to the POPs disposal targets. The revised result framework was approved by UNDP regional office in September 2013 (TE, p.19). The project also used the MTR to reconsider how to change the project. The MTR provided several recommendations that the project management team accepted. Such as, requesting a project extension until 2012 for a no-cost extension, and to consolidate the bidding processes for entities doing clean-up and disposal (TE, p.12).
7. Assessment of project implementation and execution
Quality of Implementation includes the quality of project design, as well as the quality of supervision and assistance provided by implementing agency(s) to execution agencies throughout project implementation. Quality of Execution covers the effectiveness of the executing agency(s) in performing its roles and responsibilities. In both instances, the focus is upon factors that are largely within the control of the respective implementing and executing agency(s). A six point rating scale is used (Highly Satisfactory to Highly Unsatisfactory), or Unable to Assess.
Please justify ratings in the space below each box.
7.1 Quality of Project Implementation
/ Rating: SatisfactoryThe TE rated quality of implementation as highly satisfactory, and this TER rates it as Satisfactory. UNDP and FAO were the Lead and Co-Lead Implementing Agencies for the project. The TE noted that there were some small operational problems that hindered their overall effectiveness. Most of these issues were related to the operational set-up of the project between the two agencies, more than the quality of project implementation and backstopping. These issues were (TE, p.29):