SONEX LOG - PHASE FIVE
FITTING AND ASSEMBLY OF FINAL COMPONENTS
December 20, 2001
Mounted engine on the engine mount.
Date completed 12-20-01
Time to complete 4 hrs .
Total time to date 880 hrs.
December 26, 2001
Installed the Aero-Carb on the engine.
Date completed 12-26-01
Time to complete 1 hr.
Total time to date 881 hrs.
January 3, 2002
Constructed bracket for Throttle and mixture controls. Installed and connected the
Throttle and Mixture controls.
Date completed 1-3-02
Time to complete 5 hrs.
Total time to date 886 hrs.
January 9, 2002
Installed Carb. Heat System & Controls.
Date completed 1-9-02
Time to complete 3 hrs.
Total time to date 889 hrs.
January 18, 2002
Completed final layout for the instrument panel. Cut out all required openings for gages, switches and fuses.
Date completed 1-23-02
Time to complete 8 hrs.
Total time to date 897 hrs.
January 26, 2002
Installed all gages. Completed all wiring for engine and instruments as required.
Date completed 2-20-02
Time to complete 18 hrs.
Total time to date 915 hrs.
February 23, 2002
Installed gas tank and glare shield, final riveted in place.
Date completed 2-28-02
Time to complete 5 hrs.
Total time to date 920 hrs.
May 15, 2002
Fit and installed Cowling and Ram Air Ducts per SNX-P13.
Date completed 7-14-02
Time to complete 60 hrs.
Total time to date 980 hrs.
July 18,2002
Installed New Rudder Pedals per Sonex Service Bulletin SNX-SB-001.
Date completed 7-18-02
Time to complete 3 hrs.
Total time to date 983 hrs.
July 25,2002
Installed Windshields per Sonex SNX-D01 7 D02.
Date completed 8-15-02
Time to complete 15 hrs.
Total time to date 998 hrs.
+
August 26, 2002
Put the wings on the aircraft and final fit and riveted the wing walk/ doublers. Also installed the
Flab stop brackets and connected and adjusted the flaps and aileron controls.
Date completed 9-18-02
Time to complete 12 hrs.
Total time to date 1010 hrs.
September 19,2002
Installed the seat belts.
Date completed 9-19-02
Time to complete 3 hrs.
Total time to date 1013 hrs.
September 24, 2002
Installed the canopy.
Date completed 10-15-02
Time to complete 18 hrs.
Total time to date 1031 hrs.
October 21, 2002
Made and installed Luggage Compartment Sling.
Date completed 10-22-02
Time to complete 3 hrs.
Total time to date 1034 hrs.
October 25, 2002
Constructed a Hold Up Bracket to prop the canopy up while taxing.
Date completed 10-25-02
Time to complete 3 hrs.
Total time to date 1037 hrs.
October 30,2002
Installed and finished Wheel Pants & Gear Leg Fairings.
Date completed 11-27-02
Time to complete 25 hrs.
Total time to date 1062 hrs.