Fleet Distribution News Bulletin FDNB – 1206

Friday May 20, 2016

SCHEDULING HELPFUL HINTS

Fleet orders are prioritized based on a two-digit alpha-numeric priority code indicating month and week an order needs to be built. Numeric priority codes (including 99) are not valid for Fleet. See the Fleet Priority Code Calendar link below for valid priority codes. Please be aware of the following:

·  First available priority codes are calculated weekly based on current order bank, available allocation, controlled commodities, and plant downtime. It is very important to review the Fleet DNB weekly as first available priority codes can sometimes change drastically if, for example, a large influx of orders is received.

·  Fleet receives a pre-determined amount of allocation (production slots) each month for weekly scheduling. Once the amount of orders prioritized for that week/month exceeds the available allocation, the first available priority code is moved out to the next week/month.

·  Orders are selected for scheduling based on priority code first, then by order receipt date. Despite how long an order has been in the unscheduled order bank, if the plant is not yet filling the production week associated with the requested priority code, the order will remain unscheduled.

·  As a general rule of thumb, production dates are at least one month out from order receipt date.

·  Every effort is made to accurately estimate the lead times, and to reflect longer lead times of specific commodities. In the absence of adjusted lead times for commodities, please use the high, medium, or low risk rating as a guide.

Please review specific vehicle line information below to assist in ordering vehicles for timely delivery. Every attempt will be made to honor requested Fleet priority code. Due to unforeseen circumstances such as plant downtime or commodity issues, this may not be possible. The information and estimated timing indicated below are correct at time of publication. Availability and timing are subject to change without notice. Acceptance of an order by Ford Motor Company does not constitute a commitment to build or a guaranteed delivery date.

DESIRED PRODUCTION DATE PRIORITY CODES PLACE ORDERS BY

June F1, F2, F3, F4, F5 May 1

July G1, G2, G3, G4 June 1

August H1, H2, H3, H4, H5 July

·  CURRENTLY SCHEDULING FOR JUNE PRODUCTION

·  SCHEDULING FOR JULY PRODUCTION BEGINS 6/15/16

Week 5 Priority Codes

Effective mid-April 2010, the system will automatically change Week 5 priority codes to Week 4 whenever a month does not contain a full fifth week. For example, in the month of May, any unscheduled orders placed with "E5" will be changed to "E4".

The 2015 Fleet Priority Code Calendar can be accessed at:

https://www.fleet.ford.com/OrderingCenter/ordering_and_production/priority_code.asp

Priority Codes / Estimated
For New Orders / Currently / Lead Time
First / Last / Filling / Down / (Order to / Possible
Vehicle Line / Available / Available / Week1 / Weeks / Delivery)2 / Scheduling Delays3

2016 MODEL YEAR

Super Duty / B/O / B/O / B/O / B/O / B/O
Edge / G3 / K3 / F4 – 6/20 / 7/4 / 12-14 weeks / Sync Gen III – Trend, Titanium, Sport 9/6/16
Flex / G2 / L1 / F4 – 6/20 / 5/23, 5/30, 7/4 / 12-14 weeks
MKT / H1 / L1 / F4 – 6/20 / 5/23, 5/30, 7/4 / 14-16 weeks
MKX / F4 / K3 / F4 – 6/20 / 7/4 / 6-8 weeks
Fiesta / H4 / L4 / G4 - 7/25 / 6/20, 6/27, 7/4, 8/1, 9/19, 12/26 / 16-18 weeks
Transit / G4 / G4 / G4 – 7/25 / 7/4, 7/11 / 14-16 weeks / High delay (incremental 4-6 wks):
Seats 15 Pass Wagon w/ X2Z, X2Y, X2C, X2X
Low delay - Transportation (incremental 2 weeks):
sAll MR & HR units
Focus / G4 / L3 / G4 - 7/25 / 7/4, 7/11, 8/29, 10/3, 10/10, 10/24, 10/31, 12/26 / 12-14 weeks
CMAX / H3 / L3 / G4 - 7/25 / 5/2, 7/4, 7/11, 8/29, 10/3, 10/10, 10/24, 10/31, 12/26 / 16-18 weeks
F-150 / F4 / K3 / F4 – 6/20 / DCP 7/4, 7/11
KCAP 7/4, 7/11 / 8-10 weeks / Crew Cab (W1C/W1E) 4x2/4x4 with 6.5’ box and 5.0L/3.5L GTDI (99F/99G) WITH Heavy Payload Pkg (627) – Late 2Q 2016
Taurus Non-Police
Taurus Police / G2
G2 / L2
L2 / F4 – 6/20
F4 – 6/20 / 7/4 / 12-14 weeks
12-14 weeks / 2.0L Engine (999) - HIGH

2017 MODEL YEAR

Econoline / G2 / L4 / F4 – 6/20 / 6/27, 7/4 / 8-10 weeks / E350 138” WB with the 4.56 Axle Ratio – 8/1/16
F-150 / J3 / TBD / J2– 9/12 / TBD / USOB opens 7/18/16
Motorhome / G2 / TBD / F4 – 6/20 / 7/4, 8/1 / 10-12 weeks / 22K GVWR 178” WB for Parcel Delivery Customers – 6/6/16
Medium Duty Truck / G4 / TBD / G4 – 7/25 / 6/27, 7/4 / 12-14 weeks / 10.25” X 3.61” X .375” 120K PSI 16.98 SM/2.03M RBM frame rail – 10/3/16
Transit / H1 / TBD / H1 – 8/1 / 8/22, 9/12, 10/3 / TBD / High delay (incremental 4-6 wks):
Seats 15 Pass Wagon w/ X2Z, X2Y, X2C, X2X
Low delay - Transportation (incremental 2 weeks):
sAll MR & HR units
Transit Connect / G4 / B4 / G4 – 7/25 / 22-24 weeks
Fusion / F4 / TBD / F4- 6/20 / 7/25, 8/1, 9/12, 10/10, 12/26 / 8-10 weeks / SE Appearance pkg 20.N MP2 5/31/2016
Fusion Hybrid / F4 / TBD / F4- 6/20 / 7/25, 8/1, 9/12, 10/10, 12/26 / 8-10 weeks
MKZ / G3 / TBD / F4- 6/20 / 5/18, 5/2, 7/25, 8/1, 9/12, 10/10, 12/26 / 12-14 weeks
Escape / G4 / TBD / F4 – 6/20 / 7/4 / 12-14 weeks
MKC / F4 / TBD / F4 – 6/20 / 7/4 / 8-10 weeks
Expedition / G3 / TBD / F4- 6/20 / 7/4 / 12-14 weeks
Navigator / G3 / TBD / F4- 6/20 / 7/4 / 12-14 weeks
Explorer Non-Police
Explorer Police / G3
G3 / TBD / G2 – 7/11
G2 – 7/11 / 7/4 / 12-14 weeks
12-14 weeks
Mustang / F5 / TBD / F5 - 6/27 / 7/4, 8/15 / 8-10 weeks
Continental / H2 / TBD / G2 – 7/11 / 7/4, 8/15 / TBD
Super Duty
350/450/550 Chassis Cabs / G4 / TBD / G2 – 7/11 / 7/4 / 12-14 weeks
16-18 weeks / High Delay
Edge / L1 / TBD / K4 – 10/24 / TBD
Flex / L3 / TBD / L2 – 10/7 / TBD
MKT / L3 / TBD / L2 – 10/7 / TBD
MKX / L1 / TBD / L2 – 10/7 / TBD


1This is the first available production week at the plant (not to be confused with "First Available Priority Code"). The "First

Available Priority Code" is often beyond the first available production week at the plant due to incoming orders exceeding weekly/monthly allocation. This serves as a point of reference to help determine when order(s) may be submitted to the plant.

2 Every effort is made to accurately estimate the lead times, and reflect longer lead times of specific commodities. In the absence of adjusted lead times for commodities, please use the high, medium, or low risk rating as a guide.

3High-risk commodity has a lower probability of scheduling. Low-risk commodity has a higher probability of scheduling. Refer also to the Product Information section in the Fleet DNB for current material hold information.

3