Effective: Sep-07
Petroleum Development Oman L.L.C.
UNRESTRICTED Document ID: PR-1001x
Sep-07 Filing Key: Business Control
Engineering and Operations
Operations Variance and Change Management
User Note:The requirements of this document are mandatory. Non-compliance shall only be authorised by the Document Owner or his Delegate through STEP-OUT approval.
A controlled copy of the current version of this document is on PDO's EDMS. Before making reference to this document, it is the user's responsibility to ensure that any hard copy, or electronic copy, is current. For assistance, contact the Document Custodian or the Document Controller.
Users are encouraged to participate in the ongoing improvement of this document by providing constructive feedback.
Please familiarise yourself with the
Document Security Classification Definitions
They also apply to this Document!
This page was intentionally left blank
i Document Authorisation
Authorised For Issue – September 2007
ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of all revisions prior to these are held on file by the issuing department.
Revision No. / Date / Author / Scope / RemarksRev 2.0 / Sep-07 / UOP6 / Reformat, Review and Revision
Sep-01 / UOP1 / Review and Revalidate
Rev 1.0 / Sep-98 / UOP1 / Rewritten to new format. This document deals with the generic procedure to instigate change. All specific variance and change control procedures are addressed as individual procedures.
iii Related Business Processes
Code / Business Process (EPBM 4.0)EP.71.01 / Plan and Schedule Production Volumes and Capacities
iv Related Corporate Management Frame Work (CMF) Documents
The related CMF Documents can be retrieved from the CMF Business Control Portal.
CP-115 / Operate Surface Product Flow Assets CoPCP-185 / CoP for Technical Integrity Management
PR-1001a / Facilities Change Proposal Procedure
PR-1001b / Trip/Alarm/SCADA Settings Change Procedure
PR-1001c / Temporary Override of Safeguarding Procedure
PR-1001e / Operations Procedure Temporary Variance
TABLE OF CONTENTS
1 Introduction 6
1.1 Background 6
1.2 Purpose 6
1.3 Distribution / Target Audience 6
1.4 Structure of this Document 6
1.5 Roles and Responsibilities 6
1.6 Definitions and Abbreviations 7
1.6.1 General 7
1.6.2 Abbreviations 7
1.7 Changes to the Document 7
1.8 Step-out Approval 7
2 Operations Variance and Change Management Procedure 8
2.1 Scope 8
2.2 General Points to Consider 8
2.3 Operations Variance and Change Management Process 9
Appendix A – User Feedback Form 11
Introduction
Background
The Corporate Management Framework is the highest level document in PDO’s Management System, and it applies to all PDO activities.It describes the framework that integrates all of PDO’s activities.The building blocks of the framework are:
Business Direction / Business ResultsBusiness Management / Review and Appraisal
1 Introduction
1.1 Background
Operations Variance and Change Control encompasses a suite of procedures designed to address and manage variances and change management carried out by Production Operations. The suite of procedures comprises:
· Facilities Change Proposal (PR-1001a)
· Trip/Alarm/SCADA Settings Change (PR-1001b)
· Temporary Override of Safeguarding Systems (PR-1001c)
· Operations Procedure Temporary Variance (PR-1001e)
The suite of procedures listed is stand-alone and address the varying requirements of Operations. The procedures provide a structured approach required for the safe and effective implementation of any required changes.
The decision to introduce any change, be it procedural or to plant and process systems shall only be made after due consideration of the consequences, review of the technical, commercial or safety aspects, and shall always be formally approved by the authorised person prior to execution or implementation.
1.2 Purpose
The purpose of this procedure is to provide Operations personnel with a ‘high level’ procedure for executing changes within the Operations environment. Attention shall be drawn to areas of the procedure that are considered mandatory.
1.3 Distribution / Target Audience
This procedure targets and should be distributed and brought to the attention of the Operations and Engineering staff.
All supervisory staff shall be responsible for ensuring that this procedure is strictly adhered to, and thoroughly understood by their team members.
1.4 Structure of this Document
The procedure is laid out to provide a logical reference for personnel who require guidance on variance and change control. Where applicable, flowcharts shall be used for clarity and understanding.
1.5 Roles and Responsibilities
Production Coordinator / · Authorised to permit all changes to Operations Procedures and Assets to be initiated.· Responsible for adhering to the scope of variances and their validity
· Monitor validity of variances.
· Responsible for asset integrity and team members’ awareness.
· Disseminate information once approval is received, and when all is back to normal.
Delivery Team Leader / · Review and approve variance requests.
· Authorised to accept or reject change applications
· Responsible for organisation HSE aspects.
Asset Manager / · Review and authorise the variance request.
· Authorised to allow variation /change to take place
· Full responsibility against Operations Procedure.
Roles and responsibilities are more clearly defined in the respective Variance and Change Management procedures.
1.6 Definitions and Abbreviations
1.6.1 General
For the purposes of this Procedure the following definitions shall be used:
Authority / The right to make, on behalf of the Company, decisions which commit the Company to a course of action incurring expenditure, deployment of resources and/or release of information.Shall / The word ‘shall’ is to be understood as mandatory
Should / The word ‘should’ is to be understood as strongly recommended.
May / The word ‘may’ is to be understood as indicating a possible course of action.
1.6.2 Abbreviations
The following abbreviations are used in this Procedure.
CMF / Corporate Management FrameworkCFDH / Corporate Functional Discipline Head
PDO / Petroleum Development Oman
1.7 Changes to the Document
Responsibility for the upkeep of the Document shall be with Corporate Functional Discipline Head (CFDH) for Engineering and Operations UOP, the Owner. Changes to this document shall only be authorised and approved by the Owner.
Users of the Document who identify inaccuracy or ambiguity can notify the Custodian or his/her delegate and request changes be initiated. The Requests shall be forwarded to the Custodian using the “User Feedback Page” provided in this Document.
The Document Owner and the Document Custodian should ensure review and re-verification of this procedure every 3 years.
1.8 Step-out Approval
Not applicable to this procedure.
2 Operations Variance and Change Management Procedure
2.1 Scope
The Operations Variance and Change Management process shall be used to define the nature of the variance / change and to identify the specific process that shall be implemented to manage that variance / change.
For clarity the processes are covered under separate procedures.
PR-1001a - Facilities Change Proposal (previously SI-18)
Requests for permanent changes to process plant & operating practices must be made using the Facility Change Proposal (FCP) procedure.
PR-1001b - Trip and Alarm Setting Change (previously SI-13 and SI-23)
Requests for changes to process alarms & trips must be made using the appropriate form approved by Production Coordinator and authorised by the relevant specialist CFDH.
PR-1001c - Temporary Override of Instrument Safeguarding Systems (previously SI-25)
These are temporary changes, which must be applied for via the appropriate forms, approved by the Production Coordinator and authorised by the relevant specialist CFDH.
PR-1001d - Integrated Production Plan Variance (previously SI-14)
Withdrawn
PR-1001e - Operations Procedure Temporary Variance (previously SI-14)
An “Operations Procedure Temporary Variance” shall be initiated when an intended activity cannot be effectively or safely performed within the existing Operations ‘envelopes’ or a Production Operations Procedure. The requested variance shall be approved by the Delivery team Leader and authorised by the Asset Manager.
NOTE: Authorisation to allow a variance from an established and documented Well Services Procedure is NOT covered in this document. This rests with the CDFP for Well Services and shall be formally obtained prior to implementing a variance within their respective procedures.
2.2 General Points to Consider
a) / The proposed change including supporting documentation shall be forwarded to the ‘discipline / line supervisor’[1] for screening. The discipline / line supervisor shall decide whether the proposal is realistic and if all required documentation to support the request has been supplied.b) / Rejected proposals shall be returned to the originator. Screened and accepted proposals shall be forwarded for endorsement
c) / In all cases where a change to an established system or procedure is required, a correctly completed proposal shall be submitted by the originator for approval and authorisation by line management.
d) / Where ever possible, the originator should attach supporting documents / drawings or sketches to the respective proposal.
c) / It is mandatory that the correct line authority approves all change request forms. If technical specialist authorisation is required, this must also be obtained from the CFDH before implementation.
d) / All change requests shall be initially reviewed by the Production Coordinator and then screened by the Delivery Team Leader where, appropriate, who will either accept or reject the proposed variance / change.
e) / When a change to a system or procedure take place, the nature of the change shall be disseminated to the relevant Operation personnel by the Production Coordinator.
f) / The Production Coordinator shall check on the status of change requests and monitor their status / validity /progress on a monthly basis.
g) / Individual discipline supervisors shall keep a log of change requests and copies of the proposals on site. This shall be auditable
2.3 Operations Variance and Change Management Process
1. / The proposal for a Variance or Change should be reviewed by the Line Supervisor or the Production Coordinator who shall advise the ‘originator’ on the correct procedure to follow.2. / If the proposal required a change to a system, equipment, plant design, operating envelope etc, then it shall be considered as a ‘facilities change’ and be actioned in accordance with PR-1001a. Management of the change proposal shall be undertaken by the Field Change Proposal team.
If the proposed Variance or Change does not meet the criteria it should be rejected or redefined.
3. / If the proposal requires that the setpoint of trip, alarm or SCADA instrumentation be changed then it shall be actioned in accordance with PR-1001b. Management of the change proposal shall be undertaken by the discipline supervisor and the functional support group.
4 / If the proposal requires a temporary variance for the overriding of Safeguarding Systems then it shall be actioned in accordance with PR-1001c. Management of the variance shall be undertaken by the discipline supervisor and reviewed by process and discipline engineers.
5. / If the proposal is a request for a variance to a Mandatory Controlled Procedure then it shall be actioned in accordance with PR-1001c. Management of the variance shall be undertaken by the Production Coordinator and must be authorised by the Asset Manager.
6. / If the proposed variance or change is not addressed by any of the above then it does not require to be covered under this procedure.
Appendix A – User Feedback Form
/ PR-1001x – OPERATIONS VARIANCE AND CHANGE MANAGEMENT USER FEEDBACK PAGEAny user who identifies an inaccuracy, error or ambiguity is requested to notify the custodian so that appropriate action can be taken. The user is requested to return this page fully completed, indicating precisely the amendment(s) recommended.
Name:
Ref ID / Date:
Page Ref: / Brief Description of Change Required and Reasons
To: / UOP1
Custodian of Document / Date:
Page 4 / Operations Variance and Change Management / Printed 26/09/07
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
[1] The Discipline / Line Supervisors shall be sponsors for the FCP