SONEX LOG - PHASE FIVE

FITTING AND ASSEMBLY OF FINAL COMPONENTS

December 20, 2001

Mounted engine on the engine mount.

Date completed 12-20-01

Time to complete 4 hrs .

Total time to date 880 hrs.

December 26, 2001

Installed the Aero-Carb on the engine.

Date completed 12-26-01

Time to complete 1 hr.

Total time to date 881 hrs.

January 3, 2002

Constructed bracket for Throttle and mixture controls. Installed and connected the

Throttle and Mixture controls.

Date completed 1-3-02

Time to complete 5 hrs.

Total time to date 886 hrs.

January 9, 2002

Installed Carb. Heat System & Controls.

Date completed 1-9-02

Time to complete 3 hrs.

Total time to date 889 hrs.

January 18, 2002

Completed final layout for the instrument panel. Cut out all required openings for gages, switches and fuses.

Date completed 1-23-02

Time to complete 8 hrs.

Total time to date 897 hrs.

January 26, 2002

Installed all gages. Completed all wiring for engine and instruments as required.

Date completed 2-20-02

Time to complete 18 hrs.

Total time to date 915 hrs.

February 23, 2002

Installed gas tank and glare shield, final riveted in place.

Date completed 2-28-02

Time to complete 5 hrs.

Total time to date 920 hrs.

May 15, 2002

Fit and installed Cowling and Ram Air Ducts per SNX-P13.

Date completed 7-14-02

Time to complete 60 hrs.

Total time to date 980 hrs.

July 18,2002

Installed New Rudder Pedals per Sonex Service Bulletin SNX-SB-001.

Date completed 7-18-02

Time to complete 3 hrs.

Total time to date 983 hrs.

July 25,2002

Installed Windshields per Sonex SNX-D01 7 D02.

Date completed 8-15-02

Time to complete 15 hrs.

Total time to date 998 hrs.

+

August 26, 2002

Put the wings on the aircraft and final fit and riveted the wing walk/ doublers. Also installed the

Flab stop brackets and connected and adjusted the flaps and aileron controls.

Date completed 9-18-02

Time to complete 12 hrs.

Total time to date 1010 hrs.

September 19,2002

Installed the seat belts.

Date completed 9-19-02

Time to complete 3 hrs.

Total time to date 1013 hrs.

September 24, 2002

Installed the canopy.

Date completed 10-15-02

Time to complete 18 hrs.

Total time to date 1031 hrs.

October 21, 2002

Made and installed Luggage Compartment Sling.

Date completed 10-22-02

Time to complete 3 hrs.

Total time to date 1034 hrs.

October 25, 2002

Constructed a Hold Up Bracket to prop the canopy up while taxing.

Date completed 10-25-02

Time to complete 3 hrs.

Total time to date 1037 hrs.

October 30,2002

Installed and finished Wheel Pants & Gear Leg Fairings.

Date completed 11-27-02

Time to complete 25 hrs.

Total time to date 1062 hrs.