Model City/ Town Permit Application Guidelines
Solar Permit Checklist for Photovoltaic Systems 10 kW or less
Amend this checklist for use in your jurisdiction
Plan Submittal Requirements
Section1. Building Permit application
Completed building permit application
Stamped structural letter
- Call out rafter size and type; rafter spacing; rafter span
Component Specification sheets (All components must be listed)
- Racking
- Modules
Method of sealing/flashing for roof penetrations
Liability insurance certificate
Workers comp affidavit
CSL license
HIC license
Cover sheet
Solar Permit affidavit
Bylaws letter
Building Permit application fee =
Section 2. Electrical Permit application
1-line (or 3-line) wiring diagram (2 copies printed on 11 x 17 paper)
- Inverter AC output disconnect location, utility disconnect location, and AC output over-current protection device rating.
- Location of combiner box(es), disconnect switch, size of source circuit overcurrent protection, if required
- Service panel bus rating and main circuit breaker/fuse ampere rating
- Circuit diagram with conduit, wire type and sizes, and/or cable type and wire sizes
- Equipment grounding and bonding conductors and grounding electrode conductor, if applicable
- Energy storage systems: Battery disconnect and overcurrent protection
Site plan drawing
- Roof plan showing location of equipment and, if required, fire setbacks
- Location of all existing structures and proposed PV system equipment (including modules, disconnects,inverters, panel boards, combiner boxes, storage batteries, utility meters, etc.)
- Plumbing vent termination: vent termination is not allowed under solar installations and must be relocated or modified in accordance with plumbing and residential codes
- Existing site easements, property lines, building setback lines, zoning setbacks
Component Specification sheets
- Racking
- Modules (listed to the UL 1703 safety standard)
- Inverter (listed to the UL 1741 Safety Standard)
- Energy storage
List of all appropriate labels and marking per NEC and IFC requirements
Electrical license
Signed contract with system owner
Debris affidavit
Electrical labels
Electrical Permit application fee =
Section 3. Estimated turnaround time on permits
Electrical permits will be issued within business days of receiving a complete application.
Building permitwill be issued within business days of receiving a complete application.
Section 4. Required Inspections (check all that apply)
Prior to module installation and while all electrical equipment is open
Rough inspection (wiring)
Rough inspection (building)
Once installation is complete, but prior to system activation
Final inspection (wiring)
Final inspection (building)
Inspectional Services Division ◦ Address
Contact phone number ◦ Contact Fax
Website