SITE MONITORING REPORT

File Ref: 34 421 15 / Date: 24 May 2012 / Visit no: 1 of 3
Monitoring Officer: Tom McCarthy
Tel No: 01245 437507 / Time on site:
10:00 / Time off site: 10:30
Site Co-ordinator: Tom McCarthy / Tel No: 01245 437507
Site Name: Barling Landfill & Quarry, Barling Magna
Operator: Cory Environmental Limited
Site Representative: Kevin Coleby (Cory Environmental)
Permission no’s:
ESS/51/08/ROC: Review of Old Planning Permission (ROMP) application for permission reference ROC/634/90.
ESS/11/09/ROC: New portable building for use as a manager’s office and meeting room in substitution for a permission for two new separate buildings
ESS/36/05/ROC: Permanent installation of LFG flare within existing LFG generation plant
ESS/31/99/ROC: Installation of plant and machinery within a compound to utilise landfill gas for electricity generation
ESS/30/09/ROC: Erection of rehandling pad (not implemented)
ESS/29/10/ROC: Security compound - recently implemented and now in place
ESS/47/10/ROC: Increased surcharging on part of site
Permission Number & Romp Date Due
Outstanding Submission of details:
Permission No. / Condition No. / Scope of Condition and Action to be taken
ESS/47/10/ROC / 7/12 / Details of soil & machine movements required prior to soil being moved.
(also ESS/51/08/ROC conditions 5 & 11) – have been submitted to ECC (application validated 18/05/12).
33 / Noise monitoring – 6 monthly intervals (also ESS/51/08/ROC condition 27)
37 / Landscaping
Constraints:
Weather: Dry/ Windy / Rain / Snow
Noise: Acceptable/ Not acceptable / N/A
Approach Roads: Dry / Dusty / Wet / Muddy / Flooded
Ground: Dry / Dusty / Wet / Damp / Muddy / Flooded
Access: Obstructed / Not Obstructed / Mud on Road / Ice /
Slippery
Wheel Cleaning: Washer / Spinner / Sweeper / None – Sweeper is available on site but not operational during visit
Hose: In use / Not in Use / N/A
Machinery: Working / Not working – Landfill only
In correct position: Yes / No / N/A
Stockpiles: Height = N/A (stock pile of hardcore for use of site
haul road during winter)
Bunds: Profiled / Grassed / Weeds / N/A
Actions from last site visit:
None
Inspection Results Summary:
Site tidy and in good order, no significant signs of ‘blown away’ waste against northern boundary fence. Site actively seeking to ensure waste does not get blown away, fencing noted to the north-eastern corner of eastern cell.
Haul road clear and well maintained.
Landfill was currently taking place in the eastern cell, given the good weather, where it was noted that the surcharging on the section being worked was near the necessary level for restoration. It is anticipated (as advised by KC) that in due course, either this or next year, the next phase of the revision to the pre-settlement contours will take place.
Compliance with Conditions
Permission No. / Condition No. / Scope of Condition and Action to be taken / Action to be taken by
Operator or MPA/WPA
Officer
Actions to be taken before next site visit:
None – although note requirements of conditions as above.
Note: The actions noted in this report are required in order to ensure adequate progress is made and to avoid potential enforcement action against a breach of planning control.