CHINA

LIAONING THIRD MEDIUM CITIES INFRASTRUCTURE PROJECT (LMC3)

Procurement Plan

LIAONING DEVELOPMENT AND REFORM COMMISSION

FOREIGN FUND UTILISATION PROJECT OFFICE

April 1. 2008

I. Project Summary

1. Project Information: The People’s Republic of China is applying for a loan to support the China Liaoning Third Medium Cities Infrastructure Project. The proposed project includes six major cities in Liaoning, Anshan, Fushun, Benxi, Yingkou, Liaoyang and Huludao. The total investment is estimated as RMB 2,784 million, of which US $191 million (at the exchange rate of 7.5:1) is proposed to be financed by the World Bank loan. The project components are:

Project Name / Implementing Agency / Project Summary
Fushun Power Plant Heating Network Expansion / Fushun Power Plant Heating Company / (i) 63 new substations and 20 heating computation stations (ii) 27.5 km pipelines.
Yingkou Dashiqiao District Heating / Yingkou Dashiqiao Urban Construction and Investment Company / i) construct one new heat source plants, one installed with 4 x 64MW high temperature hot water boiler house; ii) construct 33.56km new primary network; iii)build 43 substations.
Yingkou EDZ District Heating / Yingkou EDZ Huayuan Heating Co., Ltd. / i) 84.586 km new primary network; ii) one relay pump station; iii) construct new and rehabilitate 77 substations.
Benxi Steel Central Heating / Benxi Steel (Group) Heating Development Co., Ltd. / i) construction of 41,672 meters of new trunk and part of branch pipelines of slag washing water heating network; ii) expansion of the existing primary booster pump station for heating network supplied by No. 3 power plant and construction of new pump station for return water; iii) construction of new water treatment plant and primary booster pump station for heating system supplied by slag washing water.
Haicheng District Heating / Haicheng City Hengye Heating Ltd. / (i) construction of 3×58MW new hot waterboilers; ii) 26 new substations; iii) construction of 19630m new primary network and rehabilitation of 75250m secondary network.
Benxi Nanfen District Heating / Benxi Steel (Group) Heating Development Co., Ltd. / (i)3×29MW new hot water boilers; (ii) 17,370 m of primary network; (iii) 11 new substations.
Liaoyang Gongchangling District Heating / Liaoyang City Gongchangling District Qinglong Heating Ltd / (i) one 3×58MW new hot water boiler; (ii) construct new and rehabilitate 19substations; (iii) 2 relay pump station; (iv) 37.562km new primary network.
Yangjiazhangzi Mining Area District Heating / Huludao Yangjiazhangzi EDZ Mudu Heating Company Ltd. / i) new construction of one heating plant with the capacity of 3 x 29MW ; ii) 13 new substations; iii) construction of 37.56km trunk pipelines.
Yingkou City District Heating / Yingkou Heating Company / i) contruct 23 new substatins and 60 old substations and one relay pump station; ii) construct 98.2km of new primary network.
Benxi City District Heating Phase II / Benxi Hengze Heating Development Company Ltd / i) construction ofthree heating plants with the capacities of: 2×58MW, 2x29MW and 3x58 MW each; (ii) 45 new substations; and (iii) pipelines of 17.4km.
Yingkou Gas Distribution Expansion and Rehabilitation / Yingkou General Gas Company / (i) new construction of one 50,000m3 of dry storage tank and rehabilitation of the existing one 50,000m3 and one 20,000m3 of storage tanks; (ii) construction of intelligent gas management system; iii) rehabilitate existing network.
Consulting services / Provincial PMO / Design review and institutional strengthening

2. Date of Approval of Procurement Plan: April 1, 2008

3. Planned Date of General Procurement Notice:Jan. 2008

4. Period covered by this procurement plan: 2008--2012

II. Goods and Works and non-consulting services.

1. Prior review

Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:

Procurement Method / Threshold for Prior Review
(US $) / Remarks
1. / ICB Goods / all
2 / NCB Goods / none
3 / ICB Works / all
4. / NCB Works / 5,000,000 plus the first contract

2. Prequalification

Bidders for all ICB civil works contracts shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3. Procurement Management Manual

To ensure effective implementation of the project, Liaoning PMO prepared a Procurement Management Manual that includes the following contents: procurement organizational structure, responsibilities of all entities involved in project implementation, management and procurement procedures. In the process of procurement, Liaoning PMO is responsible for general coordination and each project implementation unit will participate.

1

4.Procurement Packages with Methods and Time Schedule

Bo. / Contract/ Package / Contract Description / Contract
Number / Contract
Type / Proc.
Method / Prior-or Post-review / Bidding period / Prequalifi-cation / Period of Implementation / Total Cost
Million $
Civil Works
A.CITY CENTRAL HEATING
A1 / Fushun Heating
1 / Chengdong and Gaoshan Heating Network / Pre-insulated pipe DN150-1220mm; 32520m36 Civil works for substations / FSHC-1 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / May t to Oct.2009 / 11.122
2 / Park and Dongcheng Heating Network / Pre-insulated pipe DN150-1220mm23730m;
Civil works for 27 substations / FSHC-2 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 7.558
A2 / Yingkou Dashiqiao Heating
3 / Primary network/substations of Central Heat Source / Pre-insulated pipe DN25- 900 mm 29,900m; 43substation(0.0023-0.3537 million m2 heating area)
including 12 building level substations
Pre-insulated pipe DN200- 300 mm5033 m; / YKDHC-1 / C / NCB / Prior review / Mar .to June 2008 / No / July to Novt.2008 / 5.405
4 / Central Heat Source Plant / 4×64 MW heat source plant / YKDHC-2 / C / NCB / Prior review / Mar. to June. 2008 / No / July to Oct.2008 / 4.936
A3 / Yingkou EDZ Heating
5 / Primary network; Secondary network; Substation; Booster pump station, for the new development area / Pre-insulated pipe DN 900-1,200 mm (primary network),19620m;
Pre-insulated pipe DN 200-900 mm (primary network), 41514 m; 19substations and 11 building level substations (service areas from 39,000 m2 to 260,000 m2), booster pump station / YKEHC-1 / C / NCB / Prior review / Mar. to June. 2008 / No / July to Oct. 2008 / 17.224
6 / Primary network; Substation; Booster pump station for the constructed area / Pre-insulated pipe DN 80-400 mm (primary network), 23452 m, the diameter and length will be identified in accordance with the planning; 47substations (service areas from 8,000 m2 to 296,200 m2) booster pump station / YKEHC-2 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 12.880
A4 / Bengang Heating
7 / Heat supply network of coking water / Directly buried polyurethane heat supply network (DN900-DN600, 2204 m) and installation / BGHC-1 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / May. to Oct.2009 / 1.913
Directly buried polyurethane heat supply network (DN400-DN450, 4664 m) and installation
8 / General drawing in plant; Civil works in plant / General drawing in plant :
1. New construct 2,480 m2 road surface
2. Recovery 1,809 m2 road surface
3. Recovery 1,809 m2 green land
4. Excavation 9,640 m3 soil
5. Structure 6,583 m2 building.
Civil works in plant:
1. Filtration pumping station: 423 m2
2. Water tank/pump station: 733 m2
3. Recycle pump/filter room: 702 m2
4. Mixing tanks: 10,935 m2
5. Steel bracket/concrete base: 1897 m2
6. Power distribution room
7.Out of plant: The equipment and installation of water pumps and electric equipment for the pumping house (648 m2) / BGHC-2 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 5.782
9 / Heat supply network of No.3 power plant
Heat supply network of slag washing water
Heat supply network in plant / Directly buried polyurethane heat supply network (DN1,000-DN450, 6,094 m) and installation
Directly buried polyurethane heat supply network (DN1,000-DN3,000, 6,476 m) and installation
Directly buried polyurethane heat supply network (DN1000-DN700, 24,450 m) and installation / BGHC-3 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 12.706
10 / Heat supply network of Qianjin branch and other branches / Directly buried polyurethane heat supply network (DN800-DN400, 22,234 m) and installation / BGHC-4 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 3.635
A5 / Haicheng Heating
11 / Primary and secondary network; substation / Pre-insulated pipe DN200-700 mm, 19,630 m; 26 substations12 building level substations (for 25,000-368,000 m2 heating area) / HCHC-1 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / May to Oct.2009 / 4.927
12 / Heat Source Plant / 3x58 MW heat source plant( / HCHC-2 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / May to Oct.2009 / 4.574
A6 / Liaoyang Gongchangling Heating
13 / Gongchangling District Heat Source Plant Primary Network & Substation / Pre- insulated pipe DN200-600 mm 29723 m; 19 substations, 2 relay stations 1intermediary substation, 28 building level substations (heating area: 97,000-367,000 m2)
Pre- insulated pipe DN250-350 mm 7840 m; 2 substations (heating area: 20,000-22,000 m3) / LYHC-1 / C / NCB / Prior review / Mar. to June 2008 / No / July to Oct. 2008 / 6.918
14 / Gongchangling District Heat Source Plant / :3 x 58 MW heat source plant / LYHC-2 / C / NCB / Post review / Mar. to June 2008 / No / July to Oct. 2008 / 3.493
A7 / Yangjiazhangzi Mining Area Heating
15 / Heat Source Plant; Primary and Secondary Pipelines; Substation / Pre-insulated pipe:DN150-DN500mm
5800 m; (1,443,500 m2 primary network and 1 million m2 secondary network); (38000-224100 m2 service area)
Pre-insulated pipe:DN200-DN500mm
6970 m; (1,443,500 m2 primary network and 1 million m2 secondary network); (68100-22700 m2 service area)and13 substations and 46 building level substations, / YZZHC-1 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 5.87
16 / Heat Source Plant / :3×29 MW heat source plant / YZZHC-2 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 2.438
A8 / YingkouCity Central Heating Expansion
17 / Primary Network, substations / Pre-insulated pipe DN1000 mm,22.6k m, 11.3 km pipe ditch , DN800mm,6.4k m, 3.2 km pipe ditchetc.;(50 to 250 thousand m2 service area) and one relay pumping station / YKHC-1 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / Apr. 2009 to Oct.2009 / 16.330
18 / Primary Network, substations / Pre-insulated pipe DN80-800 mm, 69.2k m, 34.6km pipe ditch etc.;83substations (50 to 250 thousand m2 service area) / YKHC-2 / C / NCB / Prior review / Mar. to Aug. 2009 / No / Sep.2009.to Oct.2010 / 19.285
A9 / BenxiCity Central Heating Phase II
19 / Primary network, substation / Pre-insulated pipes DN125-700mm10000m, 5 Km pipe ditch,
Pre-insulated pipes DN125-700mm9450m, 4.73Km pipe ditch, 14 substations ,well etc.; / BXHC-1 / C / NCB / Prior review / Mar. to June 2008 / No / July to Oct.2008 / 11.679
20 / Heat Source Plant / :2 heat source plant (1×58MW, 1x58MW ), / BXHC-2 / C / NCB / Post review / Mar. to June 2008 / No / July to Oct.2008 / 4.931
21 / Primary network, substation / Pre-insulated pipes DN125-700mm13236m, 7.62Km pipe ditch,31 substations 4 building level substations, well etc.; / BXHC-3 / C / NCB / Prior review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 6.654
22 / Heat Source Plant / 3 heat source plant (1×58MW, 2x58MW and 2×29MW), / BXHC-4 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 2.190
A10 / Benxi Nanfen Heating
23 / Heat Source Plant / 3×29 MW heat / BXNHC-1 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / May to Oct.2009 / 2.336
24 / Primary Network, Substation / Pre-insulated pipe DN150-450mm17,370 m; 11 substations 17 building level substations, (the heated areas are from 60,000 to 163,000 m2.) / BXNHC-2 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / Apr .to Oct. 2009 / 2.910
B. Gas Distribution Improvements
B1 / YingkouCity Gas Distribution Improvements
1 / Pipeline Rehab / i) rehabilitation and new construction of medium pressure A pipeline; ii) new construction of pressure regulation station; iii) rehabilitation of cross river pipeline; iv) rehabilitation of 30 valve well (medium pressure and new construction of 40 valve wells (low pressure) / YKGC-1 / C / NCB / Post review / Sep. 2008 to Jan. 2009 / No / Apr. to Nov. 2009 / 2.673
Procurement of Equipment for Substations and Small Heat Meters
A.CITY CENTRAL HEATING
A1 / Fushun Heating
1 / Supply & Installation of Chengdong and Gaoshan Substations / 36 Stations for Supply & installation building level substations / FSHG-1 / S+I / ICB / Prior review / Sep.2008 to Jan. 2009 / No / May. to Oct.2009 / 2.555
2 / Supply & installation of Park and Dongcheng Substations / 27 Stations for Supply & installation (. 20 building level subs/heat meters) / FSHG-2 / S+I / ICB / Prior review / Sep.2008 to Jan. 2009 / No / May to Oct.2009 / 1.925
A2 / Yingkou Dashiqiao Heating
3 / Substation Equipment and Installation / 43substation(0.0023-0.3537 million m2 heating area)
including 12 building level substations; heat exchanger, pump, water treatment, heat meter and installation electric and auto-control equipmentand installation. / YKDHG-1 / S+I / ICB / Prior review / Mar. to June 2008 / No / July.to Nov. 2008 / 3.777
A3 / Yingkou EDZ Heating
4 / Substation; Booster pump station; pilot area of building heat meter / 47substations (service areas from 8,000 m2 to 296,200 m2), heat exchangers, pumps, water treatment equipment, dirt separator, heat meter, electrical instrument, automatic control equipment and installation. / YKEHG-2 / S+I / ICB / Prior review / Sep. 2008 to Jan. 2009 / No / Apr. to Oct. 2009 / 8.718
5 / Substations; / 19substations and 11 building level substations (service areas from 39,000 m2 to 260,000 m2), heat exchangers, pumps, water treatment equipment, dirt separator, heat meter, electrical instrument, automatic control equipment and installation. / YKEHG-1 / S+I / ICB / Prior review / Mar. to June 2008 / No / July. to Oct. 2008 / 3.702
A4 / Haicheng Heating
6 / Substation / Supply and installation: 26 substations (25,000-368,000 m2 heating area);12 building level substations heat exchangers, pumps, water treatment devices, electric and auto-control equipment, etc. / HCHG-1 / S+I / ICB / Prior review / Sep. 2008to Jan. 2009 / No / May. to Oct. 2009 / 2.385
A5 / Liaoyang Gongchangling Heating
7 / Gongchangling District Substation / Supply and installation: 19 substations, 2 relay stations 1intermediary substation, 28building level substations (heating area 224,100-602,000 m2), pumps, water treatment devices, electric and auto-control equipment, etc / LYHG-1 / S+I / ICB / Prior review / Mar. to June 2008 / No / July. to Oct. 2008 / 3.773
A6 / Yangjiazhangzi Mining Area Heating
8 / Substations / Supply and installation:
13 substations and 46 building level substations, heat exchanger, pumps and water treatment device,
(38000 – 227000m2
Supply and installation: electric and auto-control equipment, etc / YZZHG-1 / S+I / ICB / Prior review / Sep.2008 to Mar. 2009 / No / May to Oct. 2009 / 1.244
A7 / YingkouCity Central Heating Expansion
9 / Substation / 83substations(20 -235 thousand m2 service area),building level substations heat exchanger, water pumps, water treatment, one relay pumping station electric and auto-control equipment, etc / YKHG-1 / S+I / ICB / Prior review / Aug. 2009 to Jan. 2010 / No / Apr. to Oct.2010 / 4.716
A8 / BenxiCity Central Heating Phase II
10 / Substations / 14 substations, heat exchangers , pumps, water treatment, and installation
electric and auto-control equipment, etc / BXHG-1 / S+I / ICB / Prior review / Mar. to July 2008 / No / Aug. to Nov.2008 / 2.222
11 / Substations / 31 substations, 4 building level substationsheat exchangers , pumps, water treatment, and installation electric and auto-control equipment, etc / BXHG-2 / S+I / ICB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 4.311
A9 / Benxi Nanfen Heating
12 / Substation / 11 substations(the service areas of them are from 60,000 to 1630,000 m2.),17 building level substations, heat exchangers, pumps, water treatment equipment, electrical instrument and installation electric and auto-control equipment, etc / BXNHG-1 / S+I / ICB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 1.045
B. Gas Distribution Improvements
B1 / YingkouCity Gas Distribution Improvements
1 / Data Collection and Monitoring System / Gas intelligent data collection and monitoring system (SCADA) / YKGG-1 / S+I / ICB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 0.648
2 / The through repair and construction of the storage / a20000 and 50000m3 storage tanks, b50000m3 storage tank newly built / YKGG-2 / S+I / ICB / Prior review / Sep. 2008 to Jan. 2009 / No / May to Oct. 2009 / 2.432
Procurement of Boilers and Related Equipment
A.CITY CENTRAL HEATING
A1 / Yingkou Dashiqiao Heating
1 / Central Heat Source Plant / installation 4×64 MW boilers, auxiliary equipment & electric and auto-control equipment / YKDHG-2 / S+I / ICB / Prior review / Mar. to July. 2008 / No / Aug.
to Nov. 2008 / 9.688
A2 / Haicheng Heating
2 / Heat Source Plant / Supply and installation: 3x58 MW boilers, auxiliary equipment, electric and auto-control equipment, etc / HCHG-2 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May. to Oct. 2009 / 6.819
A3 / Liaoyang Gongchangling Heating
3 / Gongchangling District Heat Source Plant / Supply and installation: 3x58 MW hot water boilers, auxiliary equipment, electrical and auto-control equipment, etc. / LYHG-2 / S+I / ICB / Prior review / Mar. to July. 2008 / No / Aug.
to Nov. 2008 / 6.367
A4 / Yangjiazhangzi Mining Area Heating
4 / Heat Source Plant / 3×29 MW hot water boilers, auxiliary equipment; electrical equipment for boilers
Auto control systerm for the network. / YZZHG-2 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May to Oct. 2009 / 4.364
A5 / YingkouCity Central Heating Expansion
5 / Heat Source Plant / Supply&Installation of electrical and auto-control Equipment for 1×58 MW and 4×29 MW (Two heating plants) Auto control systerm for the network. / YKHG-2 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May to Oct.2009 / 3.164
A6 / BenxiCity Central Heating Phase II
6 / Heat Source Plant / 1×58MW and 1×58MW hot water boilers and auxiliaries, electrical and auto-control equipment and installation / BXHG-3 / S+I / ICB / Prior review / Mar. to July 2008 / No / Aug. to Nov.2008 / 7.412
7 / Heat Source Plant / 2×58MW ,2×29MW and 1×58MW hot water boilers and auxiliaries, electrical and auto-control equipment and installation / BXHG-4 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May to Nov. 2009 / 9.975
A7 / Bengang Heating
8 / Heating equipment & installation in plant; No.3 power plant return water and slag washing water supply booster. Out of plant Pumping stations / In plant: 1.the relevant equipment and installation of cooling, hot water, filter water supply, circulating water pumps; 2.pumps of primary pumping station of No. 3 Power plant;
3. Various bridge-model cranes (5t, 2t); and heat supply network (DN1,000-700, 2,4450 m), compensator, etc.
Transformer (500 kVA), power distribution for various pumps, motors, cranes, lighting, instrument control and communication of slag washing plant and No.3 power plant primary station, etc. / BGHG-1 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May to Oct. 2009 / 3.100
Electric, meter control and telecom equipment & installation in plant
A8 / Benxi Nanfen Heating
9 / Heat Source Plant / 3×29 MW boilers and auxiliary equipment, electrical equipment auto control equipment and installation / BXNHG-2 / S+I / ICB / Prior review / Sep. 2008 to Feb. 2009 / No / May to Oct. 2009 / 4.174
Field vehicles
A.CITY CENTRAL HEATING
A1 / Liaoyang Gongchangling Heating
1 / Gongchangling District Heat Source Plant / Vehicles / LYHG-3 / S / NCB / Post review / Aug. to Dec. 2008 / No / Jan. 2009 / 0.150
A2 / Yangjiazhangzi Mining Area Heating
2 / Heat Source Plant / Vehicles / YZZHG-3 / S / NCB / Post review / July to Dec. 2009 / No / Jan. 2010 / 0.112
A3 / Benxi Nanfen Heating
3 / Heat Source Plant / Vehicles / BXNHG-3 / S / NCB / Post review / July to Dec. 2009 / No / Jan. 2010 / 0.111
A4 / Yingkou Dashiqiao Heating
4 / The Central and Nanlou Heat Source / Vehicles / YKDHG-4 / S / NCB / Post review / Aug. to Dec. 2008 / No / Jan. 2009 / 0.145
A5 / Haicheng Heating
5 / Heat Source Plant / Vehicles / HCHG-3 / S / NCB / Post review / July to Dec. 2009 / No / Jan. 2010 / 0.116

Note: ICB — International Competitive Bidding; NCB — National Competitive Bidding; S — Supply only; S+I — Supply and Installation

1

III. Selection of Consultants

1. Threshold for prior review

Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Selection Method / Prior Review Threshold / Comments
1. / Competitive Methods (Firms) / US$200,000
2. / Single Source (Firms) / all

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.