Annex 1 : Reporting progress with Legal Instruments – Undertakings

To be submitted electronically to

Filename : [Company acronym][improvement programme number]_ [annual submission point]_ [year covered by report]

Water Company:
DWI Scheme Reference:
Scheme name:
AMP Scheme:
Quality Parameter:
Agreed solution:
Progress report date:
Is the scheme still on course to meet the final date for completion of remedial action? / Yes
No
Do the dates and steps in the schedule continue to be appropriate? / Yes
No
If the answer to either of above questions is No, provide a date by which a Change Application will be or was submitted / DATE

Embed all supporting documents

Steps to be taken; /

Describe the detail in the Undertaking and provide details of the measures taken to fulfil this step during the reporting year

/

Due Date

/

Status:

On target

Delayed or

Actual date completed

Confirm hazard has been assessed as part of Regulation 27 Risk Assessment

/ / / Submit an action plan identifying short, medium and long term mitigating steps / Embed Action Plan
Short Term Measures
Develop and implement an enhanced monitoring strategy
Provide a summary of monitoring prior to implementation of solution - include number of samples and summary of results for six month period including mean and max concentrations. Provide details for any exceedence of the standard or MDQ. Report exceedances to Inspectorate. Confirm if site was out of supply. / Description
Yr 1
Yr 2
…..
Medium Term Measures
Submit a summary of investigation to confirm the appropriateness of the remedial measures proposed (for catchment programmes this includes modelling and investigations into high hazard areas) / Description
Yr 1
Yr 2
…..
Complete planning, design and procurement or remedial measures For schemes with multiple phase solutions provide details and actual completion date for each phase / Description
Yr 1
Yr 2
…..
Complete construction, installation and implementation of relevant solution For schemes with multiple phase solutions provide details and actual completion dates for each phase / Description
Yr 1
Yr 2
…..
Optimise existing treatment (For catchment schemes, this requirement may be ongoing for the duration of the undertaking) / Description
Yr 1
Yr 2
…..
For Lead Undertakings Only
Assess monitoring for rest of supply system to identify whether further DMAs meet high risk criteria.
Submit details of further high risk DMAs and method statement / Description
Yr 1
Yr 2
…..
For Catchment Programmes Only
Carry out a review of abstraction regimes / Description
Yr 1
Yr 2
…..
For Catchment Programmes Only
Support voluntary initiatives in upstream catchment. Engage with and provide data to the EA and other stakeholders / Description
Yr 1
Yr 2
…..
Long Term Measures
Continually appraise the risk associated with the hazard as part of the Regulation 27 Risk Assessment and ensure Regulation 28 documents are updated / Description
Yr 1
Yr 2
…..
For Catchment Undertakings Only
Provide Inspectorate with an Interim report on the success of the catchment measures and develop further measures to secure compliance if required / Description
Yr 1
Yr 2
…..
Monitor at an enhance frequency for 12 months following commissioning of remedial measures NB: This does not apply to catchment management or lead undertakings.
Provide a summary of monitoring undertaken - include number of samples and a summary of results including mean and maximum concentrations. Provide details for any exceedence of the standard. Confirm if site was out of supply. / Description
Yr 1
Yr 2
…..
Changes to assets covered by the undertaking
Original list of asset references / Original list of asset names / Replacement list of asset references / Replacement list of asset names

Details of bulk supplies from assets covered by the undertaking

Further Information:

Are there any other issues relevant to the scheme that you wish to mention?

Please provide details below.