China: Liaoning Medium Cities Infrastructure Project
Updated Procurement Plan(February 2013–October 2013)
I.General
- Project information:
Country: China
Borrower: People’s Republic of China
Project Name: Liaoning Medium Cities Infrastructure Project
Project ID: P 099992
Project Implementing Agency (PIA):
Liaoning Urban Construction and Renewal Project Office (LUCRPO) will coordinate and supervise all procurement activities. The PIAs for each project component are described as follows:
No. / Project Sub-component / PIA1 / Liaoyang Sub-component / PMO under the Urban Construction Bureau
2. / Jinzhou Sub-component / PMO under the Municipal Construction Committee
3 / Benxi Sub-component / PMO under the Municipal Construction Committee
4 / Panjin Sub-component / PMO under the Municipal Construction Committee
5 / Fushun Sub-component / PMO under the Municipal Construction Committee
- Bank’s approval Date of the procurement Plan:Revised on February1, 2013
- Date of General Procurement Notice: April 6, 2006
- Period covered by this procurement plan: February 2013– October 2013
II.Goods and Works and non-consulting services.
- Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:
Prior Review Thresholds Proposed (USD)
Goods / ≥0.5 million
Works / ≥ 5million
2. The procurement method thresholds for LMCI Project will be:
/ Civil Works / Goods / Consultant servicesICB / ≥20 million / ≥500K / >300K(short list not more than 2 from a country)
<300K (shortlist can be only from national consultants)
QCBS
<200K: CQS may be used; Individual Consultant (IC)
NCB / <20 million / <500K, ≥100K
Shopping / NA / <100K
- Prequalification:Not applied.
- Any Other Special Procurement Arrangements: Not applied.
4.Procurement Packages with Methods and Time Schedule
Ref. No. / Contract / Estimated Cost / Procurement / Category / Prequalification (yes/no) / Domestic Preference / Review / Expected / Estimated Construction(Description) / Method / (yes/no) / by Bank / Bid-Opening / Period (months)
(Million RMB) / (Million USD) / (Prior / Post) / Date
Benxi
BRI191 / Digong Road / 32.00 / 5.15 / NCB / CW / NO / NO / Prior (rebidding) / March, 2013 / 6
BRM171 / Jiefang North Road and Yingbin Road / 20.50 / 3.30 / NCB / CW / NO / NO / Post / March ,2013 / 6
BRM222 / Wheeled Paver (1.8m-4.2m), Asphalt Concrete Paver(12m), Milling Machine(0.5m), Wheeled Cold Recycling Machine(2m), Wheeled Pavement Roller(30t), Double Drum Vibrating Pavement Roller(12.5t), Double Drum Oscillatory Pavement Roller(12.5t), Rotary Type Snow Sweeper(2.4m), Acoustic Screen / 21.20 / 3.41 / ICB / G / NO / NO / Prior / April,2013 / 6
BRM232 / AsphaltMixing Equipment, Wheeled Excavator(0.7m3), WateringTruck(19m3), Sludge Transport Truck(5m3), Movable Pumping Station(120KW 600m3/h), Wheeled Loader(5t), Snow RemovingPlate, Snow Sweeping Roller Brush(2.6m), Snowmelt Agent Spreader Truck(6m3), Piping Endoscopic instrument, Cherry Picker Truck(20m), Cherry Picker Truck(16m), Sewer CleaningTruck, Multifunctional High Pressure Cleaning Truck / 19.80 / 3.18 / ICB / G / NO / NO / Prior / April,2013 / 6
III. Selection of Consultants
- Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Prior Review Thresholds Proposed (USD)
Consulting Service / ≥0.2 million for firm, ≥0.05 million for individuals, all SSS
- Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 300,000 or equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3.Any Other Special Selection Arrangements: No.
4.Consultancy Assignments with Selection Methods and Time Schedule
1 / 2 / 3 / 4 / 5 / 6Ref. No. / Description of Assignment / Estimated
Cost (USD) / Selection
Method / Review
by Bank
(Prior / Post) / Expected
Proposals Submission
Date
LUCRPO
IDRI23 / Institution Development and Reinforcement & Training and Investigation Consulting Service / 450,000 / QCBS / Prior / November, 2012
Domestic trainingand overseas study tours / Statement of Eligible Expense / 360,000
IDPM34 / The fourth round public participation / 60,000 / CQS / Post / March,2013
Note:
- Benxi Beidi Bridge contract comprises two parts, overpass railway and Taizi river, but the construction was changedby some objective factors including the Shendan high speed railway construction and enterprise resettlement, after the agreement with WB, the Beidi Bridge contractonly includes overpass railway part funded by WB,and overpass Taizi river part was changed to construct by municipal government’s own fund. it also caused remain WB loan of 10 million US dollar. In order to use loan fully before closing and based on communication between PMOs and project manager, it determined to use the remain loan for restartingsome projects-Yingbin Road, Digong Road and Jiefang North Road, which are into the procurement plan of PAD ,but as lacking of money, they could not be procuredat that time. The restart projects in this procurement plan are in line with the principle of FS, EMP and RAP under LMCIP
- The remaining loan also includes the road maintenance equipment procurement which are shortage in Benxi City.
- The technical evaluation report is approved by WB on 19 Nov,2012, it expected to submit the evaluation report and draft contract in the middle of December.
- Based on communication between WB and LUCRPO, it determined to use the remaining fund of consultant service to implement the fourth round public participation for the foundation of ICR.